In: Accounting
Mello Manufacturing Company is a diversified manufacturer that manufactures three products (Alpha, Beta, and Omega) in a continuous production process. Senior management has asked the controller to conduct an activity-based costing study. The controller identified the amount of factory overhead required by the critical activities of the organization as follows:?
Values not given In question :-
I Give a Question and That Answer for your Help.
Question :-
Activity | Activity Cost Pool |
Production | $650000 |
Setup | 210000 |
Moving | 50000 |
Shipping | 144000 |
Product Engineering | 180000 |
Total | 1234000 |
The activity Bases identified for each activity are as follows :-
Activity | Activity Base |
Production | Machine Hours |
Setup | No. of Setups |
Moving | No. of Moves |
Shipping | No. of Customer orders |
Product Engineering | No. of Test runs |
The Activity Base usage quantities and units produced for the three products were determined from Corporate
records and are as follows :-
Machine Hours | No. of Setups | No. of Moves | No. of Customer orders | No. of Test runs | Units | |
Computer Paper | 1750 | 200 | 500 | 700 | 150 | 2250 |
Newsprint | 2000 | 100 | 200 | 250 | 50 | 2500 |
Specialty Paper | 1250 | 400 | 550 | 850 | 200 | 1750 |
Total | 5000 | 700 | 1250 | 1800 | 400 | 6500 |
Each product requires 0.8 machine hour per unit.
Required :-
1. Determine the activity rate for each activity.
2. Determine the total and per unit activity cost of Computer Paper.
SOLUTION :-
1) Activity Rate for each activity.
Activity | Activity Rate |
Production ($650000 / 5000) | $130 per MH |
Setup ($210000 / 700) | $300 per Setup |
Moving ($50000 / 1250) | $40 per Move |
Shipping ($144000 / 1800) | $80 per Cust. Order |
Product Engineering ($180000 / 400) | $450 per Test run |
2) Total and Per Unit Activity Cost of Computer Paper
Activity | (Activity Base * Activity Rate) | Activity Cost |
Production | (1750 * $130) | $227500 |
Setup | (200 * $300) | $60000 |
Moving | (500 * $40) | $20000 |
Shipping | (700 * $80) | $56000 |
Product engineering | (150 * $450) | $67500 |
Total Activity Cost | $431000 |
Per Unit Activity Cost :-
= Total Activity Cost / No. of Units
= $431000 / 2250
= $191.56