Question

In: Accounting

A construction company entered into a fixed-price contract to build an office building for $28 million....

A construction company entered into a fixed-price contract to build an office building for $28 million. Construction costs incurred during the first year were $8 million and estimated costs to complete at the end of the year were $12 million. During the first year the company billed its customer $10 million, of which $4 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole dollars.)

Solutions

Expert Solution


Related Solutions

A construction company entered into a fixed-price contract to build an office building for $38 million....
A construction company entered into a fixed-price contract to build an office building for $38 million. Construction costs incurred during the first year were $12 million and estimated costs to complete at the end of the year were $18 million. During the first year the company billed its customer $14 million, of which $7 million was collected before year-end. What would appear in the year-end balance sheet related to this contract using the percentage-of-completion method? (Enter your answers in whole...
Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $38 million. Construction...
Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $38 million. Construction costs incurred in the first year were $28 million and estimated remaining costs to complete at the end of the year were $19 million. How much gross profit or loss will Franklin recognize in the first year if it recognizes revenue over time according to percentage of completion method? (Enter your answer in millions.) How much gross profit or loss will Franklin recognize in...
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building.
Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. Curtiss concludes that the contract does not qualify for revenue recognition over time. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred,...
Problem 3 An entity entered into a construction contract to build a condo building at a...
Problem 3 An entity entered into a construction contract to build a condo building at a fixed price of $54,000,000. Construction started in 20x0 and ended in 20x3. Data on the contract is as follows (in ‘000’s): 20x0 20x1 20x2 20x3 Costs incurred during the year $ 6500 19500 25000 5800 Estimated costs to complete 38500 26000 6500 - Billings 18000 18000 - 18000 For each of the parts below, prepare the ‘mini’ income statement for the project for each...
Bohr Co is a construction company and has entered into a contract with a fixed price...
Bohr Co is a construction company and has entered into a contract with a fixed price of £600,000 during the year ended 30thNovember 20X8.  Bohr Co measures percentage completion using the work certified as a proportion of contract value. The following information relates to the contract: £ Costs incurred to date 360,000 Estimate of the costs to complete the contract 125,000 Value of work certified by independent architect 450,000 Amounts invoiced to client 250,000 Requirement Prepare the relevant Statement of profit...
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,000,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete are $5,000,000. Tullis billed $4,000,000 in year 1 and collected $3,500,000 by the end of the end of the year.
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000....
Tullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $1,600,000 of cost and the engineers determined that the remaining costs to complete are $4,800,000. Tullis billed $3,600,000 in year 1 and collected $3,500,000 by the end of the end of the year. How much gross profit should Tullis recognize in Year 1 assuming the use of the percentage-of-completion method? a. $0 b. $1,050,000 c....
Raider Red Construction entered into a contract to build a commercial building for $3,600,000. Raider Red...
Raider Red Construction entered into a contract to build a commercial building for $3,600,000. Raider Red Construction uses the percentage-of-completion method for recognizing revenue on the project. Construction began in September of 2018 and the building was completed in June of 2020. The company provided the following additional information on the project. 2018 2019 2020 Costs incurred to date $                 725,000 $              2,100,000 $              3,400,000 Estimated costs to complete $              2,175,000 $              1,400,000 $                             -   Billings during the year $                ...
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000.
Stone Age Construction Pte Ltd entered into a construction contract to build a commercial building for Bintang Ltd for $9,200,000. Construction commenced on 1 January 2021. The following details relate to the construction project as at 31 December 2021:                                                   S'000Progress billing to-date             5,520Cash receipt to-date                  5,120Costs incurred to-date               4,032Estimated total costs                  6,400Stone Age Construction Pte Ltd accounted for the contract using the percentage-of-completion method.Required:(a) For the year ended 2021, calculate the percentage of completion to-date, revenue recognised for the year...
Beavis Construction Company was the low bidder on a construction project to build an office building...
Beavis Construction Company was the low bidder on a construction project to build an office building for $8,000,000. The project was begun in 2017 and completed in 2019. Cost and other data are presented below: 2017 2018 2019 Costs incurred during the year $ 1,500,000 $4,500,000 $1,550,000 Estimated costs to complete 4,500,000 1,500,000 -0- Billings during the year 1,400,000 5,200,000 1,400,000 Cash collections during the year 1,000,000 4,000,000 3,000,000 Assume that Beavis recognizes revenue on this contract over time according...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT