Question

In: Accounting

Belgium Co. is constructing a tunnel for 800 million. Construction began in 2011 and is estimated...

Belgium Co. is constructing a tunnel for 800 million. Construction began in 2011 and is estimated to be completed in 2016. At December 31, 2013, Belgium has incurred costs totaling 356 million with 85 million of that incurred in 2013, 143 in 2012, and 128 in 2011. Belgium received 356 million in total progress payments to date but future activity is tenuous and its cost numbers are highly uncertain. What amount of revenue should Belgium Co. recognize for the year ended December 31, 2013?

A. No revenue should be recognized until the contract is completed in 2016.
B. 356 million.
C. 271 million.
D. 85 million.

Solutions

Expert Solution

Belgium Co. is constructing a tunnel for 800 million. i.e. the construction price to be received by the company is 800 million.

The company is highly uncertain about the cost numbers and future activities of the construction of the tunnel. Therefore the co. cannot (percentage) stage of completion method for recognizing the revenue from the contract.

There are no cost-plus commission rates provided in the contract. Hence cost-plus margin method is also not used for recognizing the revenue.

As the company is uncertain about the future cost of the contract the company should recognize revenue based on cost of construction of the tunnel.

Since the company incurred 85 million in the year ending December 31, 2013 it should recognize option D. 85 million as its revenue.

(Alternatively, the question is silent about recognition of revenue in earlier years. If the company has not recognised any revenue in the year 2011 and 2012, then the comaony should recognize a total of option B. 356 million in the year ending 31 dec 2013.)

Option A. No revenue to be recognise stands incorrect, as accouting is done on the bases of accural and matching concept of expenses and revenue. If we record expense related to a contarct in the current year, than we should also record the revenue relating to that contract.

Option C 271 Million also stands incorrect as it ignores the expense and revenue incurred in the current year.


Related Solutions

Red Man Construction is constructing a building. Construction began on January 1 and was completed on...
Red Man Construction is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Red Man borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable prepare all entries that are necessary
Red Man Construction is constructing a building. Construction began on January 1 and was completed on...
Red Man Construction is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Red Man borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable. what amount of interest should be charged...
Indiana Co. began a construction project in 2016 with a contract price of $150 million to...
Indiana Co. began a construction project in 2016 with a contract price of $150 million to be received when the project is completed in 2018. During 2016, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2017, Indiana incurred additional costs of $63.75 million...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to...
ndiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $58.5 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $90 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2022, Indiana incurred additional costs of $64 million...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to...
Indiana Co. began a construction project in 2021 with a contract price of $164 million to be received when the project is completed in 2023. During 2021, Indiana incurred $38 million of costs and estimates an additional $83 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Indiana: A. Recognized no gross profit or loss on the project...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to...
Indiana Co. began a construction project in 2021 with a contract price of $163 million to be received when the project is completed in 2023. During 2021, Indiana incurred $39 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $59 million and estimated...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to...
Indiana Co. began a construction project in 2021 with a contract price of $161 million to be received when the project is completed in 2023. During 2021, Indiana incurred $37 million of costs and estimates an additional $81 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. In 2022, Indiana incurred additional costs of $57 million and estimated...
(2) Red Man Construction is constructing a building. Construction began on January 1 and was completed...
(2) Red Man Construction is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6,400,000 on March 1, $5,280,000 on June 1, and $8,000,000 on December 31. Red Man borrowed $3,200,000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6,400,000 note payable and an 11%, 4-year, $12,000,000 note payable. What amount of interest should be...
Marigold Corp. is constructing a building. Construction began on January 1 and was completed on December...
Marigold Corp. is constructing a building. Construction began on January 1 and was completed on December 31. Expenditures were $6380000 on March 1, $5250000 on June 1, and $8050000 on December 31. Marigold Corp. borrowed $3250000 on January 1 on a 5-year, 12% note to help finance construction of the building. In addition, the company had outstanding all year a 10%, 3-year, $6450000 note payable and an 11%, 4-year, $12350000 note payable. What amount of interest should be charged to...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT