Question

In: Finance

EBC is a construction company. They are in the process of constructing a building whose plumbing...

EBC is a construction company. They are in the process of constructing a building whose plumbing would be installed in 12 days at a cost of $ 64 or in 10 days at a cost of $ 80 by working overtime. Plumbing is on the critical path and each day’s saving in completion time of the whole project is worth $ 10.

a) You have been asked to advise the project team on whether to take the 10 day or the 12-day option. Using relevant computation, present your piece of advice.

b) Highlight the elements of ‘trade-off’ expressed in the above case.

c) Assume each day’s saving in completion time is worth $ 5. What advice would you give? Give reasons for your answer

Solutions

Expert Solution

Answer a) If team opts for option of 12 days then cost will be $64

If team opts for option of 10 days then cost will be $80

Saving in cost due to opting of option of 12 days is = $16

Since it take 2 days more (i.e. 12days instead of 10days ) to complete the work so there is oppurtinity cost for this . Each day saving in completion time is $10 . But we have taken 2 days more if opt for 12 day option so we have lost $20($10*2) for extra days we have taken if we opt for 12 days option .

Hence for option of 12days total cost will be = $64+$20 = $84

And for option of 10 days cost is= $80

So it is advisable to opt for option of days as in that case there is saving of $4

Answer b) The elements of trade off shown in above question are Time,Cost and quality . Since time ,qualitty and cost are interdependent parameters in a poject. If construction time is shortened , then project cost should be added. Also he might loose profit if he fails to implement project in right quality,time and cost .

Answer c) if each day saving in completion time is worth $5 then oppurtunity cost if opt for option of 12days is $10 ($5*2)

So

Total Cost for option of 12 days is = $64+$10= $74

Total Cost for option of 10 days is= $80

So it is advisable to opt for option of 12 days if saving per day in completion time is $5


Related Solutions

Company Corp. is constructing a building. The following information pertains to the construction of the building....
Company Corp. is constructing a building. The following information pertains to the construction of the building. prepare journal entries 1) On 1/1/2015, company borrows $2,400,000 at 12% for 8 years to finance the new construction project. Payments are due quarterly with the first due date falling on 3/31/2015. Prepare the journal entries for each quarter’s payment. 2) Expenditures made on the project during 2015 are as follows: 1/1/2015 of $300,000; 5/1/2015 of $400,000; 7/1/2015 of $1,100,000; 10/1/2015 of $400,000. Journalize...
X Company is constructing a building. Construction began in 2018 and the building was completed 31...
X Company is constructing a building. Construction began in 2018 and the building was completed 31 December, 2018. X made payments to the construction company of $1,000,000 on 1 July, $2,100,000 on 1 September, and $2,000,000 on 31 December. Average accumulated expenditures were ------. Select one: a. $5,100,000. b. $1,200,000. c. $3,100,000. d. $1,025,000. The treasury stocks should be deducted from the stockholder’s equity. Select one: a. True. b. False.
Sandhill Company is constructing a building. Construction beganon February 1 and was completed on December...
Sandhill Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $2,700,000 on March 1, $1,800,000 on June 1, and $4,500,000 on December 31.Sandhill Company borrowed $1,500,000 on March 1 on a 5-year, 10% note to help finance construction of the building. In addition, the company had outstanding all year a 12%, 5-year, $3,000,000 note payable and an 11%, 4-year, $5,250,000 note payable. Compute avoidable interest for Sandhill Company. Use the weighted-average...
Arlington Company is constructing a building. Construction began on January 1 and was completed on December...
Arlington Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Arlington Company borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable. What is the avoidable interest for Arlington Company?
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December...
Sheridan Company is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6380000 on March 1, $5290000 on June 1, and $8650000 on December 31. Sheridan Company borrowed $3240000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6410000 note payable and an 11%, 4-year, $12850000 note payable. What is the avoidable interest for Sheridan Company?
Novak Company is constructing a building. Construction began on February 1 and was completed on December...
Novak Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $1,944,000 on March 1, $1,224,000 on June 1, and $3,072,650 on December 31. Compute Novak’s weighted-average accumulated expenditures for interest capitalization purposes. Weighted-Average Accumulated Expenditures = $
Skysong Company is constructing a building. Construction began on February 1 and was completed on December...
Skysong Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $3,240,000 on March 1, $2,160,000 on June 1, and $5,400,000 on December 31. Skysong Company borrowed $1,800,000 on March 1 on a 5-year, 10% note to help finance construction of the building. In addition, the company had outstanding all year a 12%, 5-year, $3,600,000 note payable and an 11%, 4-year, $6,300,000 note payable. Compute avoidable interest for Skysong Company. Use the...
Bramble Company is constructing a building. Construction began on February 1 and was completed on December...
Bramble Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $3,600,000 on March 1, $2,400,000 on June 1, and $6,000,000 on December 31. Bramble Company borrowed $2,000,000 on March 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 8%, 5-year, $4,000,000 note payable and an 11%, 4-year, $7,000,000 note payable. Compute avoidable interest for Bramble Company. Use the...
Larkspur Company is constructing a building. Construction began on February 1 and was completed on December...
Larkspur Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $1,920,000 on March 1, $1,200,000 on June 1, and $3,070,300 on December 31. Larkspur Company borrowed $1,041,900 on March 1 on a 5-year, 13% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 5-year, $2,227,300 note payable and an 11%, 4-year, $3,799,000 note payable. Compute avoidable interest for Larkspur Company. Use the...
Riverbed Company is constructing a building. Construction began on February 1 and was completed on December...
Riverbed Company is constructing a building. Construction began on February 1 and was completed on December 31. Expenditures were $5,040,000 on March 1, $3,360,000 on June 1, and $8,400,000 on December 31. Riverbed Company borrowed $2,800,000 on March 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 8%, 5-year, $5,600,000 note payable and an 11%, 4-year, $9,800,000 note payable. Compute avoidable interest for Riverbed Company. Use the...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT