Question

In: Civil Engineering

PROBLEM 5 If the general contractor of a project fails to pay its subcontractors, the subcontractors...

PROBLEM 5

If the general contractor of a project fails to pay its subcontractors, the subcontractors may file a lien against the owner’s property, and the project owner is required to pay the subcontractors. To avoid the lien against the property and payment to the subcontractors, what measures could the owner do?

Solutions

Expert Solution


Related Solutions

A construction project is carried out by a general contractor with the following descriptions: Project Duration:...
A construction project is carried out by a general contractor with the following descriptions: Project Duration: 3 months (Start: May 1st; End: July 31st) Contract Amount: 20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181 Budget Amount: 100,936+200,081+300,685 Contract Terms and Conditions Materials: The construction company pays material suppliers in full when it receives payment from the owner. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after...
An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a...
An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a given day the contractor is faced with three electrical jobs associated with various projects. Each subcontractor will have enough time to work on up to two projects during the day. Each project should be completed by exactly two subcontractors. Given below are the distances between the subcontractors and the projects a. Draw a network to represent the possible subcontractor-project assignments. b. Develop a linear...
An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a...
An electrical contractor pays his subcontractors a fixed fee plus mileage for work performed. On a given day the contractor is faced with three electrical jobs associated with various projects. Each subcontractor will have enough time to work on up to two projects during the day. Each project should be completed by exactly two subcontractors. Given below are the distances between the subcontractors and the projects Projects Subcontractor A B C Westside 2 3 4 Federated 6 1 5 Goliath...
In a CM at Risk (CM/GC) project, is there privity of contract between the general contractor...
In a CM at Risk (CM/GC) project, is there privity of contract between the general contractor and the architect? Explain. On a construction project, who ultimately pays for bonds and insurance?
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
If the general contractor on a project decided to further pursue his/her claims to dispute methods...
If the general contractor on a project decided to further pursue his/her claims to dispute methods beyond adjudication, what are the possible options? List the advantages and disadvantages of each one of such options. In regards to construction contracts.
how can u partner in a 2 storey construction project as a general contractor? describe the...
how can u partner in a 2 storey construction project as a general contractor? describe the extent to which any other person or group maybe partnering on project. what are challenges and benefits to any partnering that is occuring? what is preventing any further partnering?
The statement that is incorrect is (select one). a. If a debtor fails to pay the...
The statement that is incorrect is (select one). a. If a debtor fails to pay the receivable on it's due date this means that the debt is bad. b. An outstanding debt may be turned over to a collection agency c. Bad debts should be deducted as an expense in the same accounting period in which the credit sale was reconginised d. Bad debits are a cost of selling on credits.
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursed construction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursedconstruction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of financial...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT