Question

In: Accounting

MASLI Islamic Bank entered into an Istisna' contract with Pembinaan Berhad to build a factory in...

MASLI Islamic Bank entered into an Istisna' contract with Pembinaan Berhad to build a factory in Ipoh, Perak for RM500,000, to be completed in 2 years.Total costs is RM400,000 (including pre contract cost of RM 25,000). Additional detail information as follows:

Year 1 Year 2

Cumulative costs incurred 300,000 400,000

Billings 280,000 220,000

Collections from purchaser(almustasni)230,000 270,000

Required:

Journalise the above said transactions pertaining to the above istisna' assuming the bank adopts the percentage completion method.

Solutions

Expert Solution

Percentage completion method Year 1 Year 2
Cost incurred in till previous year 0 300000
ADD Cost incurred during the year 300000 100000
Total cost incurred till date 300000 400000
ADD Estimated cost to be incurred 100000 0
Total estimated cost to be incurred 400000 400000
Percentage of completion (A) 75% 100%
(cost incurred till date /total estimated cost )
Total revenue (B) 500000 500000
Total revenue recognized (A *B) 375000 500000
Less Revenue recognized in previous year 0 375000
revenue recognized in current year 375000 125000
Year 1 Year 2
Revenue 375000 125000
Less Cost incurred 300000 100000
Gross profit 75000 25000
Year 1
1 Construction in progress 300000
               Accounts payable 300000
2 Contracts receivable 280000
               Progress billings 280000
3 Construction in progress 75000
Construction expense 300000
               Construction revenue 375000
4 Cash 230000
          Contract receivable 230000
Year 2
1 Construction in progress 100000
               Accounts payable 100000
2 Contracts receivable 270000
               Progress billings 270000
3 Construction in progress 25000
Construction expense 100000
               Construction revenue 125000
4 Cash 270000
          Contract receivable 270000

Related Solutions

KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total...
KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total price of $600.00 commencing 1 January 2007. The following costs were estimated at the time of concluding the contract. 31 December 2007 31 December 2008 Total Materials 120,000 60,000 180,000 Wages 180,000 120,000 300,000 Total 300,000 180,000 480,000 Billings were made in year for 2008 for $225,000 and the remaining balance was billed at the end of year 2008. Following is the payment schedule...
KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total...
KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total price of $600.00 commencing 1 January 2007. The following costs were estimated at the time of concluding the contract.                      31 December 2007             31 December 2008 Total Materials                 120,000                                   60,000                               180,000 Wages                   180,000                                  120,000                               300,000 Total                        300,000                                  180,000                               480,000 Billings were made in year for 2008 for $225,000 and the remaining balance was billed at...
IB Islamic Bank (IBIB) of Saudi Arabia entered into an Istisna' contract with the Government of Malaysia on 1st January 2014 for $100 million.
IB Islamic Bank (IBIB) of Saudi Arabia entered into an Istisna' contract with the Government of Malaysia on 1st January 2014 for $100 million. IBIB is to construct a 4-storey-hospital to be completed and handed over to the Malaysia government on 31st December 2016. IBIB and AZRB CorpIBIB then entered into a parallel Istisna' contract with AZRB Corp for RM 80 million on 28th February 2014. The subcontract restricts any passing over to IBIB of any increase in costs up...
Asian Islamic Bank entered a three-year Istisna' contract to construct a bungalow for a total price of $1,200,000 commencing 1 January 2008
Asian Islamic Bank entered a three-year Istisna' contract to construct a bungalow for a total price of $1,200,000 commencing 1 January 2008. The following costs were estimated at the time of concluding the contract: 31 Dec 200831 Dec 200931 Dec 2010TotalMaterials120,000180,00050,000350,000Wages180,000120,00050,000350,000Total300,000300,000100,000700,000 Billings were made in year 2008 for $600,000, $300,000 in year 2009 and the remaining balance was billed at the end of year 2010. Following is the payment schedule that was agreed with the client of Asian Islamic Bank:YearTotal200810%200910%201020%201130%201230% ...
ABC Ltd (“ABC”) entered into a contract on 1st January 20x6 to build a factory building...
ABC Ltd (“ABC”) entered into a contract on 1st January 20x6 to build a factory building for its customer on its customer’s land for $20 million. The completion is expected to be in two years’ time. ABC’s policy is to bill its clients based on 60% in the first year and the balance upon completion of the project. ABC has a 31st December financial year end. It has adopted FRS 115 Revenues from Contracts with Customers and adopts the input...
Islamic accounting undergraduate student… Investors deposit OMR 1000,000 with Islamic Bank under a Mudaraba contract for...
Islamic accounting undergraduate student… Investors deposit OMR 1000,000 with Islamic Bank under a Mudaraba contract for a period of 12 months and a profit allocation set out in the agreement as 80% to the investors and 20% to Islamic Bank. The investors receive Mudaraba Certificates (investment deposit certificates) in exchange for their deposits. Subsequently, Islamic Bank invests the OMR 1000,000 in Islamic Enterprises, MirrerCold Enterprise Private Limited to build a new factory. MirrerCold Enterprise Private Limited contributes its expertise in...
Islamic accounting undergraduate student… Investors deposit OMR 1000,000 with Islamic Bank under a Mudaraba contract for...
Islamic accounting undergraduate student… Investors deposit OMR 1000,000 with Islamic Bank under a Mudaraba contract for a period of 12 months and a profit allocation set out in the agreement as 80% to the investors and 20% to Islamic Bank. The investors receive Mudaraba Certificates (investment deposit certificates) in exchange for their deposits. Subsequently, Islamic Bank invests the OMR 1000,000 in Islamic Enterprises, MirrerCold Enterprise Private Limited to build a new factory. MirrerCold Enterprise Private Limited contributes its expertise in...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road for the government. Construction will take 3 years. The following information as of December 31st, 2012 is available for the contract: Total revenue according to contract $15,000 Updated estimated cost in 2013-2014 period $7,200,000 Cost incurred during 2012 $4,800,000 Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the Percentage-of-Completion method, how much revenue...
Problem 3 An entity entered into a construction contract to build a condo building at a...
Problem 3 An entity entered into a construction contract to build a condo building at a fixed price of $54,000,000. Construction started in 20x0 and ended in 20x3. Data on the contract is as follows (in ‘000’s): 20x0 20x1 20x2 20x3 Costs incurred during the year $ 6500 19500 25000 5800 Estimated costs to complete 38500 26000 6500 - Billings 18000 18000 - 18000 For each of the parts below, prepare the ‘mini’ income statement for the project for each...
Sheds Galore entered into a $70,000 contract to build a special shed for Tools and Stuff...
Sheds Galore entered into a $70,000 contract to build a special shed for Tools and Stuff Inc. Sheds Galore has determined that the performance obligation would be settlled over time and uses the cost to cost input method to measure progress. Sheds Galore follows IFRS. Details of the construction of the shed are below:                        2018           2019           2020 Total Costs Incurred               20000           45000           75000...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT