Question

In: Accounting

Waltman and Associates, a public accounting firm, uses job-order costing to capture the costs of its...

Waltman and Associates, a public accounting firm, uses job-order costing to capture the costs

of its audit jobs. There were no audit jobs in process at the beginning of November. Listed

below are data concerning the three audit jobs conducted during November:

Koppel Dupont Rojas

Direct Materials $650 $570 $435

Auditor Labour Costs $4,700 $6,100 $5,775

Auditor Hours    64 75 70

Overhead costs are applied to jobs on the basis of auditor hours, and the predetermined

overhead rate is $58 per auditor hour. The Koppel job is the only incomplete job at the end of

November. Actual overhead for the month was $12,500.

Would you be able to help me with the following ?

1. Determine the cost of each job.

2. Indicate the balance of the Work in Process account at the end of November.

3. Calculate the ending balance of the Overhead account for November.

Solutions

Expert Solution

1. Koppel Dupont Rojas
Direct materials            650              570              435
Labour costs        4,700           6,100           5,775
Auditor hours              64                75                70
OH costs        3,712           4,350           4,060
Cost of each job        9,062        11,020        10,270

OH costs to be allocated based on the predetermined rate of $58 / audit hours.

2. All costs of Koppel will be in Work in process account at the end of November since the job was not complete. Hence the closing balance of WIP account will be $ 9062.

3. Overhead costs have been allocated to jobs on at a predetermined rate @ $ 58 / audit hour. So now total OH recovered in the onth of November = 3712 + 4350 + 4060 = 12,122. This means that OH costs have not been recovered, and under applied by $378 (12500-12122). OH account will have a closing debit balance of $378 and might be adjusted in next month.


Related Solutions

Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $101,200 Number of moves 4,000 Engineering 142,400 Number of change orders 8,000 Other overhead 358,800 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $108,000 Number of moves 4,500 Engineering 165,000 Number of change orders 10,000 Other overhead 263,200 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Overhead Application and Job-Order Costing Heurion Company is a job-order costing firm that uses a plantwide...
Overhead Application and Job-Order Costing Heurion Company is a job-order costing firm that uses a plantwide overhead rate based on direct labor hours. Estimated information for the year is as follows: Overhead $789,000 Direct labor hours 100,000 Heurion worked on five jobs in July. Data are as follows: Job 741 Job 742 Job 743 Job 744 Job 745 Balance, July 1 $29,870 $55,215 $27,880 $0 $0 Direct materials $25,500 $39,800 $14,450 $13,600 $8,420 Direct labor cost $61,300 $48,500 $28,700 $24,500...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows. Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,200,000 $ 1,440,000 $ 1,680,000 Fixed overhead costs 612,000 612,000 612,000 Total overhead $ 1,812,000 $ 2,052,000 $ 2,292,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,050,000 $ 1,260,000 $ 1,470,000 Fixed overhead costs 684,000 684,000 684,000 Total overhead $ 1,734,000 $ 1,944,000 $ 2,154,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows. Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 900,000 $ 1,080,000 $ 1,260,000 Fixed overhead costs 630,000 630,000 630,000 Total overhead $ 1,530,000 $ 1,710,000 $ 1,890,000 The expected volume is 180,000 direct...
Kansas Company uses a job costing accounting system for its production costs. The company uses a...
Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 900,000 $ 1,080,000 $ 1,260,000 Fixed overhead costs 702,000 702,000 702,000 Total overhead $ 1,602,000 $ 1,782,000 $ 1,962,000 The expected volume is 180,000 direct...
a Kansas Company uses a job costing accounting system for its production costs. The company uses...
a Kansas Company uses a job costing accounting system for its production costs. The company uses a predetermined overhead rate based on direct labor-hours to apply overhead to individual jobs. The company prepared an estimate of overhead costs at different volumes for the current year as follows: Direct labor-hours 150,000 180,000 210,000 Variable overhead costs $ 1,050,000 $ 1,260,000 $ 1,470,000 Fixed overhead costs 594,000 594,000 594,000 Total overhead $ 1,644,000 $ 1,854,000 $ 2,064,000 The expected volume is 180,000...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs...
Job Order Costing: Wadadli Products uses a job-order costing system Overhead costs are applied to jobs on the basis of machine-hours. At the beginning of the year, management estimated that 170,000 machine-hours would be required for the periods estimated level of production. The company also estimated $212,500 of fixed manufacturing overhead expenses for the coming period and variable manufacturing overhead of $1.50 per machine hour. Required: 1. Compute the company’s predetermined overhead rate. 2. Assume that during the year of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT