Question

In: Accounting

On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400....

On February 1, 2020, Joe agreed to construct a building at a contract price of $17,400. Joe estimated total construction costs would be $12,000 and the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:

                                                                             2020                       2021                      2022       

Total costs incurred to date                                        $4,500                    $7,920                  $13,800

Estimated costs to complete                                         7,500                      5,280                     -0-

Customer billings to date                                             6,600                    12,000                    16,800

Collections to date                                                      6,000                    10,500                    16,500

Instructions:

  1. Fill in the correct amounts on the following schedule. For percentage-of-completion accounting and for completed-contract accounting, show the gross profit that should be recorded for 2020, 2021, and 2022.

                        Percentage-of-Completion                                   Completed-Contract

                                    Gross Profit                                                   Gross Profit

            2020               ___________                            2020              ___________

            2021               ___________                            2021              ___________                 

            2022               ___________                            2022              ___________                 

  1. Make the journal entries to record construction expense, construction revenue, and gross profit for the second year, 2021.
  2. At the end of the 2021, the second year of construction, will the company report a current asset or a current liability? And how much?

Solutions

Expert Solution

a. The completed contract method is an accounting technique that lets taxpayers and businesses postpone the reporting of income and expenses, until after a contract is completed, even if cash payments were issued or received during a contract period. This accounting method is frequently used in the construction industry or other sectors that tend to involve long-term contracts. So all the profit or loss will be recognized in the year of completion of the project

The percentage of completion method of revenue recognition is a concept in accounting that refers to a method by which a business recognizes revenue on an ongoing basis depending on the stages of a project’s completion. In other words, the percentage of completion method is used for longer-term projects and recognizes revenue and expenses as a percentage of the project’s completion during the period.

Computation of Gross Profit under percentage of completion method:

Amount in $
Particulars 2020 2021 2022
Cost incurred during the year A                          4,500                                          3,420                          5,880
Cost incurred during previous year/years B                                 -                                            4,500                          7,920
Estimated cost still to be incurred C                          7,500                                          5,280                                 -  
Total Cost D=A+B+C                        12,000                                        13,200                        13,800
Percentage Completion till date E=(A+B)/D 37.50% 60.00% 100.00%
Percentage work already completed till last year F 0 37.50% 60.00%
Percentage revenue to be considered this year G=E-F 37.50% 22.50% 40.00%
Revenue $                          6,525                                          3,915                          6,960
H=17400*G (17,400*37.5%) (17,400*22.5%) (17,400*40%)
Expenses $                          4,500                                          3,420                          5,880
Gross Profit                          2,025                                              495                          1,080

Therefore,

Year Perecentage Completion Method
Gross Profit/(Loss) Recognized
$
2020                                                        2,025
2021                                                            495
2022                                                        1,080
Total Project profit (Loss)                                                        3,600
Year Completed Contract Methd
Gross Profit/(Loss) Recognized
$
2020 -
2021 -
2022                                                 3,600
($17,400-$13,800)
Total Project profit (Loss)                                                 3,600

b.

Journal Entries under the percentage of completion method for the Year 2021:

Account Titles and Explanations Debit Credit
CIP (construction in progress) $3,420
        Cash/ Accounts Payable $3,420
(Being entry made for recording cost incurred)
Construction Expense $3,420
Construction in progress (CIP) $495
          Construction Revenue $3,915
(Being entry made for recording revenue)

c. Reporting of current asset or a current liability by the company under the percentage of completion method:

Particulars 2021
$
Revenue Recognized till date                10,440
Billings till date 12,000
Billings in excess of Cost/ (Cost in excess of billing)                (1,560)
Balance Sheet (Partial) 2021
Current Assets:
Cost in excess of billing                         -  
Current liabilities:
Billings in excess of Cost                  1,560

Related Solutions

On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $35,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows:                                                     2020             2021           2022 Total costs incurred to date        $8,000        $10,000         $22,000 Estimated costs to complete      12,000          6,000            -0- Customer billings to date           8,000          24,000         29,000 Collections to date                     4,000           14,000         25,000 The journal entry to record Billings on Construction in Process in 2021 has the amount of _________.
On February 1, 2020, a company agreed to construct a building at a contract price of...
On February 1, 2020, a company agreed to construct a building at a contract price of $42,000. The company estimated the project would be finished in 2022. Information relating to the costs and billings for this contract is as follows: 2020 2021 2022 Total costs incurred to date $8,000 $10,000 $22,000 Estimated costs to complete 12,000 6,000 -0- Customer billings to date 9,000 21,000 29,000 Collections to date 4,000 14,000 25,000 If the company uses the percentage-of-completion method, an inventory/current...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marcos Contractors agreed to construct a building at a contract price of $3,000,000. Marcos estimated total construction costs would be $2,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: ? 2010?? 2011?? 2012? Total costs incurred to date?$ 750,000?$1,320,000?$2,300,000 Estimated costs to complete?1,250,000? 880,000?-0- Customer billings to date?1,100,000? 2,000,000?3,000,000 Collections to date?1,000,000? 1,750,000?2,950,000 Instructions 1. Fill in the correct amounts on the following...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of...
On February 1, 2010, Marsh Contractors agreed to construct a building at a contract price of $5,800,000. Marsh estimated total construction costs would be $4,000,000 and the project would be finished in 2012. Information relating to the costs and billings for this contract is as follows: 2014 2015 2016 Total costs incurred to date $1,500,000 $2,640,000 $4,600,000 Estimated costs to complete 2,500,000 1,760,000 -0- Customer billings to date 2,200,000 4,000,000 5,600,000 Collections to date 2,000,000 3,500,000 5,500,000 Instructions Fill in...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of...
On January 1, 2018, Grumpy Contractors agreed to construct a building at a contract price of $5,000,000. Grumpy estimates that the project will be finished in 2020. Information related to the costs and billings for this contract are as follows: 2018 2019 2020 Total costs incurred to date $1,500,000 $3,300,000 $4,400,000 Estimated costs to complete 2,500,000 1,000,000 -0- Customer billings to date 1,200,000 2,700,000 4,400,000 Collections to date 1,000,000 2,500,000 4,400,000 Instructions: Assuming the building was finished in 2020, calculate...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The...
In 2020 Coco Corporation signed a contract to construct a major office building for a developer.  The construction is expected to take 3 years.  The contract price is $50 million.  The actual costs incurred each year, the estimated costs of completing the project as of the end of each year, the progress billings for each year, and the collections of those billings each year are presented in the chart below. 2020 2021 2022 Actual costs incurred during each individual year $10,000,000 15,000,000 12,500,000...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During...
Splish, Inc. began work on a $6,312,000 contract in 2020 to construct an office building. During 2020, Splish, Inc. incurred costs of $1,589,940, billed its customers for $1,156,000, and collected $894,000. At December 31, 2020, the estimated additional costs to complete the project total $3,228,060. Prepare Splish’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During...
Crane, Inc. began work on a $7,016,000 contract in 2020 to construct an office building. During 2020, Crane, Inc. incurred costs of $1,798,560, billed its customers for $1,125,000, and collected $910,000. At December 31, 2020, the estimated additional costs to complete the project total $3,197,440. Prepare Crane’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During...
Stellar, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During 2020, Stellar, Inc. incurred costs of $1,941,020, billed its customers for $1,138,000, and collected $904,000. At December 31, 2020, the estimated additional costs to complete the project total $3,304,980. Prepare Stellar’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is...
ADVERTISEMENT
ADVERTISEMENT
ADVERTISEMENT