On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to construct an electric generator for Blue Spruce Corporation. At the contract date, Larkspur estimated that it would take two years to complete the project at a cost of $2,440,000. The fixed fee stipulated in the contract was $549,000. Larkspur appropriately accounts for this contract under the percentage-of-completion method. During 2020, Larkspur incurred costs of $976,000 related to this project. The estimated cost at December 31, 2020, to complete the contract is $1,464,000. Blue Spruce was billed $732,000 under the contract. The billings are non-refundable.

(a)

Correct answer iconYour answer is correct.

Calculate the amount of gross profit to be recognized by Larkspur under the contract for the year ended December 31, 2020. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

Gross profit / (loss) $

eTextbook and Media

List of Accounts

  

Attempts: 2 of 3 used

(b)

Show how the contract will be reported on the income statement for the year ended December 31, 2020. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45).)

LARKSPUR INC.
Partial Income Statement

                                                                      Quarter Ended December 31, 2020Year Ended December 31, 2020Month Ended December 31, 2020
$
select a summarizing line for the first part                                                                      ExpensesNet Income / (Loss)Total RevenuesGross Profit / (Loss)Total ExpensesRevenuesOther Expenses and LossesOperating ExpensesIncome from OperationsDividends $

eTextbook and Media

List of Accounts

Save for Later

Last saved 19 minutes ago.

Saved work will be auto-submitted on the due date.

Attempts: 0 of 3 used

  

Solutions

Expert Solution

ANSWER

A)

Contract price [$2,440,000+ $549,000]

$2,989,000

Cost to date

$976,000

Estimated cost

$1,464,000

Total estimated cost

$2,440,000

Estimated gross profit

$549,000

[$2,989,000- $2,440,000]

Percentage of completion [$2,440,000 * 0.40]   

$976,000

                                                                                   

Gross profit recognized 2020           40% of $549,000 = $219,600

Gross Profit recognized in 2020 = $219,600

------------------------------------------

AS PER CHEG RULE WE ANSWER ONLY ONE QUESTION PER POST,KINDLY POST REMANING ONE.

================

DEAR STUDENT,

IF YOU HAVE ANY QUERY PLEASE ASK ME IN THE COMMENT BOX,I AM HERE TO HELP YOU.PLEASE GIVE ME POSITIVE RATING..

****************THANK YOU****************


Related Solutions

Cost Plus Incentive Fee Calculation. In this cost plus incentive fee contract, the cost is estimated at $210,000 and the fee at $25,000.
Cost Plus Incentive Fee Calculation. In this cost plus incentive fee contract, the cost is estimated at $210,000 and the fee at $25,000. The project is complete, and the buyer has agreed that the costs were, in fact, $200,000. Because the seller's costs came in lower than the estimated costs, the seller shares in the savings: 80% to the buyer and 20% to the seller. Calculate the final fee and final price.The answer is :Fee $27,000Price: $227,000
A. You have signed a cost plus fixed fee (CPFF) contract with a supplier to perform...
A. You have signed a cost plus fixed fee (CPFF) contract with a supplier to perform some work for you. The contract parameters include: Estimated Cost: $100,000 Fixed Fee: $10,000 If the seller is able to complete the work for a cost of $80,000, what will be the final price paid to the seller? B. You have signed a cost plus percentage cost (CPPC) contract with a supplier to perform some work for you. The contract parameters include the following:...
ACCOUNTING FOR LEASES    Mickey’s Garage entered into a non-cancellable, five-year lease agreement on 1 April...
ACCOUNTING FOR LEASES    Mickey’s Garage entered into a non-cancellable, five-year lease agreement on 1 April 2020 for an item of machinery. The machinery is expected to have an economic life of seven years, after which it will have no salvage or residual value and ownership is transferred at the end of the lease. Mickey’s Garage is to make five annual payments of $100,000 (to be made at the end of the year). The rate of interest implicit in the...
Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...
Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Costs to date $848,000 $1,871,250 $2,428,000 Estimated costs to complete 1,802,000 623,750 0 Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000 Cash collected to...
Essan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...
Essan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.8 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Cost to date $800,000 $1,800,000 $2,3500,000 Estimated costs to complete $1,700,000 $600,000 0 Progress billings to date (non-refundable) $850,000 $2,300,000 $2,800,000 Cash collected to...
1) Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $9,000,000 and the target fee is $850,000.
1) Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $9,000,000 and the target fee is $850,000. The project is over, and the buyer has that the costs were, in fact, $8,000,000. Because the seller's cost came in lower than the estimated costs, the seller shares in the savings: 70% to the buyer and 30% to the seller. The ceiling price is $12,500,000. Calculate the final fee and final priceFee $1,150,000...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000,...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000, and a fixed fee of $1,000. Any cost overruns or underruns will be shared between the buyer and the seller by 50% and 50%, respectively. When the actual cost of $8,000 is incurred, how much will the supplier get paid in total?
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000,...
In a cost-plus-incentive-fee contract, a buyer and a seller agreed on a target cost of $7,000, and a fixed fee of $1,000. Any cost overruns or underruns will be shared between the buyer and the seller by 50% and 50%, respectively. When the actual cost of $8,000 is incurred, how much will the supplier get paid in total?
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000.
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000. The project is over, and the buyer has that the costs were, in fact, $210,000. Because the seller's cost came in higher than the estimated costs, the seller shares in the added cost: 60% to the buyer and 40% to the seller. The ceiling price is $200,000. Calculate the point of total assumption.$183,333
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000.
Fixed Price Incentive Fee Calculation. In this fixed price incentive fee contract, the target cost is estimated at $150,000 and the target fee is $30,000. The project is over, and the buyer has that the costs were, in fact, $210,000. Because the seller's cost came in higher than the estimated costs, the seller shares in the added cost: 60% to the buyer and 40% to the seller. The ceiling price is $200,000. Calculate the final price.$200,000
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT