A construction project
is carried out by a general contractor with the following
descriptions:
Project Duration: 3 months
(Start: May 1st; End: July 31st)
Contract Amount:
20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181
Budget Amount:
100,936+200,081+300,685
Contract Terms and Conditions
Materials: The construction
company pays material suppliers in full when it receives payment
from the owner. On the last day of each month the construction
company may bill the owner for the work completed during the month.
The owner pays the monthly bills one month after...