In: Finance
1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 = 100,000; C3 = 150,000. If the discount rate changes from 10% to 15%, the CHANGE in the NPV of the project is closest to:
A. |
$23,076 increase |
|
B. |
$23,076 decrease |
|
C. |
$9,667 decrease |
|
D. |
$9,667 increase |
|
E. |
None of the above |
2.
Companies A and B are valued as follows:
Both companies are 100% equity financed. Company A now acquires B by offering two (new) shares of A for every three shares of Company B. Suppose that the merger really does increase the value of the combined firms by $18,000. What is the net gain to target shareholders?
A. |
$4,000 |
|
B. |
$0 |
|
C. |
$17,000 |
|
D. |
$1,000 |
|
E. |
None of the above |
Dear student, only one question is allowed at a time. I am answering the first question
1)
Present value factor
= 1 / ( 1 + Rate of Interest ) ^ Number of years
So, PV Factor for year 2 when interest rate is 10% will be
= 1 / ( 1.10 ) ^ 2
= 1 / 1.21
= 0.826446
The following table shows the calculations
So, change in net present value
= Final – Initial
= $ 17,720.06 - $ 40,796.39
= - $ 23,076.33 or -$ 23,076 or $ 23,076 decrease
So, as per above discussion, option B is the correct option