Question

In: Finance

 You have been assigned the task of evaluating two mutually exclusive projects with the following projected...

 You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows:

Year

Project A

Cash Flow

Project B

Cash Flow

0

​$(102,000​)

​$(102,000)

1

32,000

           00

2

   32,000

           00

3

   32,000

           00

4

   32,000

           00

5

   32,000

  230, 000

If the appropriate discount rate on these projects is 88 ​percent, which would be chosen and​ why?

The NPV of Project A is

Solutions

Expert Solution

Net Present Value – PROJECT A

Year

Annual Cash Flow ($)

Present Value factor at 8%

Present Value of Cash Flow ($)

1

32,000

0.925926

29,629.63

2

32,000

0.857339

27,434.84

3

32,000

0.793832

25,402.63

4

32,000

0.735030

23,520.96

5

32,000

0.680583

21,778.66

TOTAL

1,27,766.72

Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment

= $1,27,766.72 - $102,000

= $25,766.72

“Net Present Value – PROJECT A = $25,766.72”

Net Present Value – PROJECT B

Year

Annual Cash Flow ($)

Present Value factor at 8%

Present Value of Cash Flow ($)

1

0

0.925926

0

2

0

0.857339

0

3

0

0.793832

0

4

0

0.735030

0

5

2,30,000

0.680583

1,56,534.14

TOTAL

1,56,534.14

Net Present Value (NPV) = Present Value of annual cash inflows – Initial Investment

= $156,534.14 - $102,000

= $54,534.14

“Net Present Value – PROJECT B = $54,534.14”

DECISION

The PROJECT B should be selected, since it has the highest Net Present Value (NPV) of $54,534.14 as compared to the NPV of PROJECT A”

NOTE    

The Formula for calculating the Present Value Factor is [1/(1 + r)n], Where “r” is the Discount/Interest Rate and “n” is the number of years.


Related Solutions

You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: Year Project A Cash Flow Project B Cash Flow 0 ​$(110,000​) ​$(110,000​) 1    40,000            0 2    40,000            0 3    40,000            0 4    40,000            0 5    40,000   240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? The NPV of Project A is ​$_____. The NPV of Project A is ​$_____. Which would be chosen...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 ------------- -100,000 ---------------   -100,000 1 --------------- 33,000 --------------- 0 2 --------------- 33,000 --------------- 0 3 --------------- 33,000 --------------- 0 4 --------------- 33,000 --------------- 0 5 --------------- 33,000 --------------- 210,000 If the appropriate discount rate on these projects is 12 percent, which would be chosen and why? 1. What is the NPV of...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected...
You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR      PROJECT A CASH FLOW                 PROJECT B CASH FLOW    0          -110,000                                               -110,000    1          30,000                                                   0    2          30,000                                                   0    3          30,000                                                   0    4          30,000                                                   0    5          30,000                                                   210,000 If the appropriate discount rate on these projects is 9 ​percent, which would be chosen and​ why? What is the NPV...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: If the appropriate discount rate on these projects is 11 ​percent, which would be chosen and​ why? What is the NPV of project​ A? ​$ nothing ​ (Round to the nearest​ cent.) What is the NPV of project​ B? ​$ ​(Round to the nearest​ cent.) Which project would be chosen and​ why? ​(Select the best choice​.) A....
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR PROJECT A CASH FLOW PROJECT B CASH FLOW    0 −​$110,000 −​$110,000    1        30,000               0    2        30,000               0    3        30,000               0    4        30,000               0    5        30,000      220,000 ​(Click on the icon located on the​ top-right corner of the data table above in order to copy its contents into a spreadsheet.​) If the appropriate discount rate on these...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive...
​(Mutually exclusive projects and NPV​) You have been assigned the task of evaluating two mutually exclusive projects with the following projected cash​ flows: YEAR   PROJECT A CASH FLOW   PROJECT B CASH FLOW 0 -105,000 -105,000 1 40,000 0 2 40,000 0 3 40,000 0 4 40,000 0 5 40,000 240,000 If the appropriate discount rate on these projects is 8 ​percent, which would be chosen and​ why? What is the NPV of project​ A? What is the NPV of project...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows: Year Project A Project B 0 ($100,000) ($100,000) 1 39,500 0 2 39,500 0 3 39,500 133,000 Based only on the information given, which of the two projects would be preferred, and why? Project A, because it has an even cash inflow stream. Project B, because it has a higher IRR. Indifferent, because the projects have equal IRRs. Include both in the capital...
Two projects being considered by a firm are mutually exclusive and have the following projected cash...
Two projects being considered by a firm are mutually exclusive and have the following projected cash flows: Project A Project B Year Cash Flow Cash Flow Proj A Project B 0 -$300,000 -$300,000 1 145,500 $150,000 2 145,500 -$ 40,000 3 145,500 $370,000 The firm’s cost of capital is 10 percent. Based only on the information given, What are the NPV for Project A and B? Which project do you choose based on the NPV? What are the payback periods...
You are evaluating two mutually exclusive projects. The cash flows for each are:
You are evaluating two mutually exclusive projects.  The cash flows for each are: Project A                      Project B             Year 0               ($60,000)                      ($85,000)             Year 1               $20,000                        $22,000             Year 2               $35,000                        $25,000             Year 3               $20,000                        $30,000             Year 4               $25,000                        $25,000             Year 5                                                   $15,000             Year 6                                                   $10,000             Year 7                                                   $10,000             Year 8                                                   $10,000 Assume that, if needed, each project is repeatable with no change in cash flows.  Your cost of capital is 13%. Using the replacement chain approach, which project would you chose to...
Two mutually exclusive projects are being considered which have the following projected cash flows:                          &nbs
Two mutually exclusive projects are being considered which have the following projected cash flows:                                 Year                       Project A               Project B                                    0                           ($50,000)              ($50,000)                                    1                           $15,625                                $         0                                    2                           $16,000                                $         0                                    3                           $15,000                                $         0                                    4                           $16,000                                $         0                                    5                           $15,500                                $99,500 a. Calculate the NPV for each of these projects using a 10% rate of return. Also, indicate which project should be chosen based on the NPV...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT