In: Operations Management
Actual Cost, planned value and earned value of the activities of an ongoing project after 5 months and after 8 months are given below. All values and costs are in Rs lakhs. Comment on status of the
a) Activities (Activity delayed/early, activity cost overrun/underrun)
b) status of project and estimated total cost at completion at 5 months and at 8 months.
After 5 months
Activity. EV PV AC Comment
A 10 10 8
B 18 15 12
C 15. 20 25
D 40 30. 35
E 25 25. 25
F 25 20 15
G 10 15 10
After 8 months
Activity EV PV AC Comment
A 20 40 45
B 25 25 20
C 15 30 25
D 70 60 40
E 70 70 80
F 40 40 40
G 30 40 20
Answer a and b :
The formula for checking whether your project is ahead of the schedule or behind the schedule only comes from a easier earner value analysis
Schedule Variance = Earned Value – Planned Value
SV = EV – PV
From the above formula, we can conclude that:
Similarly for cost variance, we need the formula to calculate
Cost Variance = Earned Value – Actual Cost
CV = EV – AC
We can conclude the following from the above formula:
We need to apply the above two formulas for each of the activity and comment
Please Please up vote. Your up vote is so valuable to me. Thank you so much. Please up vote.