Question

In: Accounting

During 2020, Nash Company started a construction job with a contract price of $1,620,000. The job...

During 2020, Nash Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available.

2020

2021

2022

Costs incurred to date

$444,400 $867,420 $1,060,000

Estimated costs to complete

565,600 230,580 –0–

Billings to date

301,000 904,000 1,620,000

Collections to date

272,000 814,000 1,411,000

Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used.

Gross profit recognized in 2020

$enter a dollar amount

Gross profit recognized in 2021

$enter a dollar amount

Gross profit recognized in 2022

$enter a dollar amount

List of Accounts

  

  

Question Part Score

--/9

Prepare all necessary journal entries for 2021. (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. For costs incurred use account Materials, Cash, Payables.)

Account Titles and Explanation

Debit

Credit

enter an account title to record cost of construction

enter a debit amount

enter a credit amount

enter an account title to record cost of construction

enter a debit amount

enter a credit amount

(To record cost of construction.)

enter an account title to record progress billings

enter a debit amount

enter a credit amount

enter an account title to record progress billings

enter a debit amount

enter a credit amount

(To record progress billings.)

enter an account title to record collections

enter a debit amount

enter a credit amount

enter an account title to record collections

enter a debit amount

enter a credit amount

(To record collections.)

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

enter an account title to recognize revenue

enter a debit amount

enter a credit amount

(To recognize revenue.)

List of Accounts

  

  

Question Part Score

--/6

Compute the amount of gross profit to be recognized each year, assuming the completed-contract method is used.

2020

2021

2022

Gross profit

$enter a dollar amount

$enter a dollar amount

$enter a dollar amount

Solutions

Expert Solution

Formula of Gross profit Recognized :-

= (Contract Value * % of Contract Complete) - Cost incurred to Date

% of Contract Complete = (Costs Incurred to Date/(Costs Incurred to Date+Estimated Costs to Complete))

Gross Profit Recognized in 2020 :-

= ($1620000 * 44%) - $444400

= $712800 - $444400

= $268400

% of Contract Complete = ($444400/($444400+$565600)) = 44%

Gross Profit Recognized in 2021 :-

= ($1620000 * 79%) - $867420

= $1279800 - $867420

= $412380

% of Contract Complete = ($867420/($867420+$230580)) = 79%

Gross Profit Recognized in 2022 :-

= ($1620000 * 100%) - $1060000

= $1620000 - $1060000

= $560000

% of Contract Complete = ($1060000/($1060000+$0)) = 100%

Journal Entries :-

Particulars Debit($) Credit($)
Construction in Process A/c ($867420-$444400) 423020
Materials A/c 423020
(To record cost of Construction)
Accounts Receivable A/c 603000
Billing on Construction A/c ($904000-$301000) 603000
(To record Progress Billings)
Cash A/c ($814000-$272000) 542000
Accounts Receivable A/c 542000
(To Record Collections)
Construction Expenses A/c 423020
Construction in Process A/c 412380
Revenue from Long term Contract A/c 835400
(To Recognize Revenue)

Calculation of Gross Profit Recognize each year :-

Particulars 2020 2021 2022
Gross Profit $0 $0 ($1620000-$1060000) = $560000

Related Solutions

During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sage Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $444,400 $867,420 $1,060,000 Estimated costs to complete 565,600 230,580 –0– Billings to date 301,000 904,000 1,620,000 Collections to date 272,000 814,000 1,411,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sweet Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Sweet Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $749,360 $1,070,000 Estimated costs to complete 636,300 352,640 –0– Billings to date 302,000 907,000 1,620,000 Collections to date 268,000 815,000 1,425,000 (a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar...
During 2020, Tamarisk Company started a construction job with a contract price of $1,620,000. The job...
During 2020, Tamarisk Company started a construction job with a contract price of $1,620,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $373,700 $749,360 $1,070,000 Estimated costs to complete 636,300 352,640 –0– Billings to date 302,000 907,000 1,620,000 Collections to date 268,000 815,000 1,425,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 225,700 Gross profit recognized...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Martinez Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 –0– Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job...
During 2020, Riverbed Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. T he following information is available. 2020 2021 2022 Costs incurred to date $383,800 $905,280 $1,063,000 Estimated costs to complete 626,200 198,720 –0– Billings to date 302,000 896,000 1,610,000 Collections to date 271,000 817,000 1,419,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job...
During 2020, Shamrock Company started a construction job with a contract price of $1,600,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $830,680 $1,074,000 Estimated costs to complete 584,100 262,320 –0– Billings to date 302,000 898,000 1,600,000 Collections to date 272,000 818,000 1,420,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Blossom Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $410,000 $901,180 $1,067,000 Estimated costs to complete 590,000 197,820 –0– Billings to date 297,000 903,000 1,590,000 Collections to date 271,000 805,000 1,434,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job...
During 2020, Sandhill Company started a construction job with a contract price of $1,590,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $424,200 $885,330 $1,060,000 Estimated costs to complete 585,800 207,670 –0– Billings to date 299,000 908,000 1,590,000 Collections to date 273,000 819,000 1,435,000 Part 1 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job...
During 2020, Sheridan Company started a construction job with a contract price of $1,376,000. The job was completed in 2022. The following information is available. The contract is non-cancellable. 2020 2021 2022 Costs incurred to date $344,000 $709,500 $920,200 Estimated costs to complete 516,000 236,500 0 Billings to date (non-refundable) 258,000 774,000 1,376,000 Collections to date 232,200 696,600 1,225,500 Calculate the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. (Enter negative amounts using...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT