Question

In: Finance

1. The following cash flows are given for the Project Z _________________________________________________________             C0            C1&

1. The following cash flows are given for the Project Z

_________________________________________________________

            C0            C1            C2            C3            C4               C5

         -$7000    +$3,000   +$4,000   +$6,000     +$2,500      +$2,000

_________________________________________________________

Calculate the following:     (a) NPV (Net Present Value) at 12% discount rate  
                                             (b) IRR (Internal Rate of Return)  

                                             (c) The payback period for Project (Z)

Solutions

Expert Solution

a) Net Present Value (NPV) : NPV is the sum of present value of all Cash inflows and Casho outflows of a project.

Compuation Net Present Value for Project Z

Year Cash Flows Present Value Factor @12% Present Value of Cash Flows
0 $(7,000) 1 $(7,000)
1 $3,000 0.8929 $2,678.7
2 $4,000 0.7972 $3,188.8
3 $6,000 0.7118 $4,270.8
4 $2,500 0.6335 $1,583.75
5 $2,000 0.5674 $1,134.8
NPV $5,856.8

Ans : NPV of the Project is $5856.8

b) Internal Rate of Return (IRR) is the rate at which Present Value of Cash Inflows is equal to Present Value of Cash Flows i.e. NPV is 0.

IRR is calculated by trial and error method

Assumed Discount Rate at 43 %

Year Cash Flows Present Value Factor @43% Present Value of Cash Flows
0 $(7,000) 1 $(7,000)
1 $3,000 0.6993 $2097.9
2 $4,000 0.4890 $1956
3 $6,000 0.3420 $2052
4 $2,500 0.2391 $597.75
5 $2,000 0.1672 $334.4
NPV 38.05

Assumed Discount Rate at 44 %

Year Cash Flows Present Value Factor @43% Present Value of Cash Flows
0 $(7,000) 1 $(7,000)
1 $3,000 0.6944 $2083.2
2 $4,000 0.4823 $1929.2
3 $6,000 0.3349 $2009.4
4 $2,500 0.2326 $581.5
5 $2,000 0.1615 $323
NPV (73.7)

IRR rate is between 43% and 44%.

IRR Rate = 43% + 38.05 / 111.73
= 43 + 0.34
=~43.34%

Ans : IRR of the project is ~43.34%

c) Payback Period


Yr Cash Flows Cumulative Cash Flows
0 $(7,000) $(7,000)
1 $3,000 $(4,000)
2 $4,000 0
3 $6,000 $6,000
4 $2,500 $2,500
5 $2,000 $2,000

Payback Period = 2 years i.e. in 2 year entire intial investment is recovered.

Discounted Payback Period using 12% discount rate

Yr Cash Flows Present Value Factor @ 12% Present Value of Cash Flows Cumulative Present Value of Cash Flows
0 $(7,000) 1 $(7,000) $(7,000)
1 $3,000 0.8929 $2,678.7 $(4321.3)
2 $4,000 0.7972 $3,188.8 $(1132.5)
3 $6,000 0.7118 $4,270.8 $3138.3
4 $2,500 0.6335 $1,583.75 $4722.05
5 $2,000 0.5674 $1,134.8 $5856.85

Discounted PBP = T + CPVCF / PVCF

where,

T = time period where cumulative present value of cash flows was last negative
CPVCF = Cumulative Present Value Cash Flow of Period T
PVCF = Present Value of Cash Flow of the period following the period t

Discounted PBP = Year 2 + $1132.5 / $4270.8
= 2 + 0.265
= 2.265 = ~2.27 years


Related Solutions

1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 =...
1. A project has the following cash flows: C0 = -200,000; C1 = 50,000; C2 = 100,000; C3 = 150,000. If the discount rate changes from 10% to 15%, the CHANGE in the NPV of the project is closest to: A. $23,076 increase B. $23,076 decrease C. $9,667 decrease D. $9,667 increase E. None of the above 2. Companies A and B are valued as follows: Both companies are 100% equity financed. Company A now acquires B by offering two...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
A company is considering a project that has the following cash flows: C0 = -5,000, C1...
A company is considering a project that has the following cash flows: C0 = -5,000, C1 = +900, C2 = +2,500, C3 = +1,100, and C4 = +2,900 with a risk-adjusted discount rate of 12%. a) Calculate the Net Present Value (NPV), Internal Rate of Return (IRR), Profitability Index, and the Payback of this project. b) If you were the manager of the firm, will you accept or reject the project based on the calculation results above?
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −190 +130 +150 +140 The estimated project beta is 1.58. The market return rm is 18%, and the risk-free rate rf is 5%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C
A project has the following forecasted cash flows: Cash    Flows Thousands of dollars C0       C1        C2        C3 -100      40        60        50          The investor expected rate of return is 10%. The cost of capital is 12%. Required: What will you choose to be the discount rate? Why? Please calculate the payback period (PP) and return on investment (ROI). Please calculate NPV,PVI and IRR.. Make decision based on the above calculation and explain the reasons. David said that the profit is the same as...
A project has the following cash flows: C0 - $6,750; C1 - $4,500; C2 - $5,000....
A project has the following cash flows: C0 - $6,750; C1 - $4,500; C2 - $5,000. At a discount rate of 10%, the project’s NPV - $1,473. We learned that as the discount rate is increased, the NPV of a specific project will decrease. How high can the discount rate be before you would reject the project?
Here are the cash flows for a project under consideration: C0 = -$6750 C1 = $4500...
Here are the cash flows for a project under consideration: C0 = -$6750 C1 = $4500 C2 = $18000 A. Calculate the project's net present value for discount rates of 0, 50%, and 100%. B. What is the IRR of the project? Please show work.
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT