In: Accounting
Question 2
Technics Inc., a manufacturing company, utilizes job order costing. Each division establishes its own estimates regarding overhead which are as follows:
Division A |
Division B |
|
Total estimated overhead |
$128,000 |
$261,000 |
Total estimated machine hours |
16,000 |
72,500 |
Total estimated direct labor hours |
10,000 |
15,000 |
Total actual overhead |
$130,000 |
$250,000 |
Total actual machine hours |
17,000 |
25,000 |
Total actual direct labor hours |
18,000 |
14,000 |
Division A allocates overhead on the basis of machine hours
Division B allocates overhead on the basis of direct labor costs
Required:
For Division A and Division B,
Division A allocates overhead on the basis of machine hours
Division B allocates overhead on the basis of direct labor hours
a. Overhead application = Total estimated cost/estimated hourse in allocation base
Department A:
Here allocation base is machine hours
$128,000/16,000
=$8 per machine hour
Department B:
Here allocation base is labor hours
$261,000/15,000
=$17.4 per direct labor hour
b.Applied overhead = overhead application rate* Actual cost driver
Department A:
$8 per machine hour*17,000 Actual machine hours
=$136,000
Department B:
$17.4 per direct labor hour*14,000
=$243,600
c.under /over absorbed
This will be based on actual overhead and applied overhead
if applied overhead>actual overhead it is over applied
if applied overhead<actual overhead it is underapplied
Department A:
(Over)under applied overhead = Actual overhead-applied overhead
=$130,000-$136,000
=($6,000)
as the actual cost is lower than applied cost the overhead is over applied by $6,000
Department B:
=$250,000-$243,600
=$6,400 under applied
As the actual overhead is higher than the applied overhead the overhead is under applied by $6,400
Please upvote if you find this helpful.incase of query please comment.