Question

In: Operations Management

How would you explain to management how EAC and ETC forecasts work and how they are...

How would you explain to management how EAC and ETC forecasts work and how they are calculated?

If EV is higher than AC, what does this signify? What is likely to happen to the forecasted cost at completion compared to the approved budget?

Why bother to analyze very positive variances?

Solutions

Expert Solution

Estimate at Completion (EAC) is part of earned value management analysis and it is defined as the forecasted cost of the project that is on hand. It can be equal to, more than or less than the budgeted cost of the project. It tells the management regarding the resources required so that project is completed on time.

EAC is calculated by the following formula.

EAC = AC + BAC – EV

Here,

Ac = Actual cost

BAC = budget at completion

EV = Earned value

If earned value is equal to the BAC, then it means that EAC is equal to AA and there is no need to bring in more resources.

In comparison to EAC, estimate to complete (ETC) is calculated by the following formula:

ETC = BAC – EV

If BAC = EV

Then,

ETC = 0

It means that ETC tells that how much more money is required to complete the project if project gets delayed or EV is less than the BAC.

Besides, there is a relationship between EAC and ETC as follows:

EAC = AC + ETC

If EV is greater than AC, then EAC will be decreased and project will be completed at a cost that is less than the approved budgeted cost.

The positive variance should also be analysed, because it tells the lacklustre planning or relaxed valuation of the expenses or the project cost. It brings additional commitment of resources to the project and other projects may suffer. Hence, positive variance should also be evaluated to prevent the poor planning if any.


Related Solutions

Industrial Management How would you distinguish between engineering management and management in general?
Industrial Management How would you distinguish between engineering management and management in general?
Explain how you would decide what light levels are required on a work surface for particular...
Explain how you would decide what light levels are required on a work surface for particular workplaces. Give at least five examples of different visual tasks and state the range of illuminance that is acceptable for that task.
Explain how a gold standard, as monetary policy, would work.
Explain how a gold standard, as monetary policy, would work.
How would you explain “context diagram” to someone with no IT background? How would you explain...
How would you explain “context diagram” to someone with no IT background? How would you explain “normalization” to someone with no IT background? How would you explain “use case diagram” to someone with no IT background? How would you explain “system development life cycle (SDLC)” to someone with no IT background?
Think of a problem that you have recently been faced with (personal, work-related, etc). Illustrate how...
Think of a problem that you have recently been faced with (personal, work-related, etc). Illustrate how you might use the sequence-attribute modification process on your problem? What are the limitations of this method? Do you think that the outcome would have been different if you used the sequence-attribute modification process in the original decision making process? Why or why not?
In six sentences or more, explain how you would use the descriptive statistical procedure(s) at work...
In six sentences or more, explain how you would use the descriptive statistical procedure(s) at work or in your personal life.
How would you use MUDA at home or at your work environment? Explain using all 7...
How would you use MUDA at home or at your work environment? Explain using all 7 deadly wastes.
In Particcular large scale chemical project such as ammonia etc etc , explain where and how...
In Particcular large scale chemical project such as ammonia etc etc , explain where and how did you apply principles of inherent safety
How would you use activity-based costing (ABC) in the organization you work/worked at? Explain activity level...
How would you use activity-based costing (ABC) in the organization you work/worked at? Explain activity level in your organization in addition to the steps needed to follow while implementing ABC. Subject: Managerial Accounting Write more than 350 words
How would you use activity-based costing (ABC) in the organization you work/worked at? Explain activity level...
How would you use activity-based costing (ABC) in the organization you work/worked at? Explain activity level in your organization in addition to the steps needed to follow while implementing ABC. Subject: Managerial Accounting Write more than 350 words
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT