In: Accounting
t
CASE 2: AMAZON LTD
Multibus Ltd manufactures four products namely; A, B, C and D using the same plant and processes. The following data relate to the production activities of the company for the period ended 30th November 2008:
Product |
Number of units |
Material cost per unit (Sh) |
Labour cost per unit (Sh) |
Machine time per unit (hours) |
A |
500,000 |
5 |
0.5 |
0.25 |
B |
5,000,000 |
5 |
0.5 |
0.25 |
C |
600,000 |
16 |
2.0 |
1.00 |
D |
7,000,000 |
17 |
1.5 |
1.50 |
Additional information:
The production overhead costs incurred by the company over the period under consideration were analyzed as follows:
Sh.
Machine set up costs 4,355,000
Ordering costs 1,920,000
Machining costs 37,424,000
Quality control costs 7,580,000
Maintenance costs 8,600,000
The production overheads were absorbed by the products based on machine hourly rate
An investigation into the production overhead activities for the period reveal the following:
Product |
Number of machine set-ups |
Number of material orders |
Number of maintenance runs |
Number of production runs |
A |
1 |
1 |
2 |
2 |
B |
6 |
4 |
5 |
10 |
C |
2 |
1 |
1 |
3 |
D |
8 |
4 |
4 |
12 |
Required:
The production cost per unit using the machine hourly rate method
The production cost per unit using the activity based costing method, tracing the overheads to production units by means of appropriate cost drivers
Briefly comment on the differences in costs attributed to products A, B, C and D in b(i) and (ii) above