your project status end of 10th day.Discuss the status of this project in terms of schedule and budget using EVM.What is your estimate budget at completion if your performance continuous as is planned?Based on the current performance update the expected completion time,and how efficiently must we work from on to complete the project within budget and schedule?
Solution:
BC = Budgeted cost for activity
PV = Planned Value at the end of period t
EV = Earned value at the end of period t or amount of money budgeted for the work that has been performed till date. (% complete x BC)
AC = Actual Cost
CV = Cost variance = EV – AC
SV = Schedule Variance = EV – PV
Earned value analysis at the end of day 10
Activity |
Budgeted Cost |
Expected Complete |
Planned Value (PV) till 4 week |
% complete till 4 week |
EV till 4 week (% complete x BC) |
Actual Cost (AC) |
CV = EV - AC |
SV = EV - PV |
Startup |
100,000 |
100% |
1*100 =100,000 |
100% |
1*100 = 100,000 |
105,000 |
-5,000 |
0 |
Construction |
325,000 |
85.71% |
0.8571*325000 = 278,558 |
90% |
0.6*250 = 292,500 |
280,000 |
12,500 |
13,942 |
Finishing |
50,000 |
16.67% |
0.1667*50,000 = 8,335 |
25% |
0.5*450 = 12,500 |
2,500 |
10,000 |
4,165 |
Total |
386,893 |
405,000 |
387,500 |
17,500 |
18,107 |
CV = Cost variance = EV – AC = 405,000 – 387,500 = 17,500
SV = Schedule Variance = EV – PV = 405,000 - 386,893 = 18,107
Cost performance Index = CPI = EV/AC = 405,000/387,500 = 1.0452
Schedule Performance Index = SPI = EV/PV = 405,000/386,893 = 1.0468
b. The CPI and SPI both are greater than 1, thus, the project is ahead of schedule and under budget
**********************************************************************