In: Accounting
QUESTION 2
Dotsero Technology, Inc., has a job-order costing system. The company uses departmental predetermined overhead rates to apply manufacturing overhead cost to individual jobs. The predetermined overhead rate in Department A is based on machine hours, and the rate in Department B is based on direct labour hours. At the beginning of the most recent year (i.e., January 1, 2012), the company's management made the following estimates for the coming year:
Department
A B
Machine hours 80,000 21,000
Direct labour hours 35,000 65,000
Direct materials cost $190,000 $400,000
Direct labour cost $280,000 $530,000
Manufacturing overhead cost $416,000 $720,000
Job 243 entered into production on April 1, 2012, and all 24 units of product in the job were completed on May 1, 2012. The company's cost records show the following information about the job:
Department
A B
Machine hours 350 70
Direct labour hours 80 130
Direct materials cost $940 $1,200
Direct labour cost $710 $980
At the end of the year (December 31, 2012), the records of Dotsero showed the following actual total cost and operating data for all jobs worked on during the year:
Department
A B
Machine hours 73,000 24,000
Direct labour hours 30,000 68,000
Direct materials cost $165,000 $420,000
Direct labour cost $265,000 $510,000
Manufacturing overhead cost $390,000 $740,000
Required:
1. Compute the predetermined overhead rates for Department A and Department B at the beginning of the year 2012. ( 3 marks)
2. Compute the total overhead cost applied to Job 243 during the year 2012. ( 2 marks) (b) What was the total cost of Job 243 once the job was completed? ( 2 mark)
3. Compute the amount of under-applied or over-applied overhead in each department, and in total, at the end of the current year (December 31, 2012). Based on this analysis, comment on the apparent relative quality of this job costing system for generating useful cost information. Briefly justify your answer. ( 5 marks)
4. Return to the original data at the beginning of the question. Assume that, instead of two separate departmental overhead rates, the company uses a single plant-wide overhead application rate based on direct materials cost as the allocation base. Compute the single predetermined overhead application rate for Dotsero Company as of the beginning of the year 2012, and the amount of overhead which would be applied to Job 243. ( 3 marks)
Please give positive ratings so I can keep answering. It would help me a lot. Please comment if you have any query. Thanks! |
Dotsero Technology, Inc. | ||||
Answer 1 | ||||
Calculation of Departmental OH Rate | Dept. A | Dept. B | Note | |
Manufacturing overhead | 416,000.00 | 720,000.00 | A | |
Machine/ Direct Labor Hour | 80,000.00 | 65,000.00 | B | |
Departmental OH Rate | 5.20 | 11.08 | C=A/B | |
Answer 2 | ||||
Allocated OH for Job 243 | Dept. A | Dept. B | Total | |
Machine/ Direct Labor Hour | 350.00 | 130.00 | D | |
Departmental OH Rate | 5.20 | 11.08 | See C | |
Allocated OH | 1,820.00 | 1,440.00 | 3,260.00 | E=C*D |
Answer 3 | Dept. A | Dept. B | Note | |
Machine/ Direct Labor Hour | 73,000.00 | 68,000.00 | F | |
Departmental OH Rate | 5.20 | 11.08 | See C | |
OH applied | 379,600.00 | 753,230.77 | G=F*C | |
Actual OH | 390,000.00 | 740,000.00 | H | |
Difference | (10,400.00) | 13,230.77 | I=G-H | |
Remarks | Under applied | Over applied | ||
Answer 4 | ||||
Calculation of Plant wide OH Rate | Dept. A | Dept. B | Total | Note |
Manufacturing overhead | 416,000.00 | 720,000.00 | 1,136,000.00 | See A |
Direct materials cost | 190,000.00 | 400,000.00 | 590,000.00 | J |
Predetermined OH Rate | 1.93 | K=A/J | ||
Allocated OH for Job 243 | Dept. A | Dept. B | Total | |
Direct materials cost | 940.00 | 1,200.00 | 2,140.00 | L |
Departmental OH Rate | 1.93 | See K | ||
Allocated OH | 4,120.41 | M=L*K |