50 Hz synchronous generator is supplying 60% of its maximum power
to an infinite bus through a reactive network. Due to a certain
fault, the reactance of the network between the generator internal
voltage and the infinite bus is increased four times. After the
fault is cleared, 80% of maximum power can be transferred
Sketch the mechanical power vs. power angle curves, in the
same figure, under the different operation conditions, and annotate
all the key points on the...