Question

In: Finance

1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 =...

1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 = 100,000; C3 = 150,000. If the discount rate changes from 10% to 15%, the CHANGE in the NPV of the project is closest to:

A.

$23,076 increase

B.

$23,076 decrease

C.

$9,667 decrease

D.

$9,667 increase

E.

None of the above

2.

Companies A and B are valued as follows:

Both companies are 100% equity financed. Company A now acquires B by offering two (new) shares of A for every three shares of Company B. Suppose that the merger really does increase the value of the combined firms by $18,000. What is the net gain to target shareholders?

A.

$4,000

B.

$0

C.

$17,000

D.

$1,000

E.

None of the above

Solutions

Expert Solution

Dear student, only one question is allowed at a time. I am answering the first question

1)

Present value factor

= 1 / ( 1 + Rate of Interest ) ^ Number of years

So, PV Factor for year 2 when interest rate is 10% will be

= 1 / ( 1.10 ) ^ 2

= 1 / 1.21

= 0.826446

The following table shows the calculations

So, change in net present value

= Final – Initial

= $ 17,720.06 - $ 40,796.39

= - $ 23,076.33 or -$ 23,076 or $ 23,076 decrease

So, as per above discussion, option B is the correct option


Related Solutions

A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −190 +130 +150 +140 The estimated project beta is 1.58. The market return rm is 18%, and the risk-free rate rf is 5%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following cash flows: C0 - $6,750; C1 - $4,500; C2 - $5,000....
A project has the following cash flows: C0 - $6,750; C1 - $4,500; C2 - $5,000. At a discount rate of 10%, the project’s NPV - $1,473. We learned that as the discount rate is increased, the NPV of a specific project will decrease. How high can the discount rate be before you would reject the project?
A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C
A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C3 -100      40        60        50          The investor expected rate of return is 10%. The cost of capital is 12%. Required: What will you choose to be the discount rate? Why? Please calculate the payback period (PP) and return on investment (ROI). Please calculate NPV,PVI and IRR.. Make decision based on the above calculation and explain the reasons. David said that the profit is the same as...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Hamstring Inc. is considering a project with the following cash flows: C0 C1 C2      C3...
Hamstring Inc. is considering a project with the following cash flows: C0 C1 C2      C3 C4 $(25,000) $10,000 $12,000 $5,000 $8,000 The company is reluctant to consider projects with paybacks of more than three years. If projects pass the payback screen, they are considered further by means of the NPV and IRR methods. The firm's cost of capital is 9%. a. What is the project 's payback period? Should the project be considered further? b. What is the project's...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / +...
Consider the following cash flows: C0 / C1/ C2 /C3 /C4 ? $ 27 / + $ 24 / + $ 24 / + $ 24 / ? $ 46 a. Which two of the following rates are the IRRs of this project? (You may select more than one answer. Single click the box with the question mark to produce a check mark for a correct answer and double click the box with the question mark to empty the box...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT