Question

In: Operations Management

Consider the following data for a project to install a new server at the Northland Pines...

Consider the following data for a project to install a new server at the Northland Pines High School.

Activity

Activity Time (days)

Immediate Predecessor(s)

A

2

B

4

A

C

5

A

D

2

B

E

1

B

F

8

B, C

G

3

D, E

H

5

F

I

4

F

J

7

G, H, I

  1. Draw the network diagram.
  2. Calculate the critical path for this project.
  3. How much slack is in each of the activities G, H, and I?

Solutions

Expert Solution

(a)

(b)

The critical path of a project is composed of activities with zero total slack. The critical path(s) is/ are the longest path(s) in a project network. The slacks for each activity can be computed by carrying out forward pass and backward pass in the project network.

Forward Pass:

ES of the starting activities = 0
ES of all other activities = Max. (EF of their immediate predecessors)
EF of an activity = Its ES + Its duration

Backward Pass:

LF of ending activities = Max. (All the EFs)
LF of all other activities = Min. (LS of their immediate successors)
LS of an activity = Its LF - Its duration

Total slack (or, float) = LF - EF for each activity.

Activity Durations ES EF LS LF Slack
A 2 0 2 0 2 0
B 4 2 6 3 7 1
C 5 2 7 2 7 0
D 2 6 8 15 17 9
E 1 6 7 16 17 10
F 8 7 15 7 15 0
G 3 8 11 17 20 9
H 5 15 20 15 20 0
I 4 15 19 16 20 1
J 7 20 27 20 27 0

So, the critical path is A-C-F-H-J.with a duration of 27 days.

(c)

As we have already computed in part (b), the slack of G, H, and I are 9, 0, and 1 day respectively.


Related Solutions

Consider a capital expenditure project to purchase and install new equipment with an initial cash outlay...
Consider a capital expenditure project to purchase and install new equipment with an initial cash outlay of $25,000. The project is expected to generate net after-tax cash flows each year of $6800 for ten years, and at the end of the project, a one-time after-tax cash flow of $11,000 is expected. The firm has a weighted average cost of capital of 12 percent and requires a 3-year payback on projects of this type. Determine whether this project should be accepted...
The following information has been gathered for a project to install a new machine lathe at...
The following information has been gathered for a project to install a new machine lathe at Diamond Manufacturing, Inc. Activity Activity Time (wks) Immediate Predecessor(s) A 4 — B 7 A C 9 B D 3 B E 14 D F 10 C, D G 11 F, E Draw the network diagram. Calculate the slack for each activity and determine the critical path. How long will the project take?
Firm is evaluating the following project to install a new production facility. The production facility requires...
Firm is evaluating the following project to install a new production facility. The production facility requires an investment in a machine costing 25,000 USD. The machine will be fully depreciated according to the straight-line method. The life of the project is estimated to be 4 years. When the project is over, although the book value of the machine is 0, you expect to sell the machine at a market value of 1,000 USD. The project also requires working capital in...
Project engineer found that it is necessary for his project to install new software, the purchase...
Project engineer found that it is necessary for his project to install new software, the purchase price for the software is SR 2,870,325, the software needs update every 3 years and it will cost him SR 328.854, along with a yearly operating cost of SR 47,866. This system will last for 7 years what is the amount he should invest now to cover the cost of this system, use interest rate of 9%. Don't use the negative sign in the...
Firm XYZ is considering a project to built a new facility to install a new production...
Firm XYZ is considering a project to built a new facility to install a new production line. The firm requires a minimum return of 10% in this project, due to the risks involved. The firm is a 34% tax bracket. Sales, revenues and costs details are given in the table below: Cost of new plant and equipment $9,700,000 Shipping and installations costs $300,000 Unit Sales forecasted                                              Year 1 50,000           Year 2 100,000           Year 3 100,000         Year...
Firm XYZ is considering a project to built a new facility to install a new production...
Firm XYZ is considering a project to built a new facility to install a new production line. The firm requires a minimum return of 10% in this project, due to the risks involved. The firm is a 34% tax bracket. Sales, revenues and costs details are given in the table below: Cost of new plant and equipment $9,700,000 Shipping and installations costs $300,000 Unit Sales forecasted                                              Year 1 50,000           Year 2 100,000           Year 3 100,000         Year...
Kennedy Air is evaluating a new project.  The equipment will cost $50,000 plus $10,000 to install.  It will...
Kennedy Air is evaluating a new project.  The equipment will cost $50,000 plus $10,000 to install.  It will be depreciated using the MACRS 3-year class.  The project would require an increase in inventories of $6,000 and an increase in A/P of $1,000.  The firm’s yearly revenues would increase by $40,000 but would also increase operating costs by $10,000.  The project is expected to last 3 years and the equipment can then be sold for $10,000.  The firm’s tax rate is 40% and their cost of capital...
Kennedy Air is evaluating a new project. The equipment will cost $70,000 plus $8,000 to install....
Kennedy Air is evaluating a new project. The equipment will cost $70,000 plus $8,000 to install. It will be depreciated using the MACRS 3-year class. The project would require an increase in inventories of $5,000 and an increase in A/P of $3,000. The firm’s yearly revenues would increase by $70,000 but would also increase operating costs by $20,000. The project is expected to last 3 years and the equipment can then be sold for $12,000. The firm’s tax rate is...
You are working on a project to install 200 new computers for your department. Your sponsor...
You are working on a project to install 200 new computers for your department. Your sponsor is the CTO (Chief Technology Officer). Although the CTO is your key stakeholder, you know that many other individuals will affect the success or failure of your project. This is the first time you have worked with this CTO, and you have heard that he often changes his mind about the requirements and due date. In fact, you heard that a PM who failed...
Problem # 10. NPV: A project costs 3,000 to install will provide to install will provide...
Problem # 10. NPV: A project costs 3,000 to install will provide to install will provide annual cash flows of 800 for each of the next 6 years. A. What is the NPV if the discount rate is 10% B. How high can the discount rate be before you would reject the project? How to do in excel also
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT