Question

In: Finance

A project has the following cash flows: C0 - $6,750; C1 - $4,500; C2 - $5,000....

A project has the following cash flows: C0 - $6,750; C1 - $4,500; C2 - $5,000. At a discount rate of 10%, the project’s NPV - $1,473. We learned that as the discount rate is increased, the NPV of a specific project will decrease. How high can the discount rate be before you would reject the project?

Solutions

Expert Solution


Related Solutions

A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −190 +130 +150 +140 The estimated project beta is 1.58. The market return rm is 18%, and the risk-free rate rf is 5%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A company is considering a project that has the following cash flows: C0 = -5,000, C1...
A company is considering a project that has the following cash flows: C0 = -5,000, C1 = +900, C2 = +2,500, C3 = +1,100, and C4 = +2,900 with a risk-adjusted discount rate of 12%. a) Calculate the Net Present Value (NPV), Internal Rate of Return (IRR), Profitability Index, and the Payback of this project. b) If you were the manager of the firm, will you accept or reject the project based on the calculation results above?
1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 =...
1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 = 100,000; C3 = 150,000. If the discount rate changes from 10% to 15%, the CHANGE in the NPV of the project is closest to: A. $23,076 increase B. $23,076 decrease C. $9,667 decrease D. $9,667 increase E. None of the above 2. Companies A and B are valued as follows: Both companies are 100% equity financed. Company A now acquires B by offering two...
A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C
A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C3 -100      40        60        50          The investor expected rate of return is 10%. The cost of capital is 12%. Required: What will you choose to be the discount rate? Why? Please calculate the payback period (PP) and return on investment (ROI). Please calculate NPV,PVI and IRR.. Make decision based on the above calculation and explain the reasons. David said that the profit is the same as...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / +...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / + $ 24 / + $ 24 / + $ 24 / ? $ 46 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT