Question

In: Economics

The EV for a project is $100,000 and the PV is $60,000. What is the SPI?...

The EV for a project is $100,000 and the PV is $60,000.

What is the SPI?

Select one:

a. Cannot calculate SPI with info given.

b. 0.6

c. 1.66

d. 1.52

Activity A is worth $500, is finished, and cost $500 to do.

Activity B is worth $1000, is 75% finished, and has cost $700 to do so far.

Activity C is worth $100, is 50% finished, and has cost $90 to do so far.

What is the total EV for the project?

Select one:

a. -$1075

b. $1300

c. $1075

d. $1600

Activity A is worth $500, is finished, and cost $500 to complete.

Activity B is worth $1000, is 75% finished, and has cost $700 so far.

Activity C is worth $100, is 50% finished, and has cost $90 so far.

What is the CPI for the project?

Select one:

a. 0.83

b. -1.01

c. 1.01

d. -0.83

Which of the following is a measure of the remaining amount that needs to be spent on the project based on current spending efficiency?

Select one:

a. Estimated cost to completion

b. Cost Performance Index

c. Budget remaining

d. Cost variance

Activity A is worth $100, is finished, and cost $150 to complete.

Activity B is worth $500, is 25% finished, and has cost $400 so far.

Activity C is worth $500, is 75% finished, and has cost $100 so far.

Assuming current variances are typical of future variances, what is the estimated cost at completion for this project?

Select one:

a. $750

b. $880

c. $1375

d. $1200

If the CPI is 1.4 and the SPI is 2.0, what is the status of the project?

Select one:

a. Over budget and ahead of schedule

b. Over budget and behind schedule

c. Under budget and ahead of schedule

d. Under budget and behind schedule

Earned value analysis has produced the following numbers: EV = 523,000, AC = 623,000, PV = 643,000.

What are the CV and SV?

Select one:

a. CV = 100,000 and SV = 120,000

b. CV = –100,000 and SV = –120,000

c. CV = 120,000 and SV = 100,000

d. CV = –120,000 and SV = –100,000

What is the cost performance index if the earned value is 120 and the actual cost is 100?

Select one:

a. 0.83

b. 1.2

c. 2

d. -20

Earned value analysis has provided information for a project that was recently closed out: CPI = 0.7, SPI = 1.0.

What does this mean?

Select one:

a. The project’s deliverables have all been completed and the project came in on schedule but over budget

b.

The project’s deliverables have all been completed and the project came in ahead of schedule but on budget

c.

The project’s deliverables have all been completed and the project came in behind schedule but on budget

d.

The project has been cancelled while it was being executed and at that time it was behind schedule but on budget

If currently a project is 6 months ahead of schedule, what is the SV?

Select one:

a. SV = 0

b. None of these answers

c. SV > 1

d. SV < 1

Solutions

Expert Solution

SPI is schedule performance index it describes how soon the project will be completed

Earned value describes the value of work generated till today


Related Solutions

a. What is the present value​ (PV) of $60,000 received thirty years from​ now, assuming the...
a. What is the present value​ (PV) of $60,000 received thirty years from​ now, assuming the interest rate is 6​% per​ year? a. 10,447 b.8880 c. 18,282 d. 39,000 b. If $546 invested today yields $600 in one​ year's time, what is the discount​ factor? a. 1.91 b. 0.09 c. 1.82 d. 0.91 c. If the one​-year discount factor is equal to 0.95238​, the interest must be equal​ to: a.5.0% b. 4.5% c.2.5% d.4.0%
Based on the information provided for a one-year project, answer the following questions. PV =$100,000     AC...
Based on the information provided for a one-year project, answer the following questions. PV =$100,000     AC =$60,000     BAC=$125,000    ETC = $100,000 If 75% of the Planned Value was completed to date, what is the Earned Value of the work completed (round to nearest whole number)? What is the Cost Variance (round to nearest whole number)? What is the Schedule Variance (round to nearest whole number)? What is the Cost Performance Index (round to 2 decimals)? What is the Schedule Performance...
Explain PV, AC, and EV, and how they are used to determine the variance AV, SV,...
Explain PV, AC, and EV, and how they are used to determine the variance AV, SV, CV, and TV. Explain the meaning of these variances?
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Question - Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?  The answer is...
You placed $50,000 of insurance with company A, $60,000 of insurance with company B and $100,000...
You placed $50,000 of insurance with company A, $60,000 of insurance with company B and $100,000 of insurance with company C. Suppose the actual loss is $200,000, how much should each company pay you according to pro-rata liability provision and contribution by equal shares provision respectively?
A proton with initial kinetic energy 50.0 eV encounters a barrier of height 70.0 eV. What...
A proton with initial kinetic energy 50.0 eV encounters a barrier of height 70.0 eV. What is the width of the barrier if the probability of tunneling is How does this compare with the barrier width for an electron with the same energy tunneling through a barrier of the same height with the same probability ?
You currently have $60,000 in your bank account and you will need a total of $100,000...
You currently have $60,000 in your bank account and you will need a total of $100,000 in 5 years to pay for a down payment on a house. What interest rate do you need to earn in order to have $100,000 in your bank account 5 years from now?
George pays 100,000 today for a 4-year investment that returns cash flows of 60,000 at the...
George pays 100,000 today for a 4-year investment that returns cash flows of 60,000 at the end of each years 3 and 4. Suppose that, at 15%, the net present value of George's cash flows is equal to the net present value fo Joe's cash flows, where Joe makes an investment of X one year from today that returns cash flows of 60,000 at the end of each of years 4 and 5. Calculate X.
Mutually exclusive Projects Project A Project B Project C Initial cash Outlay        (50,000)       (60,000)...
Mutually exclusive Projects Project A Project B Project C Initial cash Outlay        (50,000)       (60,000)        (40,000) Required Rate of Return 11% 8% 13% Cash Flows:       Inflow Year 1 10,000 30000 8,000 Inflow Year 2 15,000 50000 20,000 Inflow Year 3 20,000 5000 20,000 Inflow Year 4 25,000 5000 20,000 Inflow Year 5 30,000 2000 15,000 Step 1 Your first assignment as a financial analysis manager at Caledonia Products is to evaluate three new capital budget proposals. You have...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT