Question

In: Accounting

KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total...

KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total price of $600.00 commencing 1 January 2007. The following costs were estimated at the time of concluding the contract.

31 December 2007 31 December 2008 Total
Materials 120,000 60,000 180,000
Wages 180,000 120,000 300,000
Total 300,000 180,000 480,000

Billings were made in year for 2008 for $225,000 and the remaining balance was billed at the end of year 2008.

Following is the payment schedule that was agreed with the client of KL Islamic Bank:

Year % of total price
2007 25%
2008 30%
2009 45%

There was a substantial increase in material cost in 2008 due to the liquidation of a major supplier for the said material. Accordingly, the bank revised its cost estimate for material to be $60,000 higher than previously planned.

The bank recognizes revenue based on the percentage of completion method.

Required:

a. prepare all necessary journal entries for the year 2007 to 2009 to record the above transactions in the books of KL Islamic Bank.

b. prepare the Statement of Financial Position (extract) and Income Statements (extract) for the year 2007 and 2008 to present tne transactions relating to the contract.

Solutions

Expert Solution

Part a)

The journal entries are given as follows:

Year - 2007
Account Titles Debit Credit
Istisna' WIP $300,000
Cash $300,000
Istisna' Receivable $225,000
Istisna' Billings $225,000
Cash (600,000*25%) $150,000
Istisna' Receivable $150,000
Cost of Istisna' Revenue $300,000
Istisna' WIP $75,000
Istisna' Revenue $375,000
Year - 2008
Istisna' WIP $240,000
Cash $240,000
Istisna' Receivable $375,000
Istisna' Billings $375,000
Cash (600,000*30%) $180,000
Istisna' Receivable $180,000
Cost of Istisna' Revenue $240,000
Istisna' WIP $15,000
Istisna' Revenue $225,000
Istisna' Asset $600,000
Istisna' WIP $600,000
Istisna' Billings $600,000
Istisna' Asset $600,000
Year - 2009
Cash (600,000*45%) $270,000
Istisna' Receivable $270,000

_____

Part b)

The statement of financial position (extract) and Income Statements (extract) for the year 2007 and 2008 to present tne transactions relating to the contract is provided as follows:

Statement of Income For: 2007 2008
Istisna' Revenue 375,000 225,000
Cost of Istisna' Revenue -300,000 -240,000
Istisna' Profit/(Loss) $75,000 -$15,000

_____

Statement of Financial Position As At: 2007 2008
Istisna' Billings 275,000
Istisna' WIP -375,000
Istisna' Receivable 45,000 270,000

Related Solutions

KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total...
KL Islamic Bank entered a two-year Istisna' contract to construct a power generator for a total price of $600.00 commencing 1 January 2007. The following costs were estimated at the time of concluding the contract.                      31 December 2007             31 December 2008 Total Materials                 120,000                                   60,000                               180,000 Wages                   180,000                                  120,000                               300,000 Total                        300,000                                  180,000                               480,000 Billings were made in year for 2008 for $225,000 and the remaining balance was billed at...
Asian Islamic Bank entered a three-year Istisna' contract to construct a bungalow for a total price of $1,200,000 commencing 1 January 2008
Asian Islamic Bank entered a three-year Istisna' contract to construct a bungalow for a total price of $1,200,000 commencing 1 January 2008. The following costs were estimated at the time of concluding the contract: 31 Dec 200831 Dec 200931 Dec 2010TotalMaterials120,000180,00050,000350,000Wages180,000120,00050,000350,000Total300,000300,000100,000700,000 Billings were made in year 2008 for $600,000, $300,000 in year 2009 and the remaining balance was billed at the end of year 2010. Following is the payment schedule that was agreed with the client of Asian Islamic Bank:YearTotal200810%200910%201020%201130%201230% ...
MASLI Islamic Bank entered into an Istisna' contract with Pembinaan Berhad to build a factory in...
MASLI Islamic Bank entered into an Istisna' contract with Pembinaan Berhad to build a factory in Ipoh, Perak for RM500,000, to be completed in 2 years.Total costs is RM400,000 (including pre contract cost of RM 25,000). Additional detail information as follows: Year 1 Year 2 Cumulative costs incurred 300,000 400,000 Billings 280,000 220,000 Collections from purchaser(almustasni)230,000 270,000 Required: Journalise the above said transactions pertaining to the above istisna' assuming the bank adopts the percentage completion method.
IB Islamic Bank (IBIB) of Saudi Arabia entered into an Istisna' contract with the Government of Malaysia on 1st January 2014 for $100 million.
IB Islamic Bank (IBIB) of Saudi Arabia entered into an Istisna' contract with the Government of Malaysia on 1st January 2014 for $100 million. IBIB is to construct a 4-storey-hospital to be completed and handed over to the Malaysia government on 31st December 2016. IBIB and AZRB CorpIBIB then entered into a parallel Istisna' contract with AZRB Corp for RM 80 million on 28th February 2014. The subcontract restricts any passing over to IBIB of any increase in costs up...
Big Red Engineering Associates entered into a 3 year contract to construct an office building at...
Big Red Engineering Associates entered into a 3 year contract to construct an office building at a contract price of $1,700,000. With the construction data below prepare the necessary journal entries to record cost incurred, billings to customers, cash collections, and the end of year adjusting entry applicable to percentage of completion method:                                                  Year 1                    Year 2                    Year 3 Construction cost incurred       250,000                 900,000                  210,000 Estimated cost to complete   1,000,000                  287,500                       0 Progress Billings                      190,000               1,200,000                  310,000 Collections...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract...
Rookie Construction Limited (RCL) entered into a contract to construct a building for $975,000. The contract provided for progress payments. RCL’s accounting year ends December 31. Work began under the contract on August 1, 2019, and was completed on October 31, 2021. RCL uses the percentage-of-completion method to account for this long-term contract. Construction activities are summarized below: 2019 2020 2021 Construction costs incurred to date 180,000 630,000 825,000 Estimated remaining costs to complete 630,000 190,000 0 Progress Billings during...
Islamic accounting undergraduate student… Investors deposit OMR 1000,000 with Islamic Bank under a Mudaraba contract for...
Islamic accounting undergraduate student… Investors deposit OMR 1000,000 with Islamic Bank under a Mudaraba contract for a period of 12 months and a profit allocation set out in the agreement as 80% to the investors and 20% to Islamic Bank. The investors receive Mudaraba Certificates (investment deposit certificates) in exchange for their deposits. Subsequently, Islamic Bank invests the OMR 1000,000 in Islamic Enterprises, MirrerCold Enterprise Private Limited to build a new factory. MirrerCold Enterprise Private Limited contributes its expertise in...
Islamic accounting undergraduate student… Investors deposit OMR 1000,000 with Islamic Bank under a Mudaraba contract for...
Islamic accounting undergraduate student… Investors deposit OMR 1000,000 with Islamic Bank under a Mudaraba contract for a period of 12 months and a profit allocation set out in the agreement as 80% to the investors and 20% to Islamic Bank. The investors receive Mudaraba Certificates (investment deposit certificates) in exchange for their deposits. Subsequently, Islamic Bank invests the OMR 1000,000 in Islamic Enterprises, MirrerCold Enterprise Private Limited to build a new factory. MirrerCold Enterprise Private Limited contributes its expertise in...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year $ 2,604,000 $ 4,032,000 $ 1,940,400 Estimated costs to complete as of year-end 5,796,000 1,764,000 0 Billings during the year 2,040,000 4,596,000 3,364,000 Cash collections during the year 1,820,000 4,000,000 4,180,000 Westgate recognizes revenue over time according to...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa...
In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2021 2022 2023 Cost incurred during the year $ 1,584,000 $ 3,240,000 $ 2,613,600 Estimated costs to complete as of year-end 5,616,000 2,376,000 0 Billings during the year 1,200,000 3,624,000 5,176,000 Cash collections during the year 1,000,000 2,800,000 6,200,000 Assume that Westgate Construction’s contract with Santa...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT