Question

In: Operations Management

Actual Cost, planned value and earned value of the activities of an ongoing project after 5...

Actual Cost, planned value and earned value of the activities of an ongoing project after 5 months and after 8 months are given below. All values and costs are in Rs lakhs. Comment on status of the

a) Activities (Activity delayed/early, activity cost overrun/underrun)

b) status of project and estimated total cost at completion at 5 months and at 8 months.

After 5 months   

Activity. EV PV AC Comment   

A 10 10 8   

B 18 15 12

C 15. 20 25

D 40 30. 35

E 25 25. 25

F 25 20 15

G 10 15 10

After 8 months

Activity EV PV AC Comment  

A 20 40 45

B 25 25 20

C 15 30 25

D 70 60 40

E 70 70 80

F 40 40 40

G 30 40 20

Solutions

Expert Solution

Answer a and b :

The formula for checking whether your project is ahead of the schedule or behind the schedule only comes from a easier earner value analysis

Schedule Variance = Earned Value – Planned Value

SV = EV – PV

From the above formula, we can conclude that:

  • You are ahead of schedule if the Schedule Variance is positive.
  • You are behind schedule if the Schedule Variance is negative.
  • You are on schedule if the Schedule Variance is zero.

Similarly for cost variance, we need the formula to calculate

Cost Variance = Earned Value – Actual Cost

CV = EV – AC

We can conclude the following from the above formula:

  • You are under budget if the Cost Variance is positive.
  • You are over budget if the Cost Variance is negative.
  • You are on the budget if the Cost Variance is zero.

We need to apply the above two formulas for each of the activity and comment

Please Please up vote. Your up vote is so valuable to me. Thank you so much. Please up vote.


Related Solutions

A variance is the difference between a budgeted, planned, or standard cost and the actual amount...
A variance is the difference between a budgeted, planned, or standard cost and the actual amount incurred/sold. Variances can be computed for both costs and revenues. Identify and explain the types of variance analysis tools, which can be used in a production department of a manufacturing company, which specialises in spare parts for cars
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly)...
Earned Value Management (EVM) is a project management technique for measuring project performance (schedule, cost mainly) and progress in an objective manner in terms of work achieved (Value): The data identified below was listed in a project’s status report. At time of status report: Planned Value of work (PV) = $70,000 Earned Value of work performed (EV) = $50,000 Actual Cost of work performed (AC) = $75,000 Original Planning: Budgeted cost At Completion (BAC) = $110,000 Original length of the...
Build an Earned Value Management (EVM) model using these variables: Planned Value: $45,000 i.Note for understanding,...
Build an Earned Value Management (EVM) model using these variables: Planned Value: $45,000 i.Note for understanding, this based on time, and what we expected to use based on time.  Your schedule variance is based on earned and planned. Actual Cost: $39,500 Earned Value (how much has been spent based on planned costs) : $43,500 i.Note for understanding, this usually based on expected costs at the task level.  In other words, for the tasks complete the project was expected to use this much...
An earned value analysis (EVA) is performed after Month 10 on a 15-month commercial building project...
An earned value analysis (EVA) is performed after Month 10 on a 15-month commercial building project with an estimated final cost (BAC) of $8.45 million. The values at the data date are as follows: EV = $5.25M, AC = $4.95M, and PV = $6.50M. What are the cost and schedule variances and indices? What is the projected final cost (EAC)? All things being equal, what will be the final duration (FD)? It is acceptable to use SPI to estimate the...
The status of a project after 100 days and after 150 days is as follows. (EV-Earned...
The status of a project after 100 days and after 150 days is as follows. (EV-Earned Value, PV-Planned Value, AC-Actual Cost in Rs). Determine the time and cost overruns and underruns of: The project Of each activity after 100 days and after 150 days. Show all calculations. Status after 100 days Status after 150 days Activity EV PV AC EV PV AC A 80 100 200 200 200 250 B 120 200 80 120 300 80 C 300 500 350...
What are the benefits to earned value managment in a project setting?
What are the benefits to earned value managment in a project setting?
What are the benefits to earned value managment in a project setting?
What are the benefits to earned value managment in a project setting?
When the amount that has been earned (BCWP) is consistently below the actual cost to date...
When the amount that has been earned (BCWP) is consistently below the actual cost to date (ACWP), it can be concluded that the project is under cost. True False QUESTION 2 16.6       The main purpose of an audit of a construction company’s financial statements is to: Confirm that the statement was prepared in accordance with GAAP rules Prepare income tax returns Check the arithmetic used in the financial statement Find employee malfeasance QUESTION 3 16.5       From the project lifecycle, we can learn...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT