Question

In: Civil Engineering

In a CM at Risk (CM/GC) project, is there privity of contract between the general contractor...

In a CM at Risk (CM/GC) project, is there privity of contract between the general contractor and the architect? Explain.

On a construction project, who ultimately pays for bonds and insurance?

Solutions

Expert Solution

Yes there is privity of contract between the general contractor and the architect. As the architect is ultimate document preprator of the whole process of the work and the contractor need to have bond with insurance from the insurance company or bank so that it guarantee that the work would complete with abudent finance. This bond is important which need to be paid by contractor if it fails to achieve its target. The earnest money deposite is done by the contractor at the time of tender filing which makes the contractor firm to send the bank guareenty to the client or archiect for the work order to proceed.


Related Solutions

Assume that the general contractor during the contract bidding phase notices a critical element of the...
Assume that the general contractor during the contract bidding phase notices a critical element of the wall section detail for the building is omitted. Further assume, the general contractor knows that the missing element is necessary for a successful project, required by code and will increase the cost of the project. The general contractor with knowledge of the error fails to disclose it or raise any question or request for information and bids the project believing they will be entitled...
A construction project is carried out by a general contractor with the following descriptions: Project Duration:...
A construction project is carried out by a general contractor with the following descriptions: Project Duration: 3 months (Start: May 1st; End: July 31st) Contract Amount: 20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181 Budget Amount: 100,936+200,081+300,685 Contract Terms and Conditions Materials: The construction company pays material suppliers in full when it receives payment from the owner. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after...
what are the principles of risk and general contract provision
what are the principles of risk and general contract provision
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the...
Fact Situation: You are the Senior Project Manager for Wackinsmack, Inc., the general contractor on the prime contract for the construction of a new waste water treatment plant for Dimwit County DPW. The Contract Price has grown to $115 million after Dimwit made adjustments to the scope of the Work and issued the appropriate Change Orders. Wackinsmack’s contract with Dimwit is based on the ConsensusDOCs, CD 200, “Owner/Prime Contractor” Form. You have successfully negotiated the subcontract with Acme Mechanical, Inc....
PROBLEM 5 If the general contractor of a project fails to pay its subcontractors, the subcontractors...
PROBLEM 5 If the general contractor of a project fails to pay its subcontractors, the subcontractors may file a lien against the owner’s property, and the project owner is required to pay the subcontractors. To avoid the lien against the property and payment to the subcontractors, what measures could the owner do?
If the general contractor on a project decided to further pursue his/her claims to dispute methods...
If the general contractor on a project decided to further pursue his/her claims to dispute methods beyond adjudication, what are the possible options? List the advantages and disadvantages of each one of such options. In regards to construction contracts.
how can u partner in a 2 storey construction project as a general contractor? describe the...
how can u partner in a 2 storey construction project as a general contractor? describe the extent to which any other person or group maybe partnering on project. what are challenges and benefits to any partnering that is occuring? what is preventing any further partnering?
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursed construction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried...
Contractor performed considerable work on a project. Owner then became insolvent, leaving Contractor unpaid. Contractor tried to recover payment from the undisbursedconstruction loan proceeds being held by Owner's bank. Contractractor argued that it was a beneficiary of the loan agreement between bank and Owner. Bank refused to make payment. Discussion Do you agree with the Contractor's argument? Does the bank have any contractual obligation to disburse the unused loan to the contractor? How would you prevent this kind of financial...
Advise when a contractor will not be in breach of a construction contract as defined under...
Advise when a contractor will not be in breach of a construction contract as defined under the Housing Grants Construction and Regeneration Act 1996, if he wants to stop work on a project due to non-payment.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT