Question

In: Computer Science

Asian Islamic Bank entered a three-year Istisna' contract to construct a bungalow for a total price of $1,200,000 commencing 1 January 2008

Asian Islamic Bank entered a three-year Istisna' contract to construct a bungalow for a total price of $1,200,000 commencing 1 January 2008. The following costs were estimated at the time of concluding the contract:

 

31 Dec 2008

31 Dec 2009

31 Dec 2010

Total

Materials

120,000

180,000

50,000

350,000

Wages

180,000

120,000

50,000

350,000

Total

300,000

300,000

100,000

700,000

 

Billings were made in year 2008 for $600,000, $300,000 in year 2009 and the remaining balance was billed at the end of year 2010. Following is the payment schedule that was agreed with the client of Asian Islamic Bank:

Year

Total

2008

10%

2009

10%

2010

20%

2011

30%

2012

30%

 

There was a substantial increase in material cost in 2010 due to the liquidation of a major supplier for the said material. Accordingly, the bank revised its cost estimate for material to increase by 10% higher from overall original cost. In order to anticipate the increase in cost, the customer and the bank has agreed to incorporate the increase in the selling price by the same amount.

The bank recognizes profit based on the percentage of completion method.

 

Required:

1.       Prepare ledger accounts in the books of Asian Islamic Bank for all relevant transactions for the accounting periods ending;

  1. 31st Dec 2008
  2. 31st Dec 2009
  3. 31st Dec 2010
  4. 31st Dec 2011, and
  5. 31st Dec 2012

 

2.    Prepare the Statements of Financial Position (extract) and Income Statements (extract) for the year 2008 to 2010 to present the transactions relating to the contract

 

Solutions

Expert Solution

ANSWER QUESTION 1

  1. 31st December 2008

 

Dr ($)

Cr ($)

Istisna’ WIP

300,000

 

Cash

 

300,000

 

 

 

Istisna’ Receivable

600,000

 

Istisna’ Billings                                       

 

600,000

 

 

 

Cash

120,000 (1,200,000*10%)

 

Istisna’ Receivable

 

120,000

 

 

 

Cost of Istisna’ Revenue

300,000

 

Istisna’ WIP

214,286 (500,000*300,000/700,000)

 

Istisna’ Revenue

 

514,286

 

  1. 31st December 2009 

 

Dr

Cr

Istisna’ WIP

300,000

 

Cash

 

300,000

 

 

 

Istisna’ Receivable

8300,000

 

Istisna’ Billings

 

300,000

 

 

 

Cash

120,000 (1,200,000*10%)

 

Istisna’ Receivable

 

120,000

 

 

 

Cost of Istisna’ Revenue

300,000

 

Istisna’ WIP

214,286 (500,000*300,000/700,000)

 

Istisna’ Revenue

 

514,286

 

  1. 31st December 2010 

 

Dr

Cr

Istisna’ WIP

135,000

 

Cash

 

135,000

 

 

 

Istisna’ Receivable

300,000

 

Istisna’ Billings

 

300,000

 

 

 

Cash

240,000 (1,200,000*20%)

 

Istisna’ Receivable

 

240,000

 

 

 

Cost of Istisna’ Revenue

135,000

 

Istisna’ WIP

36,428

 

Istisna’ Revenue

 

171,428

  1. 31st December 2011

 

Dr

Cr

Cash

360,000

 

Istisna’ Receivable

 

360,000

 

  1. 31st December 2012

 

Dr

Cr

Cash

360,000

 

Istisna’ Receivable

 

360,000

 

ANSWER QUESTION 2

Income Statement (extract) for

 

2008

2009

2010

Istisna’ revenue

514,286

514,286

171,428

Cost of Istisna’ Revenue

(300,000)

(300,000)

(135,000)

Istisna’ Profit

214,286

214,286

36,428

 

Statement of Financial Position (extract) as at

 

2008

2009

2010

Istisna’ Billings

600,000

900,000

-

Istisna’ WIP

(514,286)

(1,028,572)

-

Istisna’ Receivable

480,000

660,000

720,000

 


Refer answer details for answer question 1 and 2

Related Solutions

KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total...
KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total price of $600.00 commencing 1 January 2007. The following costs were estimated at the time of concluding the contract. 31 December 2007 31 December 2008 Total Materials 120,000 60,000 180,000 Wages 180,000 120,000 300,000 Total 300,000 180,000 480,000 Billings were made in year for 2008 for $225,000 and the remaining balance was billed at the end of year 2008. Following is the payment schedule...
KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total...
KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total price of $600.00 commencing 1 January 2007. The following costs were estimated at the time of concluding the contract.                      31 December 2007             31 December 2008 Total Materials                 120,000                                   60,000                               180,000 Wages                   180,000                                  120,000                               300,000 Total                        300,000                                  180,000                               480,000 Billings were made in year for 2008 for $225,000 and the remaining balance was billed at...
MASLI Islamic Bank entered into an Istisna' contract with Pembinaan Berhad to build a factory in...
MASLI Islamic Bank entered into an Istisna' contract with Pembinaan Berhad to build a factory in Ipoh, Perak for RM500,000, to be completed in 2 years.Total costs is RM400,000 (including pre contract cost of RM 25,000). Additional detail information as follows: Year 1 Year 2 Cumulative costs incurred 300,000 400,000 Billings 280,000 220,000 Collections from purchaser(almustasni)230,000 270,000 Required: Journalise the above said transactions pertaining to the above istisna' assuming the bank adopts the percentage completion method.
IB Islamic Bank (IBIB) of Saudi Arabia entered into an Istisna' contract with the Government of Malaysia on 1st January 2014 for $100 million.
IB Islamic Bank (IBIB) of Saudi Arabia entered into an Istisna' contract with the Government of Malaysia on 1st January 2014 for $100 million. IBIB is to construct a 4-storey-hospital to be completed and handed over to the Malaysia government on 31st December 2016. IBIB and AZRB CorpIBIB then entered into a parallel Istisna' contract with AZRB Corp for RM 80 million on 28th February 2014. The subcontract restricts any passing over to IBIB of any increase in costs up...
On January 1 2019 Areej entered into a contract with a customer to construct a stadium...
On January 1 2019 Areej entered into a contract with a customer to construct a stadium for consideration of $ 200 million. The contract was expected to take 2 years to complete. At 31 December 2019 Areej had incurred costs of $ 55 million, Costs to complete are estimated at $ 50 million. In addition to these costs, Amir purchased plant to be used on the contract at a cost of $ 30 million. This plant was purchased on 1...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2018, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2019, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2019 billings were $2,990,000, and $2,675,000 cash was collected. The project was completed in 2020 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,050,000. During 2021, costs of $2,020,000 were incurred, with estimated costs of $4,020,000 yet to be incurred. Billings of $2,524,000 were sent, and cash collected was $2,270,000. In 2022, costs incurred were $2,524,000 with remaining costs estimated to be $3,630,000. 2022 billings were $2,774,000, and $2,495,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...
On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,150,000. During 2018, costs of $2,050,000 were incurred with estimated costs of $4,050,000 yet to be incurred. Billings of $2,550,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,550,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,800,000 and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT