Question

In: Accounting

Essan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

Essan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.8 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period.

2020 2021 2022
Cost to date $800,000 $1,800,000 $2,3500,000
Estimated costs to complete $1,700,000 $600,000 0
Progress billings to date (non-refundable) $850,000 $2,300,000 $2,800,000
Cash collected to date $700,000 $2,200,000 $2,800,00

(A) Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

2020 2021 2022
Gross profit / (loss) $ $ $

(B) Using the percentage-of-completion method, prepare the journal entries for 2020 and 2021. (Use Materials, Cash, Payables for costs incurred to date.) (Credit account titles are automatically indented when amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts.)

For Year 2020:

Account Titles and Explanations Debit Credit
(To record cost of construction)
(To record progress billings)
(To record collections)
(To record revenues)
(To record construction expenses)

For Year 2021:

Account Titles and Explanation Debit Credit
(To record cost of construction)
(To record progress billings)
(To record collections)
(To record revenues)
(To record construction expenses)

(C) Using the percentage-of-completion method, what is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021? (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

December 31,2020 December 31, 2021
Balance in the Contract Asset/Liability account
$ $

(D)

Solutions

Expert Solution

ANSWER

Essan Construction Inc.
A) Calculation of Gross Profit
Particulars 2020 2021 2022
Contract Price          2,800,000          2,800,000          2,800,000 A
Cost Incurred to date             800,000          1,800,000          2,350,000 D
Estimated cost to complete          1,700,000             600,000                        -   C
Cost Incurred during the year             800,000          1,000,000             550,000 B
Estimated total cost          2,500,000          2,400,000          2,350,000 E=C+D
Percentage complete 32.00% 75.00% 100.00% F=D/E
(Cost Incurred to date/Estimated total cost)
Revenue to be recognized             896,000          1,204,000             700,000 G
(Contract Price*Percentage complete)- revenue previously recognized
Year 2020: 32% completed. Revenue recognized = 32% x $ 2,800,000 = $ 896,00.
Year 2021: 75% completed. Revenue recognized = 75% x $ 2,800,000 – $ 896,000 (previously recognized) = $ 1,204,000.
Year 2022: 100% completed. Revenue recognized = 100% x $ 2,800,000 – $ 896,00- $ 1,204,000 (previously recognized) = $ 700,000.
Gross Profit/(Loss)               96,000             204,000             150,000 H=G-B
Billings to date             850,000          2,300,000          2,800,000
Billings during the year       850,000.00    1,450,000.00       500,000.00
Cash collection to date             700,000          2,200,000          2,800,000
Collection during the year       700,000.00    1,500,000.00       600,000.00
2020 2021
B) Journal Entries Debit $ Credit $ Debit $ Credit $
Costs Incurred CIP (Work-in-progress)       800,000 1,000,000
Cash       800,000     1,000,000
Billing Accounts Receivable       850,000 1,450,000
Billing on CIP       850,000     1,450,000
Receiving Payments Cash       700,000 1,500,000
Accounts Receivable       700,000     1,500,000
Period end adjustments for Revenue Construction Expense       800,000
(Gross Profit entry) CIP (Work-in-progress)         96,000
Construction Revenue       896,000
Period end adjustments for Revenue Construction Expense 1,000,000
(Gross Profit entry) CIP (Work-in-progress)      204,000
Construction Revenue     1,204,000

================

DEAR STUDENT,

IF YOU HAVE ANY QUERY PLEASE ASK ME IN THE COMMENT BOX,I AM HERE TO HELP YOU.PLEASE GIVE ME POSITIVE RATING..

****************THANK YOU****************


Related Solutions

Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...
Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to construct an electric generator for Blue Spruce Corporation. At the contract date, Larkspur estimated that it would take two years to complete the project at a cost of $2,440,000. The fixed fee stipulated in the contract was $549,000. Larkspur appropriately accounts for this contract under the percentage-of-completion method. During 2020, Larkspur incurred costs of $976,000 related to this project. The estimated cost at December...
Crane Ltd., which has a calendar year end, entered into an equipment lease on June 1,...
Crane Ltd., which has a calendar year end, entered into an equipment lease on June 1, 2020, with GH Financing Limited. The lease term is two years and requires payments of $2,600 at the end of each month beginning September 30. The stated rate of interest in the lease is 6%. As an incentive for entering into the contract, GH has agreed to forgive the first three payments under the lease (June, July, and August). Calculate the amount that Crane...
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
Ballan Ltd entered into a non-cancellable lease agreement with Manufacturer Ltd to lease construction equipment from...
Ballan Ltd entered into a non-cancellable lease agreement with Manufacturer Ltd to lease construction equipment from Manufacturer Ltd under the following terms: Lease term 9 years Useful life of leased asset 11 years Expected residual value at end of lease $6,000 Lease payment at inception (beginning) $7,000 Lease payments (at end of each year) $5,000 per annum (9 payments) Implicit interest rate for lease 11% Fair Value of Equipment $37,031 Present Value of minimum lease payments $34,685 Ballan does not...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,020,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,020,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,480,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,600,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT