Question

In: Finance

A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C

A project has the following forecasted cash flows:

Cash    Flows

Thousands of dollars

C0       C1        C2        C3

-100      40        60        50

        

The investor expected rate of return is 10%. The cost of capital is 12%.

Required:

  1. What will you choose to be the discount rate? Why?
  2. Please calculate the payback period (PP) and return on investment (ROI).
  3. Please calculate NPV,PVI and IRR..
  4. Make decision based on the above calculation and explain the reasons.
  5. David said that the profit is the same as the cashflow. Do you think his opinion is right or wrong? Why?

Solutions

Expert Solution

1. we will choose cost of capital=12% as the discount rate because it is the actual cost that has to paid for raising the capital for the capex of the particular project. In other way, my cost of funding for the project is 12%. If we consider cost of capital for the discounting of future cashflows, that give us a right picture.

Pay back period is the breakeven. In how many years, will I recieve my initial investment. In this case, the investor recieves his investment in 2 years ($40,000+$60,000=$100,000)

In all these calculations, we should discount the future cashflows to the present value.

David's statement is incorrect because not all the cashflows are profit, we have to discount it back to present value and then subtract with the investment. The resultant figure is the actual profit. In this case, the actual profit is $19,134.9


Related Solutions

A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −190 +130 +150 +140 The estimated project beta is 1.58. The market return rm is 18%, and the risk-free rate rf is 5%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 =...
1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 = 100,000; C3 = 150,000. If the discount rate changes from 10% to 15%, the CHANGE in the NPV of the project is closest to: A. $23,076 increase B. $23,076 decrease C. $9,667 decrease D. $9,667 increase E. None of the above 2. Companies A and B are valued as follows: Both companies are 100% equity financed. Company A now acquires B by offering two...
A project has the following cash flows: C0 - $6,750; C1 - $4,500; C2 - $5,000....
A project has the following cash flows: C0 - $6,750; C1 - $4,500; C2 - $5,000. At a discount rate of 10%, the project’s NPV - $1,473. We learned that as the discount rate is increased, the NPV of a specific project will decrease. How high can the discount rate be before you would reject the project?
Consider projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 10% A...
Consider projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 10% A −33,000 23,400 23,400 +$7,612 B −53,000 36,000 36,000 +9,479 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Hamstring Inc. is considering a project with the following cash flows: C0 C1 C2      C3...
Hamstring Inc. is considering a project with the following cash flows: C0 C1 C2      C3 C4 $(25,000) $10,000 $12,000 $5,000 $8,000 The company is reluctant to consider projects with paybacks of more than three years. If projects pass the payback screen, they are considered further by means of the NPV and IRR methods. The firm's cost of capital is 9%. a. What is the project 's payback period? Should the project be considered further? b. What is the project's...
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV...
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 12% A −31,000 21,800 21,800 +$5,843 B −51,000 34,000 34,000 +6,462 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT