In: Accounting
Problem 18-10
On March 1, 2017, Bridgeport Construction Company contracted to
construct a factory building for Fabrik Manufacturing Inc. for a
total contract price of $8,340,000. The building was completed by
October 31, 2019. The annual contract costs incurred, estimated
costs to complete the contract, and accumulated billings to Fabrik
for 2017, 2018, and 2019 are given below:
2017 |
2018 |
2019 |
||||
Contract costs incurred during the year | $2,811,600 | $2,152,400 | $2,336,000 | |||
Estimated costs to complete the contract at 12/31 | 3,578,400 | 2,336,000 | –0– | |||
Billings to Fabrik during the year | 3,210,000 | 3,470,000 | 1,660,000 |
(a) Using the percentage-of-completion method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.)
(b) Using the completed-contract method, prepare schedules to compute the profit or loss to be recognized as a result of this contract for the years ended December 31, 2017, 2018, and 2019. (Ignore income taxes.)
1 | |||
2017 | Costs to date at December 31, 2017 | 2,811,600 | |
Estimated costs to complete | 3,578,400 | ||
Estimated total costs | 6,390,000 | ||
Percent
complete 2811600/6,390,000 |
44% | ||
Revenue
recognized 8340000*44% |
3,669,600 | ||
Costs incurred | 2,811,600 | ||
Profit recognized in 2017 | 858,000 | ||
2018 | Costs to date at December 31, 2018 | 4,964,000 | |
Estimated costs to complete | 2,336,000 | ||
Estimated total costs | 7,300,000 | ||
Contract price | (8,340,000) | ||
Total loss | (1,040,000) | ||
Plus gross profit recognized in 2017 | 858,000 | ||
Loss recognized in 2018 | (182,000) | ||
2019 | Costs to
date at December 31, 2019 2336000+2811600+2152400 |
7,300,000 | |
Estimated costs to complete | - | ||
Contract price | (8,340,000) | ||
Total loss | (1,040,000) | ||
Total loss | (1,040,000) | ||
Less: Loss recognized in 2018 | (182,000) | ||
Gross profit recognized in 2017 | 858,000 | 676,000 | |
Loss recognized in 2019 | (364,000) | ||
b | |||
2017 | No profit or loss is recognized in 2017. | ||
2018 | Contract price | 8,340,000 | |
Estimated costs | 5,914,400 | ||
Profit recognized | 2,425,600 | ||
2019 | Contract price | 8,340,000 | |
Cost incurred | -7,300,000 | ||
Total Profit | 1,040,000 | ||
Less: Profit recognized in 2018 | 2,425,600 | ||
Loss recognized | (1,385,600) |