Question

In: Accounting

Sage Landscaping began construction of a new plant on December 1, 2020. On this date, the...

Sage Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $138,000 in cash. In addition, it paid $2,160 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials.

Architectural plans were also formalized on December 1, 2020, when the architect was paid $32,400. The necessary building permits costing $3,360 were obtained from the city and paid for on December 1 as well. The excavation work began during the first week in December with payments made to the contractor in 2021 as follows.

Date of Payment Amount of Payment
March 1 $254,400
May 1 336,000
July 1 61,200


The building was completed on July 1, 2021.

To finance construction of this plant, Sage borrowed $609,600 from the bank on December 1, 2020. Sage had no other borrowings. The $609,600 was a 10-year loan bearing interest at 10%.

Compute the balance in each of the following accounts at December 31, 2020, and December 31, 2021. (Round answers to 0 decimal places, e.g. 5,275.)

December 31, 2020 December 31, 2021
(a) Balance in Land Account
(b) Balance in Building
(c) Balance in Interest Expense

Solutions

Expert Solution

Please give positive ratings.................... Your ratings will be helpful for me. If you have any query regarding this solution please comment below. I will be grateful to help you. Thank you!


Related Solutions

Crane Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Crane Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $145,200 in cash. In addition, it paid $2,400 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $720 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $31,200. The necessary...
Grouper Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Grouper Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $146,400 in cash. In addition, it paid $2,880 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $36,000. The necessary...
Based on Problem 10-6 Indigo Landscaping began construction of a new plant on December 1, 2020....
Based on Problem 10-6 Indigo Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $147,600 in cash. In addition, it paid $3,120 in surveying costs and $4,080 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,120, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was...
Pronghorn Landscaping Corp. began constructing a new plant on December 1, 2017. On this date, the...
Pronghorn Landscaping Corp. began constructing a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $183,780 cash. In addition, it paid $1,780 in surveying costs and $3,570 for title transfer fees. An old dwelling on the premises was immediately demolished at a cost of $2,750, with $990 being received from the sale of materials. Architectural plans were also formalized on December 1, 2017, when the architect was paid $29,960. The necessary building...
a) On January 1, Blair began construction of a new plant. On this date, the company...
a) On January 1, Blair began construction of a new plant. On this date, the company purchased a parcel of land for $200,000 in cash. In addition, it paid $3,000 in surveying costs and $1,000 for the title insurance policy. An old dwelling on the premises was demolished at a cost of $5,000, with $2,000 being received from the sale of materials. Architectural plans were also formalized on January 1, when the architect was paid $40,000. The necessary building permits...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 54 October 1, 2020 22 February 1, 2021 30 April 1, 2021 21 September 1, 2021 20 October 1, 2021 6 On July 1, 2020, Crocus obtained a $70 million construction loan with a 6% interest rate. The loan was outstanding through the end of...
On January 1, 2015, the Crocus Company began construction of a new manufacturing plant. The plant...
On January 1, 2015, the Crocus Company began construction of a new manufacturing plant. The plant was completed on December 31, 2016. Expenditures on the project were as follows (in $ millions): January 1, 2015 $1 July 1, 2015 54 October 1, 2015 22 February 1, 2016 30 April 1, 2016 21 September 1, 2016 20 December 31, 2016 6 On January 1, 2015, Crocus obtained a $60 million construction loan with a 6% interest rate. The loan was outstanding...
On January 2, 2020, Crane Company began construction of a new citrus processing plant. The automated...
On January 2, 2020, Crane Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 604000 September 1, 2020 1809600 December 31, 2020 1809600 March 31, 2021 1809600 September 30, 2021 1196000 Crane Company borrowed $3240000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period. The company...
On April 1, 2020, Dalinar Company began construction on a new distribution warehouse. Construction was completed...
On April 1, 2020, Dalinar Company began construction on a new distribution warehouse. Construction was completed on December 31, 2020, at which time the building was placed in service. Dalinar made an initial payment toward construction on April 1, 2020 of $240,000 and made additional payments $30,000 every two months thereafter, beginning on June 1 and continuing through December 1. A final payment of $100,000 was made on December 31 at the completion of construction. Dalinar borrowed $150,000 at 4%...
Bruzzone industries decided to construct a new plant and began construction on January 1, 2010 and...
Bruzzone industries decided to construct a new plant and began construction on January 1, 2010 and complete construction on January 1, 2012, Assume bruzzone has a weighted average interest rate on their debt of 14% and that total actually interest paid on all existing debt each December 31 is $700,000. Bruzzone had the following expenditures related to the construction. January 1, 2010 $2,600,000 July 1, 2010 $1,000,000 April 1, 2011 $800,000 What amount of interest will be capitalized for the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT