Question

In: Accounting

Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...

Job Costs Using Activity-Based Costing

Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows:

Activity Cost Driver Amount of Driver
Materials handling $101,200 Number of moves 4,000
Engineering 142,400 Number of change orders 8,000
Other overhead 358,800 Direct labor hours 52,000

Heitger worked on four jobs in July. Data are as follows:

Job 13-43 Job 13-44 Job 13-45 Job 13-46
Beginning balance $24,200 $17,200 $3,600 $0
Direct materials $5,600 $8,600 $11,100 $10,300
Direct labor cost $970 $950 $1,680 $130
Job 13-43 Job 13-44 Job 13-45 Job 13-46
Number of moves 44 50 35 5
Number of change orders 27 41 18 19
Direct labor hours 970 950 1,680 130

By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.

Required:

1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.

Materials handling rate $ per move
Engineering rate $ per change order
Other overhead rate $ per direct labor hour

2. Prepare job-order cost sheets for each job showing all costs through July 31.

When required, round your answers to the nearest dollar. If an amount is zero, enter "0".

Heitger Company
Job-Order Cost Sheets
Job 13-43 Job 13-44 Job 13-45 Job 13-46
Balance, July 1 $ $ $ $
Direct materials
Direct labor cost
Materials handling
Engineering
Other overhead
Total $ $ $ $

3. Calculate the balance in Work in Process on July 31.

4. Calculate the cost of goods sold for July.

5. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46?

Solutions

Expert Solution

1) Activity rates
Materials handling rate 25.3 per move
engineering rate 17.8 per change order
other overhead rate 6.9 per direct labor hour
2) Job order cost sheet
job 13-43 job 13-44 job13-45 job 13-46
Balance,july 1 24,200 17,200 3,600 0
direct materials 5,600 8,600 11,100 10,300
direct labor cost 970 950 1680 130
materials handling 1113 1265 886 127
engineering 481 730 320 338
other overhead 6693 6555 11592 897
total 39,057 35,300 29,178 11,792
3) Balance of work in process july 31 40,970
(job 45 and job 46)
4) cost of goods sold for july 74,357
(job 43 and 44)
5) difference in cost will be 338

Related Solutions

Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $54,250 Number of moves 2,500 Engineering 120,700 Number of change orders 8,500 Other overhead 148,500 Direct labor hours 45,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing...
Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $108,000 Number of moves 4,500 Engineering 165,000 Number of change orders 10,000 Other overhead 263,200 Direct labor hours 47,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job...
Cornerstone Exercise 5.3 (Algorithmic) Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm...
Cornerstone Exercise 5.3 (Algorithmic) Job Costs Using Activity-Based Costing Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $62,500 Number of moves 2,500 Engineering 113,750 Number of change orders 6,500 Other overhead 343,200 Direct labor hours 52,000 Heitger worked on four jobs in July. Data are as follows: Job...
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs....
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost Driver Amount of Driver Materials handling $81,900 Number of moves 3,500 Engineering 135,150 Number of change orders 8,500 Other overhead 240,000 Direct labor hours 48,000 Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning balance...
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs....
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows: Activity Cost    Driver Amount of Driver Materials handling $ 72,000      Number of moves 3,000   Engineering 165,000      Number of change orders 10,000   Other overhead 280,000      Direct labor hours 50,000   Heitger worked on four jobs in July. Data are as follows: Job 13-43 Job 13-44 Job 13-45 Job 13-46 Beginning...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs. The following overhead activities were budgeted for the year. ? Activity Cost Driver Amount of driver setups $240,000 number of setups 6,000 purchasing 160,000 number of parts 20,000 other overhead 300,000 direct labor hours 80,000 ? The following information about the jobs was given for April. ? ? Job 101 Job 102 Job 103 Job 104 Balance 4/1 $64,900 $40,770 $30,500 0 direct...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to...
Lamour Corporation is a job order costing company that uses activity-based costing to apply overhead to jobs. The following overhead activities were budgeted for the year. Activity Cost Driver Amount of driver Setups $240,000 Number of setups 6,000 Purchasing 160,000 Number of parts 20,000 Other overhead 300,000 Direct labor hours 80,000 The following information about the jobs was given for April. Job 101 Job 102 Job 103 Job 104 Balance 4/1 $64,900 $40,770 $30,500 0 Direct materials 54,000 37,900 25,000...
Overhead Application and Job-Order Costing Heurion Company is a job-order costing firm that uses a plantwide...
Overhead Application and Job-Order Costing Heurion Company is a job-order costing firm that uses a plantwide overhead rate based on direct labor hours. Estimated information for the year is as follows: Overhead $789,000 Direct labor hours 100,000 Heurion worked on five jobs in July. Data are as follows: Job 741 Job 742 Job 743 Job 744 Job 745 Balance, July 1 $29,870 $55,215 $27,880 $0 $0 Direct materials $25,500 $39,800 $14,450 $13,600 $8,420 Direct labor cost $61,300 $48,500 $28,700 $24,500...
Questions: 1. In a company that uses job order costing, the entry to transfer the costs...
Questions: 1. In a company that uses job order costing, the entry to transfer the costs from WIP to Finished Goods would include a debit to Finished Goods equal to the A. total cost of all units worked on during the period. B. total cost of all units in batches completed and sold during the period. C. total cost of all units in batches completed during the period. D. current period costs related to units in batches completed during the...
Happy Company is a manufacturing firm that uses job-order costing. At the beginning of the year,...
Happy Company is a manufacturing firm that uses job-order costing. At the beginning of the year, the company's account balances were as follows: Cash 1,045,000 Accounts Receivable 8,000 RM Inventory 26,000 WIP Inventory 21,000 FG Inventory 39,000 Supplies 8,000 Prepaid Insurance 3,000 Equipment 528,000 Accumulated Depreciation-Equipment 48,000 Accounts Payable 26,000 Common Stock, par $10 1,500,000 Retained Earnings 104,000 Total 1,678,000 1,678,000 The company applies overhead to jobs using a predetermined overhead rate based on machine-hours. At the beginning of the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT