Question

In: Accounting

Amazon ltd produces three products; A, B, C and D using the same processing plant. The...

Amazon ltd produces three products; A, B, C and D using the same processing plant. The following information relates to the company:

Product                                  A                     B                     C                     D

Units produced                      2,000               20,000             2,400               28,000

Material cost per unit (sh)    20                    20                    64                    68

Labour hours per unit                      2                      2                      8                      6

Machine hours per unit        1                      1                      4                      6

Labour cost per unit (sh)      12                    12                    48                    36

The cost accountant analysed the production overheads recorded under the following headings:

Overhead cost element                                              Amount (sh)

Setup costs                                                                 17,420,000

Factory costs (machine oriented activity)                149,696,000

Cost of ordering materials                                        7,680,000

Materials handling costs                                           30,320,000

Administration cost for spare parts                         34,400,000

Investigations into the production overhead activities for the period reveal the following:

Product                                  A                     B                     C                     D

Number of set-ups                 4                      24                    8                      32

Number of material orders 4                      32                    4                      32

Number of times material

Was handled                          8                      40                    12                    48

Number of spare parts used 8                      20                    4                      16

Required:

Unit cost per product using the machine hour rate                       

Unit cost per product using the activity based costing                  

Outline the shortfalls of activity based costing                              

Solutions

Expert Solution

Product A B C D Product A B C D
Units Produced 2000 20000 2400 28000 Labor Hour PU 2.00 2.00 8.00 6.00
Material Cost PU 20.00 20.00 64.00 68.00 Machine Hour PU 1.00 1.00 4.00 6.00
Labor Cost PU 12.00 12.00 48.00 36.00
Overhead Cost Element: Amount Activity Total Activity Per Activity Rate
Overhead Cost Element: A B C D Total Setup Cost 17420000 No of Setup Ups 1403200 12.41
No of Setup Ups 4 24 8 32 68 Factory Cost(Machine) 149696000 Machine HourTotal 199600 749.98
No of Material Order 4 32 4 32 72 Cost of Ordering 7680000 No of Material Order 1553600 4.94
No of Material Handling 8 40 12 48 108 Material Handling 30320000 No of Material Handling 2188800 13.85
No of Spare Parts 8 20 4 16 48 Admisitrative Cost 34400000 No of Spare Parts 873600 39.38
TotalCost 239516000
Overhead Cost Element: A B C D Total
No of Setup Ups 8000 480000 19200 896000 1403200 Total Machine Hours 199600
No of Material Order 8000 640000 9600 896000 1553600
No of Material Handling 16000 800000 28800 1344000 2188800 Overhead Per MH 1,200.0
No of Spare Parts 16000 400000 9600 448000 873600
Product A B C D
Machine Hour PU 1.00 1.00 4.00 6.00
Units Produced 2000 20000 2400 28000
Unit Cost Using MH: Total Machine Hours 2000 20000 9600 168000
1 Product A B C D Total Machine Hours 199600
Material Cost PU 20 20 64 68
Labor Cost PU 12 12 48 36
Overhead Cost Allocated 1200 1200 4800 7200
(MH Per Unit*1200)
Total Cost 1232 1232 4912 7304
2 Unit Cost Using ABC:
Product A B C D
Material Cost PU 20 20 64 68
Labor Cost PU 12 12 48 36
Allocated Costs:
Setup Cost 49.66 297.95 99.32 397.26 (Each Activity* Rate Per Activity)
Factory Cost(Machine) 749.98 749.98 2,999.92 4,499.88 (Each Activity* Rate Per Activity)
Cost of Ordering 19.77 158.19 19.77 158.19 (Each Activity* Rate Per Activity)
Material Handling 111 554 166 665 (Each Activity* Rate Per Activity)
Admisitrative Cost 315 788 158 630 (Each Activity* Rate Per Activity)
Total Cost 1277 2580 3555 6454
3 Shortfalls of ABC System:
a ABC is very Costly to implement and maintain
b ABC Produces reports that are very much different from Traditional Costing
c As many of the organisations are using Traditional System and any organisation using ABC makes the Financial Statements in comparable

Related Solutions

t CASE 2: AMAZON LTD Multibus Ltd manufactures four products namely; A, B, C and D...
t CASE 2: AMAZON LTD Multibus Ltd manufactures four products namely; A, B, C and D using the same plant and processes. The following data relate to the production activities of the company for the period ended 30th November 2008: Product Number of units Material cost per unit (Sh) Labour cost per unit (Sh) Machine time per unit (hours) A 500,000 5 0.5 0.25 B 5,000,000 5 0.5 0.25 C 600,000 16 2.0 1.00 D 7,000,000 17 1.5 1.50            ...
1. A company produces products A and B using the same plant. Product A is sold...
1. A company produces products A and B using the same plant. Product A is sold in the market at a price of 300 EUR, which is 60 EUR above its cost per unit. A company produces 2.000 units of product A and 1.000 units of product B. Product B’s cost per unit is 150 EUR, while the price at which product B is sold in the market is 120 EUR. Costs per unit for both products were calculated by...
At a chip manufacturing plant, four technicians, (A, B, C, D) produce three products (Products 1,...
At a chip manufacturing plant, four technicians, (A, B, C, D) produce three products (Products 1, 2, and 3). This month, the chip manufacturer can sell 80 units of Product 1, 50 units of Product 2 and, at most, 50 units of Product 3. Technician A can make only Product 1 and 3. Techncian B can make only Products 1 and 2. Technician C can make only Product 3. Techncian D can make only Product 2. For each unit produced,...
XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...
XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 24,000 units 25,000 units 12,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 21 $ 38 direct labor cost per unit ....... $18 $ 50 $ 38 variable overhead cost per unit...
XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000...
XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 48,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year ............. 24,000 units 25,000 units 12,000 units selling price per unit ........... $80 $120 $160 direct material cost per unit .... $24 $ 21 $ 38 direct labor cost per unit ....... $18 $ 50 $ 38 variable overhead cost per unit...
XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 200,000...
XYZ Company produces three products, A, B, and C. XYZ's plant capacity is limited to 200,000 machine hours per year. The following information is available for planning purposes: Product A Product B Product C demand for next year in units .... 100,000 200,000 150,000 selling price per unit ........... $18 $28 $24 variable costs per unit .......... $15 $20 $22 It is known that it takes 0.40 machine hours to produce one unit of Product A; 0.70 machine hours to...
Baker Company produces three products: A, B, and C from the same process. Joint costs for...
Baker Company produces three products: A, B, and C from the same process. Joint costs for this production run are $2,100. Pounds Sales price per lb. at split-off Disposal cost per lb. at split-off Further processing per pound Final sales price per pound A   800 $6.50 $3.00 $2.00 $ 7.50 B 1,100 8.25 4.20 3.00 10.00 C 1,500 8.00 4.00 3.50 10.50 If the products are processed further, Baker Company will incur the following disposal costs upon sale: A, $3.00;...
Aston International Products Ltd manufactures four products A, B, C and D. The budget for the...
Aston International Products Ltd manufactures four products A, B, C and D. The budget for the upcoming financial year is as follows: Details A B C D Total $’000 $’000 $’000 $’000 $’000 Direct materials 20,000 10,000 12,000 24,000 66,000 Direct labour 6.000 4,000 7,000 8,000 25,000 Variable overheads 2,000 1,000 3,000 6,000 12,000 28,000 15,000 22,000 38,000 103,000 Sales 50,000 19,000 18,000 52,000 139,000 Contribution 22,000 4,000 (4,000) 14,000 36,000 Fixed costs (8,000) (6,000) (2,000) (7,000) (23,000) Profit/(loss) 14,000...
Benoit Company produces three products—A, B, and C. Data concerning the three products follow (per unit):...
Benoit Company produces three products—A, B, and C. Data concerning the three products follow (per unit): Product A B C Selling price $ 84.00 $ 70.00 $ 74.00 Variable expenses: Direct materials 25.20 21.00 9.00 Other variable expenses 25.20 31.50 42.80 Total variable expenses 50.40 52.50 51.80 Contribution margin $ 33.60 $ 17.50 $ 22.20 Contribution margin ratio 40 % 25 % 30 % The company estimates that it can sell 750 units of each product per month. The same...
Benoit Company produces three products—A, B, and C. Data concerning the three products follow (per unit):...
Benoit Company produces three products—A, B, and C. Data concerning the three products follow (per unit): Product A B C Selling price $ 88.00 $ 72.00 $ 78.00 Variable expenses: Direct materials 26.40 18.00 9.00 Other variable expenses 26.40 36.00 45.60 Total variable expenses 52.80 54.00 54.60 Contribution margin $ 35.20 $ 18.00 $ 23.40 Contribution margin ratio 40 % 25 % 30 % The company estimates that it can sell 900 units of each product per month. The same...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT