Question

In: Operations Management

One unit of A is made of three units of B, one unit of C, and...

One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F. Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks. Assume that lot-for-lot (L4L) lot sizing is used for items A, B, and F; lots of size 50, 50, and 200 are used for Items C, D, and E, respectively. Items C, E, and F have on-hand (beginning) inventories of 10, 50, and 150, respectively; all other items have zero beginning inventory. We are scheduled to receive 10 units of A in week 2, 50 units of E in week 1, and also 50 units of F in week 1. There are no other scheduled receipts. a. Draw a Product Structure Tree for Product A. b. If 30 units of A are required in week 8, find the necessary planned-order releases for all components.

Solutions

Expert Solution

Solution :


Related Solutions

One unit of A is made of three units of B, one unit of C, and...
One unit of A is made of three units of B, one unit of C, and two units of D. B is composed of two units of E and one unit of D. C is made of one unit of B and two units of E. E is made of one unit of F.      Items B, C, E, and F have one-week lead times; A and D have lead times of two weeks.      Assume that lot-for-lot (L4L) lot sizing is...
One unit of A is made of two units of B, three units of C, and...
One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for...
One unit of A is composed of two units of B and three units of C....
One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 20, 40, 60, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 50,...
One unit of A is composed of two units of B and three units of C....
One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 15, 40, 36, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 62,...
One unit of A is composed of two units of B and three units of C....
One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 10, 60, 60, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples of 60,...
Problem 9-16 One unit of A is composed of two units of B and three units...
Problem 9-16 One unit of A is composed of two units of B and three units of C. Each B is composed of one unit of F. C is made of one unit of D, one unit of E, and two units of F. Items A, B, C, and D have 15, 50, 45, and 25 units of on-hand inventory, respectively. Items A, B, and C use lot-for-lot (L4L) as their lot-sizing technique, while D, E, and F require multiples...
Assume that Product Z is made of two units of A and three units of B....
Assume that Product Z is made of two units of A and three units of B. A is made of three units of C and four of D. D is made of two units of E      Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.      Fifty two units of Product Z are required in Period 10. (Assume that...
Assume that Product Z is made up of one unit of A and five units of...
Assume that Product Z is made up of one unit of A and five units of B. A is made of three units of C and four units of D. D is made of two units of E. The demand for Z is 500 units in Week 8 and 500 units in Week 10. For Z, A, C, and D, there are no units on hand, no safety stock, and no units allocated. Item E has 900 units on hand,...
Product A is an end item and is made from two units of B and three...
Product A is an end item and is made from two units of B and three of C. B is made of four units of D and two of E. C is made of two units of F and two of E.    A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks. b. If 100 units of A are required in Week...
Alpha Company is selling three products: A, B and C. The company sells three units of...
Alpha Company is selling three products: A, B and C. The company sells three units of A for every unit of C, and two units of B for every unit of A. Fixed costs are 720,000 Contribution margins are: A - 1.90 B - 2 C - 2.30 How many units of B would the company sell at break even point?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT