Question

In: Accounting

Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...

Crane Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.9 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period.

2020 2021 2022
Costs to date $848,000 $1,871,250 $2,428,000
Estimated costs to complete 1,802,000 623,750 0
Progress billings to date (non-refundable) 890,000 2,378,000 2,900,000
Cash collected to date 748,000 2,271,000 2,900,000

Using the percentage-of-completion method, calculate the estimated gross profit that would be recognized during each year of the construction period.

CRANE CONSTRUCTION INC.
STATEMENT OF GROSS PROFIT
2020 2021 2022 Total
Revenue $928,000 $1,247,000 $725,000 $2,900,000
Costs ($848,000) ($1,023,250) ($556,750) ($2,428,000)
Gross profit $80,000 $223,750 $168,250 $472,000

Using the percentage-of-completion method, prepare the journal entries for 2020 and 2021. (Use Materials, Cash, Payables for costs incurred to date.)

For the Year 2020:

1-

2-

(To record Cost of Construction)

1-

2-

To record progress billings

1-

2-

To record collections

1-

2-

To record revenues

1-

2-

To record construction expenses

Same procedures for 2021:

Solutions

Expert Solution

following are the calculations as per percentage methods or degree of completion method

journal entries:


Related Solutions

Essan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price...
Essan Construction Inc., which has a calendar year end, has entered into a non-cancellable fixed price contract for $2.8 million beginning September 1, 2020, to build a road for a municipality. It has been estimated that the road construction will be complete by June 2022. The following data pertain to the construction period. 2020 2021 2022 Cost to date $800,000 $1,800,000 $2,3500,000 Estimated costs to complete $1,700,000 $600,000 0 Progress billings to date (non-refundable) $850,000 $2,300,000 $2,800,000 Cash collected to...
Crane Ltd., which has a calendar year end, entered into an equipment lease on June 1,...
Crane Ltd., which has a calendar year end, entered into an equipment lease on June 1, 2020, with GH Financing Limited. The lease term is two years and requires payments of $2,600 at the end of each month beginning September 30. The stated rate of interest in the lease is 6%. As an incentive for entering into the contract, GH has agreed to forgive the first three payments under the lease (June, July, and August). Calculate the amount that Crane...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to...
On April 1, 2020, Larkspur Inc. entered into a cost plus fixed fee non-cancellable contract to construct an electric generator for Blue Spruce Corporation. At the contract date, Larkspur estimated that it would take two years to complete the project at a cost of $2,440,000. The fixed fee stipulated in the contract was $549,000. Larkspur appropriately accounts for this contract under the percentage-of-completion method. During 2020, Larkspur incurred costs of $976,000 related to this project. The estimated cost at December...
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
Ballan Ltd entered into a non-cancellable lease agreement with Manufacturer Ltd to lease construction equipment from...
Ballan Ltd entered into a non-cancellable lease agreement with Manufacturer Ltd to lease construction equipment from Manufacturer Ltd under the following terms: Lease term 9 years Useful life of leased asset 11 years Expected residual value at end of lease $6,000 Lease payment at inception (beginning) $7,000 Lease payments (at end of each year) $5,000 per annum (9 payments) Implicit interest rate for lease 11% Fair Value of Equipment $37,031 Present Value of minimum lease payments $34,685 Ballan does not...
On January 1, 2020, Crane Corp., which uses IFRS, signs a 10-year, non-cancellable lease agreement to...
On January 1, 2020, Crane Corp., which uses IFRS, signs a 10-year, non-cancellable lease agreement to lease a specialty lathe from Liu Inc. The following information concerns the lease agreement. 1. The agreement requires equal rental payments of $76,195 beginning on January 1, 2020. 2. The lathe’s fair value on January 1, 2020, is $500,000. 3. The lathe has an estimated economic life of 12 years, with an unguaranteed residual value of $18,000. Crane Corp. depreciates similar equipment using the...
n January 1, 2020, Crane Corp., which uses IFRS, signs a 10-year, non-cancellable lease agreement to...
n January 1, 2020, Crane Corp., which uses IFRS, signs a 10-year, non-cancellable lease agreement to lease a specialty lathe from Liu Inc. The following information concerns the lease agreement. 1. The agreement requires equal rental payments of $95,654 beginning on January 1, 2020. 2. The lathe’s fair value on January 1, 2020, is $610,000. 3. The lathe has an estimated economic life of 12 years, with an unguaranteed residual value of $16,000. Crane Corp. depreciates similar equipment using the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,240,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,020,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018,...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2018, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $5,020,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2020. Estimated percentage of completion, accumulated contract costs incurred,...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT