In: Operations Management
AZRB is a road bridge construction company. The company plan to build a major road bridge for its new project. Table shows the process sequence and other related data for the major road bridge development.
Table :Activities to construct the bridge, estimated time and crashing cost.
Activity |
Predecessor |
Time Estimates (Days) |
Cost (RM per day) |
Crash cost (RM per day) |
|
||
Optimistic |
Most Likely |
Pessimistic |
Maximum crash time (days) |
||||
a |
m |
b |
|||||
A |
- |
65 |
73 |
90 |
100 |
150 |
6 |
B |
A |
20 |
27 |
40 |
80 |
120 |
6 |
C |
A |
46 |
50 |
66 |
110 |
165 |
10 |
D |
B, C |
33 |
40 |
50 |
80 |
120 |
4 |
E |
B |
15 |
22 |
35 |
90 |
135 |
5 |
F |
D, E |
50 |
71 |
80 |
130 |
195 |
3 |
G |
D |
25 |
40 |
85 |
100 |
150 |
5 |
H |
F,G |
15 |
30 |
45 |
90 |
145 |
7 |
a.
Below are the calculations and network diagram.
We will use below approach for calculating critical path and completion time:
Earliest Start Time (ES) = the earliest time that an activity can begin
Earliest Finish Time (EF) = the earliest time that an activity can be completed
EF = ES + duration of activity
Latest Start Time (LS) = the latest time that an activity can begin without lengthening the minimum project duration
Latest Finish Time (LF) = the earliest time than an activity can be completed without lengthening the minimum project duration
LF = LS + duration of activity
Duration of the project = the difference between the maximum value of the "latest finish time" of projects and the minimum value of the "earliest start time" of projects
Project duration = max(LF) - min(ES)
Slack = the amount of time that a project can be delayed without increasing the duration of the project
Slack = LF- LS or EF - ES
Critical path is the path with Total Slack = 0
Updated calculations are below.
b.
Probability that the project can be completed in between 250 and 270 days, we will calculate z statistic for the same
z= (X- mu)/ sigma
where mu is expected completion time
sigma is standard deviation of critical path
X = 250, 270
For X=250,
z= (X- mu)/ sigma = (250-266)/ 9.30 = -1.72
Looking at z table given below, we will find probability corresponding to z value of -1.72. Look at negative z value table on left side and value for row -1.7 and column 0.02. Probability value is 0.0427
For X=270,
z= (X- mu)/ sigma = (270-266)/ 9.30 = 0.43
Looking at z table given below, we will find probability corresponding to z value of 0.43. Look at positive z value table on right side and value for row 0.4 and column 0.03. Probability value is 0.6664.
Probability that the project can be completed in between 250 and 270 days,
P (-1.72 < Z < 0.43) = 0.6664 - 0.0427 =0.6237
Hence, probability that the project can be completed in between 250 and 270 days is 62.37%
c.
Possible paths in the network with expected time are:
Now, in order to shorten project by 5 days we will crash activities on critical path with lowest crash cost per day.
Activity D has lowest crash of RM 120 per day and maximum crash time for D is 4 days. Hence, we will first crash activity D will be crashed by 4 days and crashing cost of RM 120*4 =480.
Next activity on critical path with lowest crash cost per day is activity H with crashing cost of RM 145 per day. So, we will crash activity H by one day and crashing cost of 480+145= RM 625.
Hence, activity D by 4 days and activity H by one day will be crashed to shorten project by 5 days. Total crashing cost = RM 625.
Please give thumbs up/ likes if you find this answer helpful. Thank
you!