In: Accounting
Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows:
| 
 1  | 
 Activity  | 
 Activity Cost Pool  | 
| 
 2  | 
 Production  | 
 $251,598.00  | 
| 
 3  | 
 Setup  | 
 92,035.00  | 
| 
 4  | 
 Material handling  | 
 10,736.00  | 
| 
 5  | 
 Inspection  | 
 49,833.00  | 
| 
 6  | 
 Product engineering  | 
 136,230.00  | 
| 
 7  | 
 Total  | 
 $540,432.00  | 
The activity bases identified for each activity are as follows:
| Activity | Activity Base | 
|---|---|
| Production | Machine hours | 
| Setup | Number of setups | 
| Material handling | Number of parts | 
| Inspection | Number of inspection hours | 
| Product engineering | Number of engineering hours | 
The activity-base usage quantities and units produced for the three products were determined from corporate records and are as follows:
| Machine | Number of | Number of | Number of | Number of | ||
| Hours | Setups | Parts | Inspection Hours | Engineering Hours | Units | |
| Alpha | 970 | 63 | 84 | 489 | 123 | 1,354 | 
| Beta | 802 | 123 | 138 | 272 | 170 | 1,044 | 
| Omega | 435 | 209 | 266 | 256 | 185 | 452 | 
| Total | 2,207 | 395 | 488 | 1,017 | 478 | 2,850 | 
Each product requires 40 minutes per unit of machine time.
| 
 Required: 1. Activity Table - Alpha  | 
|
Complete the Activity Table for
Alpha.
  | 
| Alpha | |||||
| Activity | Activity- | ||||
| Base | Activity | Activity | |||
| Usage | X | Rate | = | Cost | |
| Production | mh | /mh | |||
| Setup | setups | /setup | |||
| Material handling | parts | /part | |||
| Inspection | insp. hours | /hour | |||
| Engineering | eng. hours | /hour | |||
| Total activity cost | |||||
| Number of units | |||||
| Activity cost per unit | |||||
2. Activity Table - beta
Complete the Activity Table for
Beta.
  | 
| Beta | |||||
| Activity | Activity- | ||||
| Base | Activity | Activity | |||
| Usage | X | Rate | = | Cost | |
| Production | mh | /mh | |||
| Setup | setups | /setup | |||
| Material handling | parts | /part | |||
| Inspection | insp. hours | /hour | |||
| Engineering | eng. hours | /hour | |||
| Total activity cost | |||||
| Number of units | |||||
| Activity cost per unit | |||||
3, Activity Table - Omega
Complete the Activity Table for
Omega.
  | 
| Omega | |||||
| Activity | Activity- | ||||
| Base | Activity | Activity | |||
| Usage | X | Rate | = | Cost | |
| Production | mh | /mh | |||
| Setup | setups | /setup | |||
| Material handling | parts | /part | |||
| Inspection | insp. hours | /hour | |||
| Engineering | eng. hours | /hour | |||
| Total activity cost | |||||
| Number of units | |||||
| Activity cost per unit | |||||