Question

In: Finance

A construction project is carried out by a general contractor with the following descriptions: Project Duration:...

A construction project is carried out by a general contractor with the following descriptions:

  • Project Duration: 3 months (Start: May 1st; End: July 31st)
  • Contract Amount: 20,713+30,081+50,630+40,978+60,886+70,089+30,500+100,165+152,181
  • Budget Amount: 100,936+200,081+300,685
  • Contract Terms and Conditions
    • Materials: The construction company pays material suppliers in full when it receives payment from the owner. On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received.
    • Labor: The construction company pays for labor on the 25th of each month.
    • Subcontractor: The construction company pays subcontractors when it receives payment from the owner but withholds 5% from the subcontractor’s payment. Final payment will include payment of the retention.
    • Between the contractor and the owner: On the last day of each month the construction company may bill the owner for the work completed during the month. The owner pays the monthly bills one month after they are received. The owner withholds 5% from the construction company's payment. Final payment will include payment of the retention.
  • Cost-loaded schedule and billing schedule to the owner
Month May June July
Cost-Loaded Schedule   Materials 20,713 30,081 50,630
Labor 40,978 60,886 70,089
Subcontractor 30,500 100,165 152,181
Bill to Owner 100,936 200,081 300,685

What is the amount of cash to maintain a positive cash flow in this project?

Solutions

Expert Solution

Assumption:

1. The contracting company bills the owner on 30th of the month and the owner receives the bill on the same day and therefore makes the payment on the 30th of the next month.

The key here is the labor payment which is made on the 25th of each month and creates requirement for working capital. Primarily for first 2 months the labor payment is made by the contracting company which amounts to 101864. By 25th of the third month the company gets an additional cashflow due to billing of the first month to the tune of 46201 but that is not sufficient to meet labor payment of third month. An additional amount of 23888 is required to meet labor payment obligations.

Thus the total cash needed to maintain a positive cashflow in the project is 125752. Please refer the table for more details

Month 1 25th of Month 2 Month 2 25th of Month 3 Month 3 Month 4
Billed amount 100936 200081 300685
Receipt from Owner 95889.2 190077 315735.9
Payment for Material 0 20713 30081 50630
Payment for Labour 40978 60886 70089 0
Payment to Subcontractor 0 28975 95156.75 158714.3
Cash Available / (Required) (40978) (60886) 46201 (23888) 64839 106392

Related Solutions

how can u partner in a 2 storey construction project as a general contractor? describe the...
how can u partner in a 2 storey construction project as a general contractor? describe the extent to which any other person or group maybe partnering on project. what are challenges and benefits to any partnering that is occuring? what is preventing any further partnering?
a- • Must a contractor be delayed beyond the contractual project duration in order to successfully...
a- • Must a contractor be delayed beyond the contractual project duration in order to successfully file a claim for 15 delay damages? • Explain your answer b- • A contract contains the following clause: • “The owner specifically reserves the right to modify the progress schedule as required by the conditions of the work.” Can a contractor that has been delayed by the owner’s revisions to the order of the work in the schedule successfully file a claim for...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project...
You are the Construction Manager for the Design and Build Contractor (and PSCS) for a project involving the construction of a multi-screen cinema and retail complex. You have had safety concerns in relation to the appointed scaffolding company, over a three weeks period. The issues raising concern include scaffolds being handed over in an unsafe state (missing toe boards, inadequate bracing and ties), scaffold workers operating at height not being tied-off, poor housekeeping and storage of materials on-site. Outline your...
On January 1, Year 1, Company ABC hired a general contractor to begin construction of a...
On January 1, Year 1, Company ABC hired a general contractor to begin construction of a new office building. ABC negotiated a $900,000, five-year, 10% loan on January 1, Year 1, to finance construction. Payments made to the general contractor for the building during Year 1 amount to $1,000,000. Payments were made evenly throughout the year. Construction is completed at the end of Year 1, and ABC moves in and begins using the building on January 1, Year 2. The...
You are field manager for the general contractor on a multi-story office building under construction. The...
You are field manager for the general contractor on a multi-story office building under construction. The project has risen all 15 floors above the foundation. The roof is on and the exterior façade of the structure, consisting of alternating blue glass ribbon windows and red granite panels, has “dried in” the project many weeks ago. On the third, seventh and fifteenth floors, the executive offices located on the corners of the building have blue glass doors that lead outside to...
1. What benefits may web collaboration provide to a general contractor in the construction industry?
1. What benefits may web collaboration provide to a general contractor in the construction industry?
You are a construction engineer working for a large utility contractor. The project you are working...
You are a construction engineer working for a large utility contractor. The project you are working on is in New York City (Manhattan). You are installing approximately 1,000 L.F. of 48” dia. RCP for storm drains. Invert elevation ranges from 9’ to 14’ below grade. Pay lines for the trench are indicated in the attached specification. Soil characteristics range from SM to SC, based on the Unified Soil Classification. What considerations would you make with regards to a trenching &...
1. A contractor needs water at a remote construction site for a five year project. A...
1. A contractor needs water at a remote construction site for a five year project. A pipeline from a river,six miles away, will supply the water. The cost of the pipeline and the cost of pumping the water will vary with pipe size. See table below. The contractor uses a MARR of 7%. The contractor plans to work 2000 hours per year, and that is the time the pump will run each year. At the end of five years the...
A building contractor is preparing a bid on a new construction project. Two other contractors will...
A building contractor is preparing a bid on a new construction project. Two other contractors will be submitting bids for the same project. Based on past bidding practices, bids from the other contractors can be described by the following probability distributions: Contractor Probability Distribution of Bid A Uniform probability distribution between $500,000 and $700,000 B Normal probability distribution with a mean bid of $600,000 and a standard deviation of $40,000 If required, round your answers to three decimal places. If...
In a CM at Risk (CM/GC) project, is there privity of contract between the general contractor...
In a CM at Risk (CM/GC) project, is there privity of contract between the general contractor and the architect? Explain. On a construction project, who ultimately pays for bonds and insurance?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT