Question

In: Finance

Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...

Here are the cash flows for two mutually exclusive projects:

Project C0 C1 C2 C3
A −$ 21,800 +$ 9,592 +$ 9,592 +$ 9,592
B 21,800 0 0 + 29,430


What is the IRR of each project? (Round your answers to 2 decimal places.)

PRoject A %

Project B %

Solutions

Expert Solution


Related Solutions

Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A...
Here are the cash flows for two mutually exclusive projects: Project C0 C1 C2 C3 A −$ 23,000 +$ 10,120 +$ 10,120 +$ 10,120 B − 23,000 0 0 + 31,050 What is the IRR of each project? (Round your answers to 2 decimal places.)
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A...
Consider the following two mutually exclusive projects: Cash Flows ($) Project C0 C1 C2 C3 A -$100 +$60 +$60 +$60 B -$100 ---- ---- +$208.35 Calculate the NPV of each project for a discount rate of 14%. What is approximately the IRR for each project individually? Use the IRR cross-over method to determine which of the projects you should accept (describe the correct decision rule describing when you pick A versus B based on what discount rate).
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV...
Consider two mutually exclusive projects A and B: Cash Flows (dollars) Project C0 C1 C2 NPV at 12% A −31,000 21,800 21,800 +$5,843 B −51,000 34,000 34,000 +6,462 a. Calculate IRRs for A and B. (Do not round intermediate calculations. Enter your answers as a percent rounded to 2 decimal places.)
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,000 2,000 0 0 0 0 B −4,000 2,000 2,000 5,000 2,000 2,000 C −5,000 2,000 1,300 0 2,000 2,000 a. If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,500 2,500 0 0 0 0 B −5,000 2,500 2,500 5,500 2,500 2,500 C −6,250 2,500 2,500 0 2,500 2,500 a. If the opportunity cost of capital is 9%, which project(s) have a positive NPV? Positive NPV project(s) Project A Project B Project C Projects A and B Projects A and C Projects B and C Projects A, B, and C No project b. Calculate...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800...
Consider the following projects: Cash Flows ($) Project C0 C1 C2 C3 C4 C5 A −2,800 2,800 0 0 0 0 B −5,600 2,800 2,800 5,800 2,800 2,800 C −7,000 2,800 2,500 0 2,800 2,800 If the opportunity cost of capital is 12%, which project(s) have a positive NPV? Positive NPV Projects Calculate the payback period for each project. Project A years Project B    years Project C    years Which project(s) would a firm using the payback rule accept...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4...
Cash flows of Project A and B are as following: Project C0 C1 C2 C3 C4 C5 A -9000 2000 3000 4000 5000 6000 B -11000 2000 3000 4000 5000 6000          Compute the payback periods for the following two projects.          Payback period for A = _________ years; for B __________years          If the discount rate is 10%, what is the discounted payback period?          Discounted payback period for A=_________ years; for B __________years
Consider the following two mutually exclusive projects withtheir expected Cash Flows ($)Project C0 C1...
Consider the following two mutually exclusive projects with their expected Cash Flows ($)Project C0 C1   C2 C3A –$100 +$60 +$60 +$60B –$100 ------ ------ +$208.35What is the cross-over rate for these two projects?a. unknown, because the discount rate is unkownb. 28%c. 36%d. 32%e. 15%
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −155 +95 +115 +105 The estimated project beta is 1.51. The market return rm is 15%, and the risk-free rate rf is 3%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3...
A project has the following forecasted cash flows: Cash Flows ($ thousands) C0 C1 C2 C3 −125 +67 +85 +75 The estimated project beta is 1.55. The market return rm is 17%, and the risk-free rate rf is 7%. a. Estimate the opportunity cost of capital and the project’s PV (using the same rate to discount each cash flow). (Do not round intermediate calculations. Enter your cost of capital answer as a percent and enter your PV answer in thousands....
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT