Question

In: Operations Management

One unit of A is made of three units of B, one unit of C, and...

One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F.

     Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks.

     Assume that lot-for-lot (L4L) lot sizing is used for Items A, B, and F; lots of size 65, 65, and 180 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 12, 80, and 150, respectively; all other items have zero beginning inventory. We are scheduled to receive 9 units of A in Week 2, 50 units of E in Week 1, and also 50 units of F in Week 1. There are no other scheduled receipts. If 35 units of A are required in Week 8, use the low-level-coded bill of materials to find the necessary planned order releases for all components.


Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.)


Period 1 2 3 4 5 6 7 8
Item A
OH = 0
LT = 2
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item C
OH = 12
LT = 1
SS = 0
Q = 65
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item B
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item D
OH = 0
LT = 2
SS = 0
Q = 65
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item E
OH = 80
LT = 1
SS = 0
Q = 180
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item F
OH = 150
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases

Solutions

Expert Solution

Solution :

A, LT - 2, Lot - L4L On Hand 1 2 3 4 5 6 7 8 Total
Gross Requirements 0 0 0 0 0 0 0 35 35
Scheduled Receipts 0 9 0 0 0 0 0 0
Projected On Hand 0 0 9 9 9 9 9 9 0
Net requirements 0 0 0 0 0 0 0 26
Planned order receipts 0 0 0 0 0 0 0 26
Planned order releases 0 0 0 0 0 26 0 0
C, LT - 1, Lot - 65 On Hand 1 2 3 4 5 6 7 8 Total
Gross Requirements 0 0 0 0 0 26 0 0 26
Scheduled Receipts 0 0 0 0 0 0 0 0
Projected On Hand 12 12 12 12 12 12 51 51 51
Net requirements 0 0 0 0 0 14 0 0
Planned order receipts 0 0 0 0 0 65 0 0
Planned order releases 0 0 0 0 65 0 0 0
B, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 Total
Gross Requirements 0 0 0 0 65 78 0 0 143
Scheduled Receipts 0 0 0 0 0 0 0 0
Projected On Hand 0 0 0 0 0 0 0 0 0
Net requirements 0 0 0 0 65 78 0 0
Planned order receipts 0 0 0 0 65 78 0 0
Planned order releases 0 0 0 65 78 0 0 0
D, LT - 2, Lot - 65 On Hand 1 2 3 4 5 6 7 8 Total
Gross Requirements 0 0 0 65 78 52 0 0 195
Scheduled Receipts 0 0 0 0 0 0 0 0
Projected On Hand 0 0 0 0 0 52 0 0 0
Net requirements 0 0 0 65 78 0 0 0
Planned order receipts 0 0 0 65 130 0 0 0
Planned order releases 0 65 130 0 0 0 0 0
E, LT - 1, Lot - 180 On Hand 1 2 3 4 5 6 7 8 Total
Gross Requirements 0 0 0 130 286 0 0 0 416
Scheduled Receipts 50 0 0 0 0 0 0 0
Projected On Hand 80 130 130 130 0 74 74 74 74
Net requirements 0 0 0 0 286 0 0 0
Planned order receipts 0 0 0 0 360 0 0 0
Planned order releases 0 0 0 360 0 0 0 0
F, LT - 1, Lot - L4L On Hand 1 2 3 4 5 6 7 8 Total
Gross Requirements 0 0 0 360 0 0 0 0 360
Scheduled Receipts 50 0 0 0 0 0 0 0
Projected On Hand 150 200 200 200 0 0 0 0 0
Net requirements 0 0 0 160 0 0 0 0
Planned order receipts 0 0 0 160 0 0 0 0
Planned order releases 0 0 160 0 0 0 0 0

Related Solutions

One unit of A is made of three units of B, one unit of C, and...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of two units of B, three units of C, and...
One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for...
One unit of A is composed of two units of B and three units of C....
One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 20, 40, 60, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 50,...
One unit of A is composed of two units of B and three units of C....
One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 15, 40, 36, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 62,...
One unit of A is composed of two units of B and three units of C....
One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 10, 60, 60, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 60,...
Problem 9-16 One unit of A is composed of two units of B and three units...
Problem 9-16 One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 15, 50, 45, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples...
Assume that Product Z is made of two units of A and three units of B....
Assume that Product Z is made of two units of A and three units of B. A is made of three units of C and four of D. D is made of two units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty two units of Product Z are required in Period 10. (Assume that...
Assume that Product Z is made up of one unit of A and five units of...
Assume that Product Z is made up of one unit of A and five units of B. A is made of three units of C and four units of D. D is made of two units of E. The demand for Z is 500 units in Week 8 and 500 units in Week 10. For Z, A, C, and D, there are no units on hand, no safety stock, and no units allocated. Item E has 900 units on hand,...
Product A is an end item and is made from two units of B and three...
Product A is an end item and is made from two units of B and three of C. B is made of four units of D and two of E. C is made of two units of F and two of E.    A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks. b. If 100 units of A are required in Week...
Alpha Company is selling three products: A, B and C. The company sells three units of...
Alpha Company is selling three products: A, B and C. The company sells three units of A for every unit of C, and two units of B for every unit of A. Fixed costs are 720,000 Contribution margins are: A - 1.90 B - 2 C - 2.30 How many units of B would the company sell at break even point?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT