Question

In: Accounting

Pronghorn Landscaping Corp. began constructing a new plant on December 1, 2017. On this date, the...

Pronghorn Landscaping Corp. began constructing a new plant on December 1, 2017. On this date, the company purchased a parcel of land for $183,780 cash. In addition, it paid $1,780 in surveying costs and $3,570 for title transfer fees. An old dwelling on the premises was immediately demolished at a cost of $2,750, with $990 being received from the sale of materials. Architectural plans were also formalized on December 1, 2017, when the architect was paid $29,960. The necessary building permits costing $2,560 were obtained from the city and paid on December 1, 2017. The excavation work began during the first week in December and payments were made to the contractor as follows:

Date of Payment Amount of Payment

Mar. 1 $240,000

May 1 359,680

July 1 59,880

The building was completed on July 1, 2018. To finance the plant construction, Pronghorn borrowed $599,770 from a bank on December 1, 2017. Pronghorn had no other borrowings. The $599,770 was a 10-year loan bearing interest at 10%.

Q : Identify what the effects would be on Pronghorn’s financial statements for the years ending December 31, 2017 and 2018, if its policy were to expense all borrowing costs as they are incurred. Assume that Pronghorn prepares financial statements in accordance with ASPE.

2017 2018

Land

Buildings

Interest expense

Solutions

Expert Solution

1 Cost of Land 2017 2018
Purchase Price $183,780 $183,780
Surveying Cost $1,780 $1,780
Title Transfer Fees $3,570 $3,570
Demolishing Cost $2,750 $2,750
Less: Sale of Material $990 $990
Cost of Land $190,890 $190,890
2 Cost of Building 2017 2018
Architect Fees $29,960 $29,960
Building Permits $2,560 $2,560
Interest to be capitalized in 2017 $1,861.75 $1,861.75
interest to be capitalized in 2018 $31,246.25
Payment on March 1 $240,000
Payment on May 1 $359,680
Payment on July 1 $59,880
Total $34,382 $725,188
3 Interest Expense
2017 2018
Interest Expense $3,136.33 $28,730.75
Working Note:
Weighted expenditure for Interest Capitalization in 2017
Date Amount Period Weighted Expenditure
1-Dec $190,890 1/12 $15,907.50
1-Dec $29,960 1/12 $2,496.67
1-Dec $2,560 1/12 $213.33
Total $223,410 $18,618
Interest to be capitalizated (18618 x 10%) $1,861.75
Interest expense (599770 x 10% x 1/12)          4,998.08
Less: Interest to be capitalized ($1,861.75)
Interest expense 2017          3,136.33
Weighted expenditure for Interest Capitalization in 2018
Date Amount Period Weighted Expenditure
1-Jan $223,410 1/2 $111,705.00
1-Jan $1,862 1/2 $930.88
1-Mar $240,000 1/3 $80,000.00
1-May $359,680 1/6 $59,946.67
1-Jul $59,880 $59,880.00
Total $884,832 $312,462.54
Interest to be capitalizated (312463 x 10%) $31,246.25
Interest expense (599770 x 10%)        59,977.00
Less: Interest to be capitalized ($31,246.25)
Interest expense 2018        28,730.75

Related Solutions

Sage Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Sage Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $138,000 in cash. In addition, it paid $2,160 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $32,400. The necessary...
Crane Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Crane Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $145,200 in cash. In addition, it paid $2,400 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $720 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $31,200. The necessary...
Grouper Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Grouper Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $146,400 in cash. In addition, it paid $2,880 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $36,000. The necessary...
Based on Problem 10-6 Indigo Landscaping began construction of a new plant on December 1, 2020....
Based on Problem 10-6 Indigo Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $147,600 in cash. In addition, it paid $3,120 in surveying costs and $4,080 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,120, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was...
Marigold Corp. is constructing a building. Construction began on January 1 and was completed on December...
Marigold Corp. is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6380000 on March 1, $5250000 on June 1, and $8050000 on December 31. Marigold Corp. borrowed $3250000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6450000 note payable and an 11%, 4-year, $12350000 note payable. What amount of interest should be charged to...
a) On January 1, Blair began construction of a new plant. On this date, the company...
a) On January 1, Blair began construction of a new plant. On this date, the company purchased a parcel of land for $200,000 in cash. In addition, it paid $3,000 in surveying costs and $1,000 for the title insurance policy. An old dwelling on the premises was demolished at a cost of $5,000, with $2,000 being received from the sale of materials. Architectural plans were also formalized on January 1, when the architect was paid $40,000. The necessary building permits...
Pronghorn Corp. purchased a machine on July 1, 2017, for $32,000. Pronghorn paid $290 in title...
Pronghorn Corp. purchased a machine on July 1, 2017, for $32,000. Pronghorn paid $290 in title fees and a legal fee of $300 related to the machine. In addition, Pronghorn paid $500 in shipping charges for delivery, and paid $600 to a local contractor to build and wire a platform for the machine on the plant floor. The machine has an estimated useful life of 10 years, a total expected life of 12 years, a residual value of $6,000, and...
Bonita Industries is constructing a building. Construction began on January 1 and was completed on December...
Bonita Industries is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6552000 on March 1, $5280000 on June 1, and $8450000 on December 31. Bonita Industries borrowed $3180000 on January 1 on a 5-year, 10% note to help finance construction of the building. In addition, the company had outstanding all year a 8%, 3-year, $6410000 note payable and an 9%, 4-year, $12150000 note payable. What are the weighted-average accumulated expenditures? a.20282000 b.8540000...
Arlington Company is constructing a building. Construction began on January 1 and was completed on December...
Arlington Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Arlington Company borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable. What is the avoidable interest for Arlington Company?
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December...
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6380000 on March 1, $5290000 on June 1, and $8650000 on December 31. Sheridan Company borrowed $3240000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6410000 note payable and an 11%, 4-year, $12850000 note payable. What is the avoidable interest for Sheridan Company?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT