Question

In: Operations Management

The status of a project after 100 days and after 150 days is as follows. (EV-Earned...

The status of a project after 100 days and after 150 days is as follows. (EV-Earned Value, PV-Planned Value, AC-Actual Cost in Rs). Determine the time and cost overruns and underruns of:

  1. The project
  2. Of each activity after 100 days and after 150 days.

Show all calculations.

Status after 100 days

Status after 150 days

Activity

EV

PV

AC

EV

PV

AC

A

80

100

200

200

200

250

B

120

200

80

120

300

80

C

300

500

350

300

600

D

100

80

E

500

700

Solutions

Expert Solution

a.

after 100 days,

project EV = 80+120+300 = 500
Project PV = 100+200+500 = 800
project AC = 200+80+500 = 780

Project schedule variance = EV-PV = 500-800 = -300 = time underrun by 300
project cost variance = EV-AC = 500-780 = -280 = Cost overrun by 280

After 150 days,

project EV = 200+120+350+100 = 770
Project PV = 200+300+300+700 = 1500
project AC = 250+80+600+80 = 1010

Project schedule variance = EV-PV = 770-1500 = -730 = time underrun by 730
project cost variance = EV-AC = 770-1010 = -240 = Cost overrun by 240

b.
after 100 days,

Activity A Schedule variance = EV-PV = 80-100 = -20 (time underrun by 20) ; cost variance = EV-AC = 80-200 = -120 (Cost overrun by 120)

Activity B Schedule variance = EV-PV = 120-200 = -80 (time underrun by 80) ; cost variance = EV-AC = 120-80 = 40 (Cost underrun by 40)

Activity C Schedule variance = EV-PV = 300-0 = 300 (time overrun by 300) ; cost variance = EV-AC = 300-500 = -200 (Cost overrun by 200)

Activity D Schedule variance = EV-PV = 0 ; cost variance = 0 (No overrun/underrun)

Activity E Schedule variance = EV-PV = 0-500 = -500 (time underrun by 500) ; cost variance = EV-AC = 0

After 150 days,

Activity A Schedule variance = EV-PV = 200-200   = 0 ; cost variance = EV-AC =200-250 = -50 (Cost overrun by 50)

Activity B Schedule variance = EV-PV = 120-300 = -180 (time underrun by 80) ; cost variance = EV-AC = 120-80 = 40 (Cost underrun by 40)

Activity C Schedule variance = EV-PV = 350-300 = 50 (time overrun by 50) ; cost variance = EV-AC = 350-600 = -250 (Cost overrun by 250)

Activity D Schedule variance = EV-PV = 100-0 = 100 (time overrun by 100) ; cost variance = 100-80 = 20 (Cost underrun by 20)

Activity E Schedule variance = EV-PV = 0-700 = -700 (time underrun by 700) ; cost variance = EV-AC = 0


Related Solutions

Read through the Tree Trimming Project case. This case refers to the earned value (EV) of...
Read through the Tree Trimming Project case. This case refers to the earned value (EV) of the owner, Will Fence’s Tree Trimming business. Will briefly describes his techniques for EV. Based on the description provided in the case, is Will using EV? Answer the corresponding question provided at the end of the case (300-500 words). Use references from the reading materials to support your response. Case is below Tree Trimming Project Wil Fence is a large timber and Christmas tree...
Why is the times interest earned ratio considered important? ANswer in 100-150 words
Why is the times interest earned ratio considered important? ANswer in 100-150 words
In a 100-150 word response, discuss what you think the current status of Québec independence is....
In a 100-150 word response, discuss what you think the current status of Québec independence is. Do you think we will see another referendum for independence? Why or Why not?
Actual Cost, planned value and earned value of the activities of an ongoing project after 5...
Actual Cost, planned value and earned value of the activities of an ongoing project after 5 months and after 8 months are given below. All values and costs are in Rs lakhs. Comment on status of the a) Activities (Activity delayed/early, activity cost overrun/underrun) b) status of project and estimated total cost at completion at 5 months and at 8 months. After 5 months    Activity. EV PV AC Comment    A 10 10 8    B 18 15 12...
your project status end of 10th day.Discuss the status of this project in terms of schedule...
your project status end of 10th day.Discuss the status of this project in terms of schedule and budget using EVM.What is your estimate budget at completion if your performance continuous as is planned?Based on the current performance update the expected completion time,and how efficiently must we work from on to complete the project within budget and schedule?
A zero-coupon Treasury bill maturing in 150 days is trading at $98 per $100 face value....
A zero-coupon Treasury bill maturing in 150 days is trading at $98 per $100 face value. Determine the following rates for the T-bill: Dealer’s annual discount yield? (use 360-day count convention) Yield to maturity? (Use an actual 365-day count convention) Logarithmic return (use an actual 365-day count convention)
A project cost $650 and has cash flows of $150 for the first year, $100 for...
A project cost $650 and has cash flows of $150 for the first year, $100 for the second year, and $80 in each of the subsequent years. What is the payback period of the project?
The Project Status Report Meeting You are driving to a project status report meeting with your...
The Project Status Report Meeting You are driving to a project status report meeting with your client. You encountered a significant technical problem on the project that has put your project behind schedule. This is not good news because completion time is the number one priority for the project. You are confident that your team can solve the problem if they are free to give their undivided attention to it and that with hard work you can get back on...
The EV for a project is $100,000 and the PV is $60,000. What is the SPI?...
The EV for a project is $100,000 and the PV is $60,000. What is the SPI? Select one: a. Cannot calculate SPI with info given. b. 0.6 c. 1.66 d. 1.52 Activity A is worth $500, is finished, and cost $500 to do. Activity B is worth $1000, is 75% finished, and has cost $700 to do so far. Activity C is worth $100, is 50% finished, and has cost $90 to do so far. What is the total EV...
Perimeter Road has 4 streetlights. A streetlight burns out after an average of 100 days of...
Perimeter Road has 4 streetlights. A streetlight burns out after an average of 100 days of use (exponentially distributed). It takes an average of 10 days to replace a burned-out street lamp (exponentially distributed). Model the number of functioning streetlights as a birth-and-death process. (a) What is the long-run proportion of time that all streetlights are burned out? (b) On average how many streetlights are illuminating the Perimeter Road?
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT