In: Accounting
On January 1 2019 Areej entered into a contract with a customer to construct a stadium for consideration of $ 200 million. The contract was expected to take 2 years to complete. At 31 December 2019 Areej had incurred costs of $ 55 million, Costs to complete are estimated at $ 50 million. In addition to these costs, Amir purchased plant to be used on the contract at a cost of $ 30 million. This plant was purchased on 1 January 2019 and will have a residual value of $ 10 million the end of 2-year contract. Depreciation on the plant is to be allocated using a straight line method.
Areej determines the progress on contracts with an output method, based on the value of work certified to date. At 31 December 2019, the value of the work certified was $ 110 million, and the payment received from the was $ 20 million.
Required:
a).
b).
At the inception of the contract, the entity should assess the goods or services that have been promised to the customer, and identify as a performance obligation: [IFRS 15.22]
A series of distinct goods or services is transferred to the customer in the same pattern if both of the following criteria are met: [IFRS 15:23]
A good or service is distinct if both of the following criteria are met: [IFRS 15:27]
Factors for consideration as to whether a promise to transfer goods or services to the customer is not separately identifiable include, but are not limited to: [IFRS 15:29]
c).
The following are 2 methods used to determine the progress of a contract :
1). Units Completed
The Units Completed lends itself well to tracking tasks that are done repeatedly, where each iteration can easily be measured. Usually a task that is done repeatedly tends to take about the same amount of time, resources and effort, so tracking the units completed works well here. A simple example could be installing standard light fixtures. Each fixture takes roughly the same amount of time. If we had 100 fixtures to install then we can simply count the units installed. In this case, there are no subjective experience-based judgement involved.
2). Cost Ratio
The Cost Ratio method is usually implemented on a project that has tasks that tend to occur over a long phase or the entire project. Often used for Overhead costs, this technique is measured based on the budgeted allocation of dollars vs. the labour hours of production. This method gives the contractor the ability to earn value that is equal to the overall percent of project completion.
d).
Direct Costs:
Direct Material cost
Direct Labour cost
Direct machine working costs
Wages for workers specifically taken for a contract
Amounts paid to obtain the contract
Electricity and Water charges payable for completion of
contract
Indirect Costs: