Question

In: Advanced Math

your project status end of 10th day.Discuss the status of this project in terms of schedule...

your project status end of 10th day.Discuss the status of this project in terms of schedule and budget using EVM.What is your estimate budget at completion if your performance continuous as is planned?Based on the current performance update the expected completion time,and how efficiently must we work from on to complete the project within budget and schedule?

Solutions

Expert Solution

Solution:

BC = Budgeted cost for activity

PV = Planned Value at the end of period t

EV = Earned value at the end of period t or amount of money budgeted for the work that has been performed till date. (% complete x BC)

AC = Actual Cost

CV = Cost variance = EV – AC

SV = Schedule Variance = EV – PV

Earned value analysis at the end of day 10

Activity

Budgeted Cost

Expected Complete

Planned Value (PV) till 4 week

% complete till 4 week

EV till 4 week

(% complete x BC)

Actual Cost (AC)

CV

= EV - AC

SV

= EV - PV

Startup

100,000

100%

1*100

=100,000

100%

1*100

= 100,000

105,000

-5,000

0

Construction

325,000

85.71%

0.8571*325000

= 278,558

90%

0.6*250

= 292,500

280,000

12,500

13,942

Finishing

50,000

16.67%

0.1667*50,000

= 8,335

25%

0.5*450

= 12,500

2,500

10,000

4,165

Total

386,893

405,000

387,500

17,500

18,107

CV = Cost variance = EV – AC = 405,000 – 387,500 = 17,500

SV = Schedule Variance = EV – PV = 405,000 - 386,893 = 18,107

Cost performance Index = CPI = EV/AC = 405,000/387,500 = 1.0452

Schedule Performance Index = SPI = EV/PV = 405,000/386,893 = 1.0468

b. The CPI and SPI both are greater than 1, thus, the project is ahead of schedule and under budget

**********************************************************************


Related Solutions

The Project Status Report Meeting You are driving to a project status report meeting with your...
The Project Status Report Meeting You are driving to a project status report meeting with your client. You encountered a significant technical problem on the project that has put your project behind schedule. This is not good news because completion time is the number one priority for the project. You are confident that your team can solve the problem if they are free to give their undivided attention to it and that with hard work you can get back on...
CREATING THE PROJECT SCHEDULE - PROJECT MANAGEMENT Your project sponsor is concerned about the duration of...
CREATING THE PROJECT SCHEDULE - PROJECT MANAGEMENT Your project sponsor is concerned about the duration of your project schedule and thinks that you need to cut some time out of the schedule. He thinks that all of the testing that you have included in the plan is not necessary. How would you respond to this? What are the risks of removing the testing with regard to the overall project?
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Question - Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index...
Question Relates to Project Management TERMS CPI – Cost Performance Index SPI – Schedule Performance Index SV- Schedule Variance CV- Cost Variance Can the CPI and SPI give you a different information about your project that the SV and CV didn’t already give you. I guess what I want to know is if the SV CV are negative result can the CPI AND SPI be 1.0 or greater? Well, the answer to that is straightforward! Right people! Right?  The answer is...
Your friend is asking a $55,000 loan from you with the following repayment schedule: End of...
Your friend is asking a $55,000 loan from you with the following repayment schedule: End of year 1 $ 0 End of year 2 $ 11,000 End of year 3 $ 22,000 End of year 4 $ 33,000 You demand at least 8% return on this loan deal. Answer to the following questions by showing your work using financial calculator keys. (a) Should you enter into this loan based on your PV (or NPV) analysis? (b) What is the expected...
How the time management: Project Schedule, Schedule Monitoring, and Approval of Schedule Changes be used in...
How the time management: Project Schedule, Schedule Monitoring, and Approval of Schedule Changes be used in the real project management?
a) On your sister’s 10th birthday, your parents want to invest a certain amount to enable...
a) On your sister’s 10th birthday, your parents want to invest a certain amount to enable her to withdraw R25 000 every six months from her 18th to her 24th birthday (both birthdays included). Calculate the sum they will have to invest if compounded interest is estimated at 12% per annum, compounded biannually. b) What is the present value of a perpetuity that pays R4 800 per year if the first payment does not begin until four years later and...
Explain the Schedule management in the manhattan project?
Explain the Schedule management in the manhattan project?
As the semester comes to an end and visions of your final project are perculating in...
As the semester comes to an end and visions of your final project are perculating in your head - one last discussion for the road (worth 20 points). I'm sure that most of you took this course because it was either a requirement or you needed an online elective. There are a few of you, that I know from talking to you, have business ideas in mind that would benefit from sales training. But honestly, most people do not seek...
Discuss the various Schedule A Itemized Deductions, the Standard Deductions for each Filing Status, the Additional...
Discuss the various Schedule A Itemized Deductions, the Standard Deductions for each Filing Status, the Additional Standard Deduction, and those taxpayers eligible for the Qualified Business Income Deduction. For Tax Years 2019 and 2020, taxpayers can claim medical and dental expenses that exceed 7.5% of AGI when they itemize on a Schedule A. The citation for the new tax law is the Further Consolidated Appropriations Act, 2020 (Public Law 116-94), which states: SEC. 103. REDUCTION IN MEDICAL EXPENSE DEDUCTION FLOOR....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT