Question

In: Operations Management

Assume that Product Z is made of two units of A and three units of B....

Assume that Product Z is made of two units of A and three units of B. A is made of three units of C and four of D. D is made of two units of E

     Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks.

     Fifty two units of Product Z are required in Period 10. (Assume that there is currently no inventory on hand of any of these items.)


b. Develop an MRP planning schedule showing gross and net requirements and order release and order receipt dates. (Leave no cells blank - be certain to enter "0" wherever required.)


Period 1 2 3 4 5 6 7 8 9 10
Item Z
OH = 0
LT = 2
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item A
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item B
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item C
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item D
OH = 0
LT = 1
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases
Item E
OH = 0
LT = 3
SS = 0
Q = L4L
Gross requirements
Scheduled receipts
Projected available balance
Net requirements
Planned order receipts
Planned order releases

Solutions

Expert Solution

Period 1 2 3 4 5 6 7 8 9 10
Item Z Gross requirements 0 0 0 0 0 0 0 0 0 52
OH = 0 Scheduled receipts 0 0 0 0 0 0 0 0 0 0
LT = 2 Projected available balance 0 0 0 0 0 0 0 0 0 0
SS = 0 Net requirements 0 0 0 0 0 0 0 0 0 52
Q = L4L Planned order receipts 0 0 0 0 0 0 0 0 0 52
Planned order releases 0 0 0 0 0 0 0 52 0 0
Item A Gross requirements 0 0 0 0 0 0 0 104 0 0
OH = 0 Scheduled receipts 0 0 0 0 0 0 0 0 0 0
LT = 1 Projected available balance 0 0 0 0 0 0 0 0 0 0
SS = 0 Net requirements 0 0 0 0 0 0 0 104 0 0
Q = L4L Planned order receipts 0 0 0 0 0 0 0 104 0 0
Planned order releases 0 0 0 0 0 0 104 0 0 0
Item B Gross requirements 0 0 0 0 0 0 0 156 0 0
OH = 0 Scheduled receipts 0 0 0 0 0 0 0 0 0 0
LT = 1 Projected available balance 0 0 0 0 0 0 0 0 0 0
SS = 0 Net requirements 0 0 0 0 0 0 0 156 0 0
Q = L4L Planned order receipts 0 0 0 0 0 0 0 156 0 0
Planned order releases 0 0 0 0 0 0 156 0 0 0
Item C Gross requirements 0 0 0 0 0 0 312 0 0 0
OH = 0 Scheduled receipts 0 0 0 0 0 0 0 0 0 0
LT = 1 Projected available balance 0 0 0 0 0 0 0 0 0 0
SS = 0 Net requirements 0 0 0 0 0 0 312 0 0 0
Q = L4L Planned order receipts 0 0 0 0 0 0 312 0 0 0
Planned order releases 0 0 0 0 0 312 0 0 0 0
Item D Gross requirements 0 0 0 0 0 0 416 0 0 0
OH = 0 Scheduled receipts 0 0 0 0 0 0 0 0 0 0
LT = 1 Projected available balance 0 0 0 0 0 0 0 0 0 0
SS = 0 Net requirements 0 0 0 0 0 0 416 0 0 0
Q = L4L Planned order receipts 0 0 0 0 0 0 416 0 0 0
Planned order releases 0 0 0 0 0 416 0 0 0 0
Item E Gross requirements 0 0 0 0 0 832 0 0 0 0
OH = 0 Scheduled receipts 0 0 0 0 0 0 0 0 0 0
LT = 3 Projected available balance 0 0 0 0 0 0 0 0 0 0
SS = 0 Net requirements 0 0 0 0 0 832 0 0 0 0
Q = L4L Planned order receipts 0 0 0 0 0 832 0 0 0 0
Planned order releases 0 0 832 0 0 0 0 0 0 0

Calculations


Related Solutions

Assume that Product Z is made of two units of A and four units of B....
Assume that Product Z is made of two units of A and four units of B. A is made of three units of C and four of D. D is made of two units of E. Lead times for purchase or fabrication of each unit to final assembly are: Z takes two weeks; A, B, C, and D take one week each; and E takes three weeks. Fifty eight units OF Product Z are required in Period 10. (Assume that...
Product A is an end item and is made from two units of B and three...
Product A is an end item and is made from two units of B and three of C. B is made of four units of D and two of E. C is made of two units of F and two of E.    A has a lead time of one week. B, C, and E have lead times of two weeks, and D and F have lead times of three weeks. b. If 100 units of A are required in Week...
Assume that Product Z is made up of one unit of A and five units of...
Assume that Product Z is made up of one unit of A and five units of B. A is made of three units of C and four units of D. D is made of two units of E. The demand for Z is 500 units in Week 8 and 500 units in Week 10. For Z, A, C, and D, there are no units on hand, no safety stock, and no units allocated. Item E has 900 units on hand,...
One unit of A is made of two units of B, three units of C, and...
One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Hickory Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool   Activity Measure   Estimated Overhead Cost   Expected Activity Machining   Machine-hours   $   242,400   12,000   MHs...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Hickory Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z:    Activity Cost Pool   Activity Measure   Estimated Overhead Cost   Expected Activity Machining   Machine-hours   $   200,000   10,000  ...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,600 12,000 MHs...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The...
Greenwood Company manufactures two products—13,000 units of Product Y and 5,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 231,600 12,000 MHs...
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The...
Greenwood Company manufactures two products—14,000 units of Product Y and 6,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 203,000 10,000 MHs...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The...
Hickory Company manufactures two products—15,000 units of Product Y and 7,000 units of Product Z. The company uses a plantwide overhead rate based on direct labor-hours. It is considering implementing an activity-based costing (ABC) system that allocates all $674,000 of its manufacturing overhead to four cost pools. The following additional information is available for the company as a whole and for Products Y and Z: Activity Cost Pool Activity Measure Estimated Overhead Cost Expected Activity Machining Machine-hours $ 216,700 11,000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT