Question

In: Operations Management

AZRB is a road bridge construction company. The company plan to build a major road bridge...

AZRB is a road bridge construction company. The company plan to build a major road bridge for its new project. Table shows the process sequence and other related data for the major road bridge development.

Table :Activities to construct the bridge, estimated time and crashing cost.

Activity

Predecessor

Time Estimates (Days)

 
 
Cost (RM per day)
 
 
Crash cost (RM per day)
 

Optimistic

Most Likely

Pessimistic

Maximum crash time (days)

a

m

b

A

-

65

73

90

100

150

6

B

A

20

27

40

80

120

6

C

A

46

50

66

110

165

10

D

B, C

33

40

50

80

120

4

E

B

15

22

35

90

135

5

F

D, E

50

71

80

130

195

3

G

D

25

40

85

100

150

5

H

F,G

15

30

45

90

145

7

  1. Develop a network diagram for the above project. Determine the critical path and minimum project completion time.
  2. Calculate the probability that the project can be completed in between 250 and 270 days.                                                                                                                        
  3. If the project has to be shortened by five (5) days, determine which activity needs to be crashed and the additional cost involved. Cost per day as well as crash cost per day were based on expected time.

Solutions

Expert Solution

a.

Below are the calculations and network diagram.

We will use below approach for calculating critical path and completion time:

Earliest Start Time (ES) = the earliest time that an activity can begin

Earliest Finish Time (EF) = the earliest time that an activity can be completed

EF = ES + duration of activity        

Latest Start Time (LS) = the latest time that an activity can begin without lengthening the minimum project duration

Latest Finish Time (LF) = the earliest time than an activity can be completed without lengthening the minimum project duration

LF = LS + duration of activity   

Duration of the project = the difference between the maximum value of the "latest finish time" of projects and the minimum value of the "earliest start time" of projects

Project duration = max(LF) - min(ES)     

Slack = the amount of time that a project can be delayed without increasing the duration of the project

Slack = LF- LS or EF - ES

Critical path is the path with Total Slack = 0

Updated calculations are below.

b.

Probability that the project can be completed in between 250 and 270 days, we will calculate z statistic for the same

z= (X- mu)/ sigma

where mu is expected completion time

sigma is standard deviation of critical path

X = 250, 270

For X=250,

z= (X- mu)/ sigma = (250-266)/ 9.30 = -1.72

Looking at z table given below, we will find probability corresponding to z value of -1.72. Look at negative z value table on left side and value for row -1.7 and column 0.02. Probability value is 0.0427

For X=270,

z= (X- mu)/ sigma = (270-266)/ 9.30 = 0.43

Looking at z table given below, we will find probability corresponding to z value of 0.43. Look at positive z value table on right side and value for row 0.4 and column 0.03. Probability value is 0.6664.

Probability that the project can be completed in between 250 and 270 days,

P (-1.72 < Z < 0.43) = 0.6664 - 0.0427 =0.6237

Hence, probability that the project can be completed in between 250 and 270 days is 62.37%

c.

Possible paths in the network with expected time are:

  • A-B-E-F-H: 74.50+28+23+69+30 = 224.50
  • A-B-D-F-H: 74.50+28+40.5+69+30= 242
  • A-C-D-F-H: 74.50+52+40.5+69+30= 266
  • A-C-D-G-H: 74.50+52+40.5+45+30= 242

Now, in order to shorten project by 5 days we will crash activities on critical path with lowest crash cost per day.

Activity D has lowest crash of RM 120 per day and maximum crash time for D is 4 days. Hence, we will first crash activity D will be crashed by 4 days and crashing cost of RM 120*4 =480.

Next activity on critical path with lowest crash cost per day is activity H with crashing cost of RM 145 per day. So, we will crash activity H by one day and crashing cost of 480+145= RM 625.

Hence, activity D by 4 days and activity H by one day will be crashed to shorten project by 5 days. Total crashing cost = RM 625.


Please give thumbs up/ likes if you find this answer helpful. Thank you!


Related Solutions

At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road...
At the beginning of 2012, Massachusetts Road Construction entered into a contract to build a road for the government. Construction will take 3 years. The following information as of December 31st, 2012 is available for the contract: Total revenue according to contract $15,000 Updated estimated cost in 2013-2014 period $7,200,000 Cost incurred during 2012 $4,800,000 Assume that the company estimates percentage complete based on costs incurred as a percentage of total estimated costs. Under the Percentage-of-Completion method, how much revenue...
Dalton Construction Co. contracted to build a bridge for $8,000,000. Construction began in 2018 and was...
Dalton Construction Co. contracted to build a bridge for $8,000,000. Construction began in 2018 and was completed in 2019. Data relating to the construction are: 2018 2019 Costs incurred during the year $2,105,600 $2,408,400 Estimated costs to complete 2,374,400 ― Dalton uses the percentage-of-completion method. Part 1 How much revenue should be reported for 2018? Part 2 Make the entry to record progress billings of $2,905,600 during 2018. (Credit account titles are automatically indented when amount is entered. Do not...
Rajbir Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2018 and was...
Rajbir Construction Co. contracted to build a bridge for $10,000,000. Construction began in 2018 and was completed in 2019. Data relating to the construction are: 2018 2019 Costs incurred during the year $3,300,000 $2,750,000 Estimated costs to complete 2,700,000 — Raj uses the percentage-of-completion method. Instructions (a) How much revenue should be reported for 2018? Show your computation. (b) Make the entry to record progress billings of $4,100,000 during 2018. (c) Make the entry to record the revenue and gross...
The municipality of a major city in Quebec is planning to build a new bridge to...
The municipality of a major city in Quebec is planning to build a new bridge to decrease the traffic load on the existing bridges connecting both sides of the city across the river. Construction is to start in 2020 and is expected to take four years at a cost of $25 million per year. After construction is completed, the cost of operation and maintenance is expected to be $2.5 million for the first year and to increase by 2.8% per...
Chapter 18 Howard Construction Co. contracted to build a bridge for $3,000,000. Construction began in 2012...
Chapter 18 Howard Construction Co. contracted to build a bridge for $3,000,000. Construction began in 2012 and was completed in 2013. Data relating to the construction are:                                                                                                  2012              2013             Costs incurred                                                     $990,000       $825,000             Estimated costs to complete                                810,000                — Howard uses the percentage-of-completion method. Instructions:         (a)           How much revenue should be reported for 2012?         (b)          Make the entry to record progress billings of $1,000,000 during 2012.         (c)            Make the entry...
The mayor of a town has proposed a plan for the construction of an adjoining bridge....
The mayor of a town has proposed a plan for the construction of an adjoining bridge. A political study took a sample of 1200 voters in the town and found that 76% of the residents favored construction. Using the data, a political strategist wants to test the claim that the percentage of residents who favor construction is above 73%. Make the decision to reject or fail to reject the null hypothesis at the 0.10 level.
The mayor of a town has proposed a plan for the construction of a new bridge....
The mayor of a town has proposed a plan for the construction of a new bridge. A political study took a sample of 1300 voters in the town and found that 66% of the residents favored construction. Using the data, a political strategist wants to test the claim that the percentage of residents who favor construction is not equal to 69%. Testing at the 0.05 level, is there enough evidence to support the strategist's claim? Step 4 of 7: Determine...
he mayor of a town has proposed a plan for the construction of an adjoining bridge....
he mayor of a town has proposed a plan for the construction of an adjoining bridge. A political study took a sample of 1000 voters in the town and found that 57% of the residents favored construction. Using the data, a political strategist wants to test the claim that the percentage of residents who favor construction is above 53%. Make the decision to reject or fail to reject the null hypothesis at the 0.20 level.
QUESTION 1: CONSTRUCTION/CIVIL FRAUD A major infrastructure company, Mega Construction Corp. had been awarded a road...
QUESTION 1: CONSTRUCTION/CIVIL FRAUD A major infrastructure company, Mega Construction Corp. had been awarded a road construction contract by the government. For execution of the project, the company had sub-divided the geographies and execution areas and invited bids for the sub-contracting. The company had publicized a whistle-blower policy and received a complaint from one of the bidders about possible collusion between certain bidders. The matter was sought to be investigated by the management of the company. As the company’s fraud...
Triad Corporation has established a joint venture with Tobacco Road Construction, Inc., to build a toll...
Triad Corporation has established a joint venture with Tobacco Road Construction, Inc., to build a toll road in North Carolina. The initial investment in paving equipment is $81.2 million. The equipment will be fully depreciated using the straight-line method over its economic life of five years. Earnings before interest, taxes, and depreciation collected from the toll road are projected to be $12.3 million per annum for 20 years starting from the end of the first year. The corporate tax rate...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT