In: Finance
Firm XYZ is considering a project to built a new facility to install a new production line. The firm requires a minimum return of 10% in this project, due to the risks involved. The firm is a 34% tax bracket. Sales, revenues and costs details are given in the table below:
Cost of new plant and equipment |
$9,700,000 |
Shipping and installations costs |
$300,000 |
Unit Sales forecasted Year 1 50,000 Year 2 100,000 Year 3 100,000 Year 4 70,000 Year 5 50,000 |
|
Sales price per unit sold |
$145 |
Variable costs per unit produced |
$80 |
Annual fixed costs |
$500,000 |
Net Working Capital requirements |
An initial $100,000 will be needed to start production. After that, net working capital requirements until year 5 will be equal to 5% of the total sales for the year. No NWC will be recuperated at the end of year 5 |
Depreciation |
Using the straight-line method, the depreciation expense is $2,000,000 per year during the five years of the project life. |
Estimate the CCFA for the next 5 years of operation
Using the NPV and IRR decision methods, decide if the firm should take the project
hurdle rate | 10% |
tax | 34% |
sale per unit | 145 |
variable per unit | 80 |
annual fixed | 500000 |
depr | 2000000 |
cost | -9700000 |
shipping | -300000 |
initial | -100000 |
y0 | y1 | y2 | y3 | y4 | y5 | ||
units | 50000 | 100000 | 100000 | 70000 | 50000 | ||
1 | Sales revenue | 7250000 | 14500000 | 14500000 | 10150000 | 7250000 | |
2 | Operating costs | 4500000 | 8500000 | 8500000 | 6100000 | 4500000 | |
3 | Depreciation | 2000000 | 2000000 | 2000000 | 2000000 | 2000000 | |
4 | Income before tax | 750000 | 4000000 | 4000000 | 2050000 | 750000 | |
[1-(2+3)] | |||||||
5 | Taxes at 34% | 0 | 255000 | 1360000 | 1360000 | 697000 | 255000 |
6 | Net income | 0 | 495000 | 2640000 | 2640000 | 1353000 | 495000 |
[4-5] | |||||||
7 | Cash flow from operation | 0 | 2495000 | 4640000 | 4640000 | 3353000 | 2495000 |
[1-2-5] | |||||||
8 | Initial Investment | -10100000 | |||||
9 | Changes in net working capital | 0 | 362500 | 725000 | 725000 | 507500 | 0 |
10 | Total cash flow from investment | -10100000 | 362500 | 725000 | 725000 | 507500 | 0 |
[8+9] | |||||||
11 | Total cash flow | -10100000 | 2857500 | 5365000 | 5365000 | 3860500 | 2495000 |
[7+10] |
Now, NPV is net present value of all these cash flows. Let's take cost of capital to e equal to 10% hurdle rate acceptable to the company.
Then NPV = C0+C1/(1+r%)+C2/(1+r%)^2+...
Or use excel formula =NPV(10%,[cells containing final cash flows])
NPV=5148387.62
IRR is the internal rate of return which is calculated from the above NPV equation where NPV=0 but we find the 'r'.
Excel or BA Plus calculator can calculate precise value of IRR. IRR is 28.65%.
As IRR is greater than hurdle rate of 10%, the company should approve this project.
Also, as NPV is positive, hence by NPV also, this project is acceptable to the company.