Question

In: Accounting

Construction Contracts A company is constructing a bridge at a fixed price of $15 million over...

Construction Contracts

A company is constructing a bridge at a fixed price of $15 million over three years. The customer remains in control of the bridge throughout the contract. The expected costs and billings are provided below.

Year

1

2

3

Expected Cost

4,000,000

4,500,000

3,500,000

Billings

5,000,000

5,000,000

5,000,000

Required

Assume the percentage of completion CAN be measured reliably.

b.

If the actual cost for Year 2 is $6,500,000 while costs for Year 1 and 3 remain unchanged:

Prepare all journal entries relating the contract for Year 1-3.

Solutions

Expert Solution

Percentage of Completion Method
Illustration year 1 year 2 year 3
Cost Incured to date 4000000 10500000 14000000
Estimated cost to complete 8040000 3480000 0
Estimated Total Contract Cost 4000000 8500000 12000000
Estimated Percentage Complete 33 71 100
Contract price 15000000 15000000 15000000
Revenue Recognizable 4950000 10650000 15000000
Revenue Recognized Prior year 4950000 15600000
Revenue Recognized currently 4950000 15600000 30600000
Cost Incured currently -4000000 -10500000 -16000000
Income Recognized currently 950000 5100000 14600000
Journal Entries for 3 Yrs
Year 1. Year 2. Year 3.
Particulars Dr Cr Dr Cr Dr Cr
Contract In Progesss 4000000 6500000 3500000
Cash 4000000 6500000 3500000
( For inccuring cost)
Accounts Recievable 5000000 5000000 5000000
Billing on Contract in Progress 5000000 500000 5000000
(for Billing)
Cash Account 5000000 500000 5000000
Accounts Recievable 5000000 500000 5000000
(Receiving Payments)
(for Cash receipts)
Billing on Contract in Progress 5000000 5000000 5000000
Profit On contract 1000000 -1500000 1500000
Contract In Progesss 4000000 6500000 3500000
(Completing the Job)

Related Solutions

A construction company entered into a fixed-price contract to build an office building for $28 million....
A construction company entered into a fixed-price contract to build an office building for $28 million. Construction costs incurred during the first year were $8 million and estimated costs to complete at the end of the year were $12 million. During the first year the company billed its customer $10 million, of which $4 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
A construction company entered into a fixed-price contract to build an office building for $38 million....
A construction company entered into a fixed-price contract to build an office building for $38 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $18 million. During the first year the company billed its customer $14 million, of which $7 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $38 million. Construction...
Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $38 million. Construction costs incurred in the first year were $28 million and estimated remaining costs to complete at the end of the year were $19 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method? (Enter your answer in millions.) How much gross profit or loss will Franklin recognize in...
AZRB is a road bridge construction company. The company plan to build a major road bridge...
AZRB is a road bridge construction company. The company plan to build a major road bridge for its new project. Table shows the process sequence and other related data for the major road bridge development. Table :Activities to construct the bridge, estimated time and crashing cost. Activity Predecessor Time Estimates (Days) Cost (RM per day) Crash cost (RM per day) Optimistic Most Likely Pessimistic Maximum crash time (days) a m b A - 65 73 90 100 150 6 B...
Belgium Co. is constructing a tunnel for 800 million. Construction began in 2011 and is estimated...
Belgium Co. is constructing a tunnel for 800 million. Construction began in 2011 and is estimated to be completed in 2016. At December 31, 2013, Belgium has incurred costs totaling 356 million with 85 million of that incurred in 2013, 143 in 2012, and 128 in 2011. Belgium received 356 million in total progress payments to date but future activity is tenuous and its cost numbers are highly uncertain. What amount of revenue should Belgium Co. recognize for the year...
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
Helmet Head Construction (HHC) is building a bridge for $12 million at a total cost of...
Helmet Head Construction (HHC) is building a bridge for $12 million at a total cost of $10 million over the next three years. The company uses percentage of completion method to recognize revenue. Below is a summary of the contract: 2016 2017 2018 Costs to Date 3,600,000 7,450,000 10,450,000 Estimated Costs to Complete 6,400,000 3,000,000 - Progress Billings During the year 4,000,000 4,000,000 4,000,000 Cash collected during the year 3,250,000 3,250,000 5,500,000 Record the necessary journal entries to account for...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is...
Long-term Contracts Koolman Construction Company began work on a contract in 2017. The contract price is $3,000,000, and the company determined that its performance obligation was satisfied over time. Other information relating to the contract is as follows: 2017 2018 Costs incurred during the year $ 600,000 $ 700,000 Estimated costs to complete, December 31 $1,400,000 $1,200,000 Billings during the year $500,000 $850,000 Collections during the year $400,000 $800,000 Required: 1. Compute the gross profit or loss recognized in 2017...
EBC is a construction company. They are in the process of constructing a building whose plumbing...
EBC is a construction company. They are in the process of constructing a building whose plumbing would be installed in 12 days at a cost of $ 64 or in 10 days at a cost of $ 80 by working overtime. Plumbing is on the critical path and each day’s saving in completion time of the whole project is worth $ 10. a) You have been asked to advise the project team on whether to take the 10 day or...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT