In: Accounting
Job Costs Using Activity-Based Costing
Heitger Company is a job-order costing firm that uses activity-based costing to apply overhead to jobs. Heitger identified three overhead activities and related drivers. Budgeted information for the year is as follows:
Activity | Cost | Driver | Amount of Driver | ||
Materials handling | $54,250 | Number of moves | 2,500 | ||
Engineering | 120,700 | Number of change orders | 8,500 | ||
Other overhead | 148,500 | Direct labor hours | 45,000 |
Heitger worked on four jobs in July. Data are as follows:
Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |||||
Beginning balance | $24,600 | $20,000 | $3,500 | $0 | ||||
Direct materials | $5,500 | $10,000 | $12,900 | $11,400 | ||||
Direct labor cost | $830 | $1,080 | $1,510 | $130 |
Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |||||
Number of moves | 45 | 49 | 30 | 6 | ||||
Number of change orders | 31 | 39 | 15 | 23 | ||||
Direct labor hours | 830 | 1,080 | 1,510 | 130 |
By July 31, Jobs 13-43 and 13-44 were completed and sold. Jobs 13-45 and 13-46 were still in process.
Required:
1. Calculate the activity rates for each of the three overhead activities. Round all activity rates to the nearest cent.
Materials handling rate | $ per move |
Engineering rate | $ per change order |
Other overhead rate | $ per direct labor hour |
2. Prepare job-order cost sheets for each job showing all costs through July 31.
When required, round your answers to the nearest dollar. If an amount is zero, enter "0".
Heitger Company | ||||
Job-Order Cost Sheets | ||||
Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | |
Balance, July 1 | $ | $ | $ | $ |
Direct materials | ||||
Direct labor cost | ||||
Materials handling | ||||
Engineering | ||||
Other overhead | ||||
Total | $ | $ | $ | $ |
3. Calculate the balance in Work in Process on
July 31.
$
4. Calculate the cost of goods sold for
July.
$
5. What if Job 13-46 required no engineering change orders? What is the difference in the new cost of Job 13-46?
$
How would the cost of the other jobs be affected?
A | Activity | Cost | Driver | Amount of Driver | Cost per Driver | ||
Materials handling | 54,250 | Number of moves | 2,500 | 21.70 | Per Move | ||
Engineering | 1,20,700 | Number of change orders | 8,500 | 14.20 | Per Change Order | ||
Other overhead | 1,48,500 | Direct labor hours | 45,000 | 3.30 | Per DLH | ||
B | Heitger Company | ||||||
Job-Order Cost Sheets | |||||||
Job 13-43 | Job 13-44 | Job 13-45 | Job 13-46 | ||||
Balance, July 1 | 24600 | 20000 | 3500 | 0 | |||
Direct materials | 5500 | 10000 | 12900 | 11400 | |||
Direct labor cost | 830 | 1080 | 1510 | 130 | |||
Materials handling | 977 | 1063 | 651 | 130 | |||
Engineering | 440 | 554 | 213 | 327 | |||
Other overhead | 2739 | 3564 | 4983 | 429 | |||
Total | 35086 | 36261 | 23757 | 12416 | |||
Job Status | Sold | Sold | WIP | WIP | |||
C | Work in Progress on Jul 31: | ||||||
Job No. | WIP Value | ||||||
Job 13-45 | 23757 | ||||||
Job 13-46 | 12416 | ||||||
Total | 36173 | ||||||
D | COGS for July: | ||||||
Job No. | COGS Value | ||||||
Job 13-43 | 35086 | ||||||
Job 13-44 | 36261 | ||||||
Total | 71347 | ||||||
E | Job 13-46 | ||||||
Balance, July 1 | 0 | ||||||
Direct materials | 11400 | ||||||
Direct labor cost | 130 | ||||||
Materials handling | 130 | ||||||
Engineering | 0 | ||||||
Other overhead | 429 | ||||||
Total | 12089 | ||||||
Job Status | WIP | ||||||
Earlier Cost | 12,416 | ||||||
Cost Revised | 12,089 | ||||||