Question

In: Finance

Consider the following two mutually exclusive projects withtheir expected Cash Flows ($)Project C0 C1...

Consider the following two mutually exclusive projects with their expected Cash Flows ($)

Project C0 C1   C2 C3

A –$100 +$60 +$60 +$60

B –$100 ------ ------ +$208.35

What is the cross-over rate for these two projects?

a. unknown, because the discount rate is unkown

b. 28%

c. 36%

d. 32%

e. 15%


Solutions

Expert Solution

IRR is the rate at which NPV of the project is 0.

Cross-over rate is a rate at which NPVs of both the projects are equal.

NPV is the sum of present value of the cash flows and the initial capital outlay.

PV of cash flow at time n = Cash flow at time n/ ((1+r)^n)

NPV of Project A = -100+ (60/((1+interest rate)^1)) + (60/((1+interest rate)^2)) + (60/((1+interest rate)^3

NPV of Project B  = -100 + (280.35/((1+interest rate)^3

We equate both the NPVs and solve for the interest rate we will get the cross-over rate

-100+ (60/((1+cross-over rate)^1)) + (60/((1+cross-over interest rate)^2)) + (60/((1+cross-over interest rate)^3 = 100 + (280.35/((1+cross-over interest rate)^3

solvinf for cross-over rate, we get cross-over rate = 15%

Hence, Option e is the answer.


Related Solutions

Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV...
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 12% A −31,000 21,800 21,800 +$5,843 B −51,000 34,000 34,000 +6,462 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 23,000 +$ 10,120 +$ 10,120 +$ 10,120 B − 23,000 0 0 + 31,050 What is the IRR of each project? (Round your answers to 2 decimal places.)
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 21,800 +$ 9,592 +$ 9,592 +$ 9,592 B − 21,800 0 0 + 29,430 What is the IRR of each project? (Round your answers to 2 decimal places.) PRoject A % Project B %
Consider the following two mutually exclusive projects and their Cash Flows ($)
Consider the following two mutually exclusive projects and their Cash Flows ($)Project                                            C0                               C1                               C2                               C3K                                                       –$100                 +$45 +$45 +$60    W                                                     –$150                 +$45 +$45 +$125Which statement is correct based on the above information about Projects K and W?a. If the discount rate is 7.5%, accept project W because the cross-over rate is 9%b. Accept project K, because at a 9% discount rate K and W have the same net present value.c. If the discount rate is 9.5%, reject project K, because the...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800 2,800 0 0 0 0 B −5,600 2,800 2,800 5,800 2,800 2,800 C −7,000 2,800 2,500 0 2,800 2,800 If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV Projects Calculate the payback period for each project. Project A years Project B    years Project C    years Which project(s) would a firm using the payback rule accept...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0   –$ 68,000   –$ 83,000 1 48,000 47,000 2 43,000 56,000 3 38,000 59,000 The cash flows of Project A are expressed in real terms, whereas those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 11 percent and the inflation rate is 5 percent. Calculate the NPV for each project. (Do not round intermediate calculations and round your answers...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0...
Consider the following cash flows on two mutually exclusive projects: Year Project A Project B 0 67000 82000 1 47000 46000 2 42000 55000 3 37000 58000 The cash flows of Project A are expressed in real terms while those of Project B are expressed in nominal terms. The appropriate nominal discount rate is 10 percent and the inflation rate is 2 percent.    Calculate the NPV for each project. (Do not round intermediate calculations and round your answers to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT