Question

In: Accounting

a) On January 1, Blair began construction of a new plant. On this date, the company...

a) On January 1, Blair began construction of a new plant. On this date, the company purchased a parcel of land for $200,000 in cash. In addition, it paid $3,000 in surveying costs and $1,000 for the title insurance policy. An old dwelling on the premises was demolished at a cost of $5,000, with $2,000 being received from the sale of materials. Architectural plans were also formalized on January 1, when the architect was paid $40,000. The necessary building permits costing $4,000 were obtained from the city and paid for on January 1 as well. The excavation work began during the first week in December with payments made to the contractor as follows: Date of payment Amount of payment February 28 $300,000 June 1 400,000 August 31 200,000 The building was completed on September 30, 2015. To finance construction of this plant, Blair borrowed $1,000,000 from Small World Bank on January 1, 2015. Blair had no other borrowings. The $1,000,000 was a 15-year loan bearing interest at 6%. b) Upon completion of the new plant, Blair put the land and building held on January 1 up for resale. c) During October, major updates were made to the equipment at a cost of $12,000. The useful life of the equipment is not extended by these updates, but productive capacity was improved. Based on the above, determine the amounts that Blair Company should report at December 31, 2015 related to the following accounts: A. Land B. Buildings C. Equipment D. Investments E. Interest Expense F. Repairs and Maintenance Expense

Solutions

Expert Solution

The amount that Blair Company should report at 31st December 2015 related to the following accounts are:

1. Land:

Particulars   Amount($)

Purchase price- $200000  

Surveying Costs- $3000

Title insurance policy- $1000

Cost of demolition- $5000

Less: Amount received from sale of materials-($2000)

Total $207000

2. Buildings:   

Particulars                                                                     Amount($)

Architectural plans- $40000

Building permits- $4000

Excavation payments:

February- $300000

June- $400000

August- $200000

Total $944000

3. Equipments:  

Interest expense from 1st January till the date of completion of construction i.e 30th September shall added to the cost of construction and capitalized;

Hence, ($1000000*6%*9/12) = $45000 shall be added to equipment.

Particulars                                                                     Amount($)

Bank loan for purchase- $1000000

Interest cost- $45000

Total $1045000

4. Investments:

6% Bank loan- $1000000

5. Interest expense:  

Interest from the date of completion of construction 30th September till the date of balance sheet i.e 31st December shall be chargeable to profit and loss account as Interest expense:

Calculation:

$1000000*6%*3/12= $15000 shall be treated as interest expense.

6.Repairs and maintenance expense:

Updates made to the equipment which did not extended the useful life of the equipment shall be treated as Revenue expenditure and it shall be charged to Repairs and maintenance expense in the profit and loss account as $12000.


Related Solutions

On January 1, 2015, the Crocus Company began construction of a new manufacturing plant. The plant...
On January 1, 2015, the Crocus Company began construction of a new manufacturing plant. The plant was completed on December 31, 2016. Expenditures on the project were as follows (in $ millions): January 1, 2015 $1 July 1, 2015 54 October 1, 2015 22 February 1, 2016 30 April 1, 2016 21 September 1, 2016 20 December 31, 2016 6 On January 1, 2015, Crocus obtained a $60 million construction loan with a 6% interest rate. The loan was outstanding...
Sage Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Sage Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $138,000 in cash. In addition, it paid $2,160 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $32,400. The necessary...
Crane Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Crane Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $145,200 in cash. In addition, it paid $2,400 in surveying costs and $3,840 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $720 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $31,200. The necessary...
Grouper Landscaping began construction of a new plant on December 1, 2020. On this date, the...
Grouper Landscaping began construction of a new plant on December 1, 2020. On this date, the company purchased a parcel of land for $146,400 in cash. In addition, it paid $2,880 in surveying costs and $4,560 for a title insurance policy. An old dwelling on the premises was demolished at a cost of $3,360, with $960 being received from the sale of materials. Architectural plans were also formalized on December 1, 2020, when the architect was paid $36,000. The necessary...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant...
On June 1, 2020, the Crocus Company began construction of a new manufacturing plant. The plant was completed on October 31, 2021. Expenditures on the project were as follows ($ in millions): July 1, 2020 54 October 1, 2020 22 February 1, 2021 30 April 1, 2021 21 September 1, 2021 20 October 1, 2021 6 On July 1, 2020, Crocus obtained a $70 million construction loan with a 6% interest rate. The loan was outstanding through the end of...
Bruzzone industries decided to construct a new plant and began construction on January 1, 2010 and...
Bruzzone industries decided to construct a new plant and began construction on January 1, 2010 and complete construction on January 1, 2012, Assume bruzzone has a weighted average interest rate on their debt of 14% and that total actually interest paid on all existing debt each December 31 is $700,000. Bruzzone had the following expenditures related to the construction. January 1, 2010 $2,600,000 July 1, 2010 $1,000,000 April 1, 2011 $800,000 What amount of interest will be capitalized for the...
On January 2, 2020, Crane Company began construction of a new citrus processing plant. The automated...
On January 2, 2020, Crane Company began construction of a new citrus processing plant. The automated plant was finished and ready for use on September 30, 2021. Expenditures for the construction were as follows: January 2, 2020 $ 604000 September 1, 2020 1809600 December 31, 2020 1809600 March 31, 2021 1809600 September 30, 2021 1196000 Crane Company borrowed $3240000 on a construction loan at 12% interest on January 2, 2020. This loan was outstanding during the construction period. The company...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made its first $500,000 payment. An additional $600,000 were paid on 4/1/2016 and $300,000 was paid on 7/1/2016. A final payment of $100,000 was made on 12/31/2016, which is also the date when the construction project was finished and the building was ready to use. To finance the project, XYZ Corp issued a $800,000 10% note. Furthermore, XYZ Corp had a $2,000,000 5% note outstanding...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made...
XYZ Corp began construction on a building on January 1, 2016. On that date, it made its first $500,000 payment. An additional $600,000 were paid on 4/1/2016 and $300,000 was paid on 7/1/2016. A final payment of $100,000 was made on 12/31/2016, which is also the date when the construction project was finished and the building was ready to use. To finance the project, XYZ Corp issued a $800,000 10% note. Furthermore, XYZ Corp had a $2,000,000 5% note outstanding...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its...
On January 1, 2018, the Highlands Company began construction on a new manufacturing facility for its own use. The building was completed in 2019. The company borrowed $2,100,000 at 8% on January 1 to help finance the construction. In addition to the construction loan, Highlands had the following debt outstanding throughout 2018: $7,000,000, 13% bonds $3,000,000, 8% long-term note Construction expenditures incurred during 2018 were as follows: January 1 $ 860,000 March 31 1,460,000 June 30 1,112,000 September 30 860,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT