In: Operations Management
One unit of A is made of two units of B, three units of C, and two units of D. B is composed of one unit of E and two units of F. C is made of two units of F and one unit of D. E is made of two units of D. Items A, C, D, and F have one-week lead times; B and E have lead times of two weeks. Lot-for-lot (L4L) lot sizing is used for Items A, B, C, and D; lots of size 60 and 200 are used for Items E and F, respectively. Item C has an on-hand (beginning) inventory of 10; D has an on-hand inventory of 50; all other items have zero beginning inventory. We are scheduled to receive 20 units of Item E in Week 2; there are no other scheduled receipts.
If 20 units of A are required in Week 8, use the low-level-coded bill-of-materials to find the necessary planned order releases for all components. (Leave no cells blank - be certain to enter "0" wherever required.)
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |||
Item A OH = 0 LT = 1 SS = 0 Q = L4L |
Gross requirements | ||||||||||
Scheduled receipts | |||||||||||
Projected on hand | |||||||||||
Net requirements | |||||||||||
Planned order receipts | |||||||||||
Planned order releases | |||||||||||
Item B OH = 0 LT = 2 SS = 0 Q = L4L |
Gross requirements | ||||||||||
Scheduled receipts | |||||||||||
Projected on hand | |||||||||||
Net requirements | |||||||||||
Planned order receipts | |||||||||||
Planned order releases | |||||||||||
Item C OH = 10 LT = 1 SS = 0 Q = L4L |
Gross requirements | ||||||||||
Scheduled receipts | |||||||||||
Projected on hand | |||||||||||
Net requirements | |||||||||||
Planned order receipts | |||||||||||
Planned order releases | |||||||||||
Item E OH = 0 LT = 2 SS = 0 Q = 60 |
Gross requirements | ||||||||||
Scheduled receipts | |||||||||||
Projected on hand | |||||||||||
Net requirements | |||||||||||
Planned order receipts | |||||||||||
Planned order releases | |||||||||||
Item F OH = 0 LT = 1 SS = 0 Q = 200 |
Gross requirements | ||||||||||
Scheduled receipts | |||||||||||
Projected on hand | |||||||||||
Net requirements | |||||||||||
Planned order receipts | |||||||||||
Planned order releases | |||||||||||
Item D OH = 50 LT = 1 SS = 0 Q = L4L |
Gross requirements | ||||||||||
Scheduled receipts | |||||||||||
Projected on hand | |||||||||||
Net requirements | |||||||||||
Planned order receipts | |||||||||||
Planned order releases | |||||||||||
|
Period | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | |
Item A | Gross requirements | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 20 |
OH = 0 | Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
LT = 1 | Projected on hand | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
SS = 0 | Net requirements | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 20 |
Q = L4L | Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 20 |
Planned order releases | 0 | 0 | 0 | 0 | 0 | 0 | 20 | 0 | |
Item B | Gross requirements | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0 |
OH = 0 | Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
LT = 2 | Projected on hand | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
SS = 0 | Net requirements | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0 |
Q = L4L | Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 40 | 0 |
Planned order releases | 0 | 0 | 0 | 0 | 40 | 0 | 0 | 0 | |
Item C | Gross requirements | 0 | 0 | 0 | 0 | 0 | 0 | 60 | 0 |
OH = 10 | Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
LT = 1 | Projected on hand | 10 | 10 | 10 | 10 | 10 | 10 | 0 | 0 |
SS = 0 | Net requirements | 0 | 0 | 0 | 0 | 0 | 0 | 50 | 0 |
Q = L4L | Planned order receipts | 0 | 0 | 0 | 0 | 0 | 0 | 50 | 0 |
Planned order releases | 0 | 0 | 0 | 0 | 0 | 50 | 0 | 0 | |
Item E | Gross requirements | 0 | 0 | 0 | 0 | 40 | 0 | 0 | 0 |
OH = 0 | Scheduled receipts | 0 | 20 | 0 | 0 | 0 | 0 | 0 | 0 |
LT = 2 | Projected on hand | 0 | 20 | 20 | 20 | 40 | 40 | 40 | 40 |
SS = 0 | Net requirements | 0 | 0 | 0 | 0 | 20 | 0 | 0 | 0 |
Q = 60 | Planned order receipts | 0 | 0 | 0 | 0 | 60 | 0 | 0 | 0 |
Planned order releases | 0 | 0 | 60 | 0 | 0 | 0 | 0 | 0 | |
Item F | Gross requirements | 0 | 0 | 0 | 0 | 80 | 100 | 0 | 0 |
OH = 0 | Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
LT = 1 | Projected on hand | 0 | 0 | 0 | 0 | 120 | 20 | 20 | 20 |
SS = 0 | Net requirements | 0 | 0 | 0 | 0 | 80 | 0 | 0 | 0 |
Q = 200 | Planned order receipts | 0 | 0 | 0 | 0 | 200 | 0 | 0 | 0 |
Planned order releases | 0 | 0 | 0 | 200 | 0 | 0 | 0 | 0 | |
Item D | Gross requirements | 0 | 0 | 120 | 0 | 0 | 50 | 40 | 0 |
OH = 50 | Scheduled receipts | 0 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
LT = 1 | Projected on hand | 50 | 50 | 0 | 0 | 0 | 0 | 0 | 0 |
SS = 0 | Net requirements | 0 | 0 | 70 | 0 | 0 | 50 | 40 | 0 |
Q = L4L | Planned order receipts | 0 | 0 | 70 | 0 | 0 | 50 | 40 | 0 |
Planned order releases | 0 | 70 | 0 | 0 | 50 | 40 | 0 | 0 |